HomeMy WebLinkAboutReso 2003-297RESOLUTION NO. 2003-297
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
CHULA VISTA ACCEPTING FILING OF ENGINEER'S
REPORT BY THE CITY ENGINEER ON THE COST OF
CONSTRUCTION AND SEITING AUGUST 19, 2003 AT 6:00
P.M. AS THE DATE AND TIME OF A PUBLIC HEARING ON
ASSESSMENT DISTRICT 2001-03 (D STREET)
WHEREAS, on June 18, 2002, pursuant to Chapter 27 of the Improvement Act of 1911
(th: "Block Act") and Article XIIID of the Constitution of California ("Article XIIID"), Council
adopted Resolution No. 2002-208 awarding a contract in the amount of $15,870 to Portillo
Construction for the construction of sidewalk improvements on D Street between Third Avenue
ant Landis Avenue; and
WHEREAS, on December 11, 2001, Council adopted Resolutions 2001-428, 2001-429
anc 2001-430 and approved the Preliminary Assessment Engineer's Report; and
WHEREAS, on February 26, 2003, Counc'fl held a public hearing on the D Street
sidewalk improvements wherein Council adopted Resolution No. 2002-058; which ordered the
ins-allation of improvements in accordance with Article XIIID of the California Constitution;
anC
WHEREAS, on June 18, 2002, Council adopted Resolution No. 2002-208 awarding the
contract for construction of sidewalk improvements on D Street to Portillo Concrete; and
WHEREAS, staff received a grant for Transportation Development Act (TDA) funding
from the San Diego Association of Governments (SANDAG), which funds can only be used to
fin~.nce the construction of sidewalks and design and advertising costs directly related to
sidewalk construction; and
WHEREAS, the City was able to finance $11,219.67 of the project cost from this grant,
leaving $2,950.00 in constmction costs to be assessed to the property owners; and
WHEREAS, staff has completed the accounting of the expenditures and apportionment to
pro-~erty owners as shown in the attached Engineer's Report (Exhibit "A"). This report amends
the ?reliminary Engineer's Report adopted by Council on December 11, 2001; and
WHEREAS, upon confirmation of the final assessments, property owners will have the
option of paying any portion of the assessments during the 30-day payoff period.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Chula
Vista does hereby accept the filing of the Engineer's Report on the cost of construction, a copy
of Which will be kept on file in the office of the City Clerk.
BE IT FURTHER RESOLVED that the City Council does hereby set August 19, 2003 at
6:IK~ p.m. in the City Council Chambers, City of Chula Vista, 276 Fourth Avenue, Chula Vista,
California as the date and time for the public heating on Assessment District 2001-3 (D Street).
Resolution 2003-297
Page 2
Presented by
Approved as to form by
~ lrt)~9~wanson
Engfnbering Director
Ann Moore
CityAttomey
PASSED, APPROVED, and ADOPTED by the City Council of the City of Chula Vista,
California, this 15th day of July, 2003, by the following vote:
AYES:
Councilmembers:
Davis, McCann, Rindone, Salas and Padilla
NAYS: Councilmembers: None
ABSENT: Councilmembers: None
~illa, Mayo~~
ATFEST:
Susan Bigelow, City Clerk
STATE OF CALIFORNIA )
COUNTY OF SAN DIEGO )
CITY OF CHULA VISTA )
I, Susan Bigelow, City Clerk of Chula Vista, California, do hereby certify that the foregoing
Resolution No. 2003-297 was duly passed, approved, and adopted by the City Council at a
regular meeting of the Chula Vista City Council held on the 15th day of July, 2003.
Executed this 15th day of July, 2003.
Susan Bigelow, City Clerk
ENGINEER'S REPORT
D STREET SIDEWALK IMPROVEMENTS
1911 ACT
ASSESSMENT DISTRICT
AD 2001-3
MAY 29, 2003
Backeround
D Street between Third and Fourth Avenues in Chula Vista is a residential street with an
80-foot width of right-of-way. Existing improvements include pavement and curb in
fi'ont of all properties; however, several properties do not have sidewalks. On the north
side of D Street, the only properties which do not have sidewalk improvements are a
portion of 321 D Street, as well as 317, 311 and 305 D Street. In September 2001 these
four property owners submitted a petition to the City requesting the initiation of
proceedings to form an assessment district in accordance with the Improvement Act of
1911. This district would finance the construction of the missing sidewalk improvements
on the north side of D Street.
The City currently has a policy regarding participation in 1911 Block Act proceedings.
According to this policy, the City will provide all engineering, inspection and
administrative services at no cost to the property owners. Additionally, it is the City's
responsibility to relocate all existing public improvements which would be in conflict
with the new improvements, including utilities. These costs have not been included in
the Engineer's Report, because they will not be assessed to the property owners.
Subsequent to the construction of the improvements, the City obtained funding for the
construction of the sidewalks from the San Diego Association of Governments
(SANDAG). Therefore, the only cost that will be assessed to the property owners is the
cost of constructing the driveway aprons,
Overall Design and Cost Estimate
The project area and general location of improvements are shown on the Assessment
Diagram for Assessment District 2001-3, D Street. The properties which will benefit
from these improvements and are a part of the district are as follows:
Address
317 D Street
311 D Street
305 D Street
Parcel Number
566-030-25-00
566~030-54-00
566-030-30-00
2mprovements included within this district consist of driveway aprons that provide a
-ransition between the street and the driveways. The improvements which will not be
assessed to property owners include a 5-foot wide sidewalk from the existing sidewalk
ending in fi'ont of 521 D Street to the curb return on Third Avenue north of D Street, as
well as a sidewalk ramp on the northwest comer of Third Avenue and D Street.
Originally, 321 D Street (APN 566-030-23-00) was included within the boundaries of
tfis district. However, a new driveway apron at this address was not included as part of
t~e construction work for this project, since the existing sidewalk ended east of the
2
existing driveway. Therefore, this property will not be assessed for any district costs and
will thus be excluded fi.om the district.
The total estimated construction cost was $23,233.00, including the City's share. The
mount allocated to the property owners was estimated at $19,759.00. The latter amount
was used to calculate the property owners' ballot amounts. The lowest bid for this
project was $15,870.00, as shown on Table 1. This amount was subsequently reduced to
$10,705.50, due to an adjustment in contract quantities. After subtracting the amount of
the grant received from SANDAG for sidewalk construction, the remaining amount to be
assessed to the property owners is $2950.40.
Method of ADl~ortionment
Costs must be apportioned to each property in proportion to the benefit received by that
property. In apportioning the cost of street improvements, it can generally be assumed
that the property adjacent to the improvements will receive the direct benefit. The
adjacent properties would be most likely to use the improvements, particularly with
respect to driveway aprons.
The City has obtained funding from SANDAG for most of the cost items included in the
contractor's bid, including removal and replacement of improvements, construction of a
4" PCC sidewalk and the pedestrian ramp at the comer of D Street and Third Avenue.
The only cost item that will be included in the assessment district is the 6" PCC
driveway. Based on the revised total quantity of 965.1 SF calculated by the City's
construction inspector, the total cost is $3,860.40. However, some of this amount relates
to the portion of sidewalk that runs through the driveway apron. This section was
estimated to cost $1,910.00 and was subtracted from the above figure to give a total of
$2950.40. This amount was not included in the grant and needs to be assessed to the
property owners.
The breakdown of construction costs among the three properties and the City is shown on
Table 2. For each property, the square footage of the driveway apron was individually
calculated based on both the measurements taken by the City's inspector during
construction in August 2002 and measurements made by the Assessment Engineer in
May 2003. The difference between the dimensions measured on both occasions was 0.20
feet at the most, which is within the expected accuracy of the measuring devices. The
areas calculated were then multiplied by $4.00, the unit cost for the 6" PCC driveways.
The total amount thus calculated for these costs totaled $2973.68 for all three properties.
There is a difference of $23.28 between this and $2950.40, the construction cost not
covered by the grant. Since this difference is less than one percent, it was decided that
the easiest way to reconcile these numbers would be to proportion out the difference
among the three properties.
The amounts to be assessed to the property owners based on the final construction costs
can thus be compared to the amotmts estimated in the Preliminary Engineer's Report as
follows:
Assessor's Parcel No. Preliminary Assessment Final Assessment
566-030-30-00 $6,961.00 $1,322.37
566-030-54-00 $5,850.00 $ 875.65
566-030-25-00 $5,969.00 $ 752.38
566-030-23-00 $ 979.00 $ 0
TOTAL $19,759.00 $2,950.40
The Preliminary Assessment amounts were included on the ballots submitted to the
property owners and tallied in accordance with Article XIIID of the California
Constitution. Since the Final Assessment amounts are all lower than the Preliminary
Assessment amounts, no additional ballot process is necessary.
I:~ENGINEERXASMTDIST~FINAL ENGINEER'S REPORT.DOC
4
ASSESSMENT DIAGRAM
ASSESSMENT DISTRICT 2001-3
1911 ACT IMPROVEMENT DISTRICT
CITY OF CHULA VISTA, COUNTY OF SAN DIEGO, STATE OF CALIFORNIA
300 BLOCK D STREET
305 D ST
311 D
I HEREBY CERTIFY THAT THE WITHIN MAP SHOWING
PROPOSED BOUNDARIES OF THE ASSESSMENT DISTRICT,
CITY OF CHULA VISTA, COUNTY OF SAN DIEGO, STATE OF
CALIFORNIA, WAS APPROVED BY THE CITY COUNCIL OF
THE CITY AT A REGULAR MEETING THEREOF, HELD ON
THE DAY OF ,20 , BY
RESOLUTION NO.
LEGEND
PROPOSED ASSESSMENT
DISTRICT BOUNDARY
AREA OF IMPROVEMENT
CITY CLERK, CITY OF CHULA VISTA
FILED IN THE OFFICE OF THE CITY CLERK OF THE CITY OF
CHULAVISTA THIS DAY OF __, 20
RECORDED IN THE OFFICE OF THE STREET
SUPERINTENDENT OF THE CITY OF CHULA
VISTA THIS DAY OF
20
CITY CLERK, CiTY OF CHULA VISTA
FILED THIS DAY OF ,20
IN BOOK AT PAGE OF MAP OF ASSESSMEI:,IT
DISTRICTS IN THE OFFICE OF THE COUNTY RECORDER
OF THE COUNTY OF SAN DIEGO, STATE OF CALIFORNIA.
COUNTY RECORDER, COUNTY OF SAN DIEGO
STREET SUPERINTENDENT
REFERENCE IS HEREBY MADE TO THE COUNTY
OF SAN DIEGO, STATE OF CALIFORNIA ASSESSO
PARCEL MAPS FOR DETAILED DIMENSIONS OF
INDIVIDUAL PARCELS.
TABLE 1
PORTILLO CONSTRUCTION
ORIGINAL BID ON D STREET IMPROVEMENTS
4" PCC Sidewalk 1220
6" PCC Driveways 1100
Pedestrian Ramp (SDRSD G-27 1
Type A)
Remove and Replace 4" PCC 200
Slabwork
Remove and Replace 6" PCC 400
Slabwork
Remove and Replace PCC Curb 120
and Gutter (6" or 8")
TOTAL
SF $3.50 $4,270
SF $4.00 $4,400
EA $1000 $1,000
SF $5.00 $1,000
SF $5.50 $2,200
LF $25.00 $3,000
$15,870
TABLE 2
D STREET APPORTIONMENT CALCULATIONS
DRIVEWAY APRONS
305 D Street; APN 566-030-30-00
12.8'x 20.2'+26.5' = 298.9 SF
2
1.7' x 20.2' = 38.4 SF
333.2 SF
333.2 SF x $4.00/SF ~- $1332.80
311 D Street; APN 566-030-54-00
12.7' x 18.9' + 12.5' = 199.39 SF
2
1.7' x 12.5' -- 21.25 SF
222.85 SF
220.64SF x $4.00/SF = $882.56
317 D Street; APN 566-030-25-00
12.7' x 17.0' + 10.5' -- 174.63 SF
2
1.3' x 11.5' = 14.95 SF
189.58 SF x $4.00/SF
189.58 SF
$758.32
Reconciliation with Grant Funding
$1332.80
$ 882.56
$ 758.32
$2973.68
$2973.68 - $2950.40 (construction cost - grant) = $23.28
Reduction to calculated amounts: $23.28/$2973.68 = 0.007829 multiplier
305 D Street: $1322.37
307D Street: $ 875.65
311 D Street: $ 752.38
J:XENGINEER~ASMTDIST~D STREET~TABLE 2 APPORTIONMENT.DOC