HomeMy WebLinkAboutReso 1986-12363 Revised 2/6/86
RESOLUTION NO. 12363
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
CHULA VISTA APPROVING TENTATIVE SUBDIVISION
MAP FOR LAS BRISAS DEL MAR, CHULA VISTA TRACT
85-5
The City Council of the City of Chula Vista does hereby
resolve as follows:
WHEREAS, Pioneer Mortgage Company has submitted a
tentative subdivision map known as Las Brisas Del Mar, Chula
Vista Tract 85-5, in order to subdivide 2.34 acres into five lots
at 188 N. Del Mar Avenue in the R-1 zone, and
WHEREAS, on January 8, 1986, after a public hearing, the
Planning Commission, by a vote of 6-0 with one absent,
recommended that the City Council adopt a resolution approving
the tentative map for Las Brisas Del Mar, Chula Vista Tract 85-5,
in accordance with Resolution PCS-85-5 and adopt the Negative
Declaration issued on IS-85-12.
NOW, THEREFORE, BE IT RESOLVED that the City Council of
the City of Chula Vista does hereby approve the tentative
subdivision map for Las Brisas Del Mar, Chula Vista Tract 85-5,
subject to the following conditions:
1. The developer shall be responsible for the construction of a
modified knuckle at the intersection of Bayview and Del Mar
Avenue in accordance with Chula Vista Design Standard (6) in
conjunction with the development of units as shown on the
Tentative Map. Said construction shall include, but not be
limited to: A.C. pavement, curb, gutter and sidewalk,
relocation of an existing storm drain inlet, and a driveway
approach in accordance with CVCS 1.
2. The structural section of the private driveway shall be
designed to meet flexible pavement structural design based on
"R" Values and a minimum traffic index of 4. All onsite
paving including parking areas except those within carports
will be inspected by the Engineering Department.
The design of the structural section shall be reviewed and
approved by the Director of Public Works/City Engineer.
Private drive construction is subject to standard design
review and inspection fees.
-1-
3. Third Avenue shall be maintained at an elevation of not less
than 1.5 feet below the 100 year flood elevation to allow
emergency access during periods of flooding. This condition
applies only to Unit 2 as shown on the Tentative Map.
4. A letter of permission from the owner of the land containing
the proposed channel shall be obtained in order to drain the
property to Glover Street as proposed.
5. In conjunction with the development of Unit 2, the developer
shall be responsible for the improvement of Third Avenue as
shown on the Tentative Map. Said improvement shall include,
but not be limited to: A.C. pavement and base, monolithic
curb, gutter and sidewalk, fire hydrants, street lights,
drainage facilities, and construction of retaining walls.
6. The developer shall be responsible for the relocation of the
existing F.H. on the northeast corner of "C" Street and the
proposed Third Avenue in conjunction with the development of
Unit 2 as shown on the Tentative Map.
7. The access drive off Del Mar Avenue and Bayview Way shall be
a minimum of 22' wide in order to provide adequate access
for fire equipment.
8. Lots 1 through 4 (Unit No. 1) shall comply with the
Panhandle lot provisions of Section 19.22.150 of the
Municipal Code.
9. A copy of the CC&R's shall be submitted prior to the
approval of the Final Map. Said CC&R's shall include the
following:
(a) The installation of T.V. or radio antennas shall be
prohibited.
(b) No garage conversions shall be permitted.
(c) Statement regarding City participation and enforcement
rights in accordance with Section 18.44.010 of the
Municipal Code.
10. Prior to the approval of the final map, and in a form
acceptable to the City Attorney, the City shall receive from
the developer a metes and bounds open space easement
covering Unit No. 2 which shall preclude development of that
Unit until the Sweetwater Flood Control Channel is graded to
the satisfaction of the City Engineer. The easement shall
include an agreement by the City to extinguish the easement
by quitclaim deed to the developer at the completion of the
channel. The easement and agreement shall be recorded prior
to the recordation of Unit No. 2.
-2-
11. Note 21 on the tentative map shall be revised to explicitly
state that no development of Unit No. 2 shall occur until
the Sweetwater Flood Control Channel is graded.
12. The developer shall take such actions as deemed necessary by
the Director of Planning and City Engineer to insure that
adequate noise mitigation is provided for this development.
BE IT FURTHER RESOLVED that the City Council does hereby
find that in accordance with Negative Declaration IS-85-12, and
the findings therein, the tentative map will not have a
significant impact upon the environment, and certifies that the
Negative Declaration was prepared in accordance with the
California Environmental Quality Act of 1970, as amended.
Presented by Approved as to form by
/~eorge~Kre~pl~ Director of on, City Attorney
/ Planning
1207a
-3-
ADOPTED AND APPROVED BY THE CITY COUNCIL OF THE CITY OF
CHULA VISTA, CALIFORNIA, this 4th day of February
19 86 , by the following vote, to-wit:
AYES: Counci]members Cox, Mcgandliss, Scott, Moore, Malcolm
NAYES: Councilmembers None
ABSTAIN: Counci]members None
ABSENT: Councilmembers None
Mayo~e' City of Chula Vista
ATTEST .,.
' / City Clerk
STATE OF CALIFORNIA )
COUNTY OF SAN DIEGO ) ss.
CITY OF CHULA VISTA )
I, JENNIE M. FULASZ, CMC, CITY CLERK of the City of Chula Vista, California,
DO HEREBY CERTIFY that the above and foregoing is a full, true and correct copy of
RESOLUTION NO. 12363 ,and that the same has not been amended or repealed.
DATED
(seal) City Clerk
CC-660