REGULAR MEETING OF THE MEASURE P CITIZENS’ OVERSIGHT COMMITTEE
OF THE CITY OF CHULA VISTA
Thursday,Sept 28, 2017 Public Works Center
6:00 p.m.1800 Maxwell Road
Chula Vista, CA 91911
CALL TO ORDER
ROLL CALL:Committee Members Doyle, Firsht, Freels, Garcias, Hunter, Lengyel,
Maldonado, Prater, Robles, Sheridan, Vigilante, Voorhees, Whitsell,Ziomek and Chair Redo.
CONSENT CALENDAR
The Board/Commission will enact the Consent Calendar staff recommendations by one
motion, without discussion, unless a Board/Commission Member, a member of the public, or
staff requests that an item be removed for discussion. If you wish to speak on one of these
items, please fill out a “Request to Speak” form and submit it to the Secretary prior to the
meeting. Items pulled from the Consent Calendar will be discussed immediately following the
Consent Calendar.
1.CONSIDERATION OF EXCUSED/UNEXCUSED ABSENTEEISM
Commissioners Lengyel and Vigilante on July 27, 2017.
Staff recommendations:Excuse the absences.
2.APPROVAL OF MINUTES of July 27, 2017.
Staff recommendations:Approve the meeting minutes.
PUBLIC COMMENTS
Persons speaking during Public Comments may address the Committee on any subject matter
within the Committee’s jurisdiction that is not listed as an item on the agenda.State law
generally prohibits the Committee from discussing or taking action on any issue not included
on the agenda, but, if appropriate, the Committee may schedule the topic for future
discussion or refer the matter to staff.Comments are limited to three minutes.
STAFF PRESENTATIONS
The items listed in this section of the agenda will consist of presentations by City staff
members. No action is expected to be taken by the Committee on these items. If any member
of the public wishes to speak on any item, please fill out a “Request to Speak” form and
submit it to the Secretary prior to the meeting.
City of Chula Vista Boards & Commissions
Measure P Citizens’ Oversight Committee
Page 1 of 11
Page 2 ׀ Measure P Citizens’ Oversight Committee Agenda September 28, 2017
3.PRESENTATIONS REGARDING MEASURE P, THE TEMPORARY, TEN-YEAR
HALF-CENT SALES TAX TO FUND HIGH PRIORITY INFRASTRUCTURE NEEDS
a.FY17 Sales tax revenues and expenditures. (David Bilby, Director of Finance)
b.City Council action to approve updated budget and Infrastructure, Facilities and
Equipment Expenditure Plan. (David Bilby, Director of Finance)
4.MEASURE P PROJECT UPDATES
a.Progress report for projects completed and underway.(Rick Hopkins, Director of
Public Works, William Valle,Director of Engineering & Capital Projects,
Iracsema Quilantan, Assistant Director of Public Works )
OTHER BUSINESS
5.STAFF COMMENTS
a.Sustainability Commission Seat on COC.(Glen Googins, City Attorney)
b.Select the date of November 2017 COC meeting.(Glen Googins, City Attorney)
6.COMMITTEE MEMBERS’ COMMENTS
ADJOURNMENT
Materials provided to the Measure P Citizens’ Oversight Committee related to any open-session
item on this agenda are available for public review in the Office of the City Clerk, Chula Vista
during normal business hours.
In compliance with the
AMERICANS WITH DISABILITIES ACT
The City of Chula Vista requests individuals who require special accommodations to access,
attend, and/or participate in a City meeting, activity, or service, contact the Human Resources
Department at (619) 691-5041 (California Relay Service is available for the hearing impaired by
dialing 711) at least forty-eight hours in advance of the meeting.
Page 2 of 11
Page 3 of 11
Page 4 of 11
Page 1 | Measure P Citizens’ Oversight Committee Minutes July 28, 2017
DRAFT MINUTES
MINUTES OF A SPECIAL MEETING OF THE
MEASURE P CITIZENS’ OVERSIGHT COMMITTEE
OF THE CITY OF CHULA VISTA
Thursday, July 28, 2017 6:00 p.m.
A Special Meeting of the Measure P Citizens’ Oversight Committee of the City of Chula Vista was
called to order at 6:03 p.m. in the Public Works Center, located at 1800 Maxwell Road, Chula
Vista, California.
ROLL CALL
PRESENT: Committee Members Coleman, Doyle, Firsht, Freels, Hunter,
Maldonado (arrived at 6:07), Prater, Redo, Robles (arrived at
7:20), Sheridan, and Whitsell.
ABSENT: Committee Member Garcias, Lengyel, Vigilante, Voorhees, and
Ziomek
ALSO PRESENT: Assistant City Manager Kachadoorian, City Attorney Googins,
Director of Finance Bilby, Marketing & Communications Manager
Steinberger, Public Works Director Hopkins, Engineering &
Capital Projects Director/City Engineer Valle, Assistant Director
of Public Works Quilantan, Budget & Analysis Manager Nguyen,
and Accounting Technician Delap.
CONSENT CALENDAR
1. CONSIDERATION OF EXCUSED ABSENCE
Committee Member Maldonado and Ziomek on April 18, 2017.
2. APPROVAL OF MINUTES of March 28, 2017.
3. RESOLUTION OF THE MEASURE P CITIZENS’ OVERSIGHT COMMITTEE
SETTING THE DATE, TIME, AND LOCATION OF REGULAR MEETINGS
ACTION: Committee Member Hunter moved to approve staff’s recommendation on the
above Consent Calendar items, Committee Member Whitsell seconded the
motion, and it passed by the following vote:
Yes: 9 – Coleman, Doyle, Firsht, Freels, Hunter, Prater, Redo, Sheridan,
and Whitsell.
No: 0
Abstain: 0
Page 5 of 11
Page 2 | Measure P Citizens’ Oversight Committee Minutes July 28, 2017
Committee Member Maldonado arrived at 6:07 p.m.
PUBLIC COMMENTS
There were none.
ACTION ITEMS
4. FISCAL YEAR 2017/18 CHAIR, VICE CHAIR, AND SECOND VICE CHAIR
City Attorney Googins presented the option of voting to keep the existing Chair, Vice
Chair, and Second Vice Chair or to vote for a new Chair, Vice Chair, and Second Vice
Chair.
ACTION: Committee Member Freels moved to continue with previously selected Chair,
Vice Chair, and Second Vice Chair. Committee Member Whitsell seconded the
motion, and it passed by the following vote:
Yes: 10 – Coleman, Doyle, Firsht, Freels, Hunter, Maldonado, Prater,
Redo, Sheridan, and Whitsell.
No: 0
Abstain: 0
5. PRESENTATIONS REGARDING MEASURE P, THE TEMPORARY, TEN-YEAR
HALF-CENT SALES TAX TO FUND HIGH PRIORITY INFRASTRUCTURE NEEDS
a. Review amended Infrastructure, Facilities and Equipment Expenditure Plan which
reflects year-to-date allocations and highlights information technology and energy
efficiency programs.
Finance Director Bilby spoke regarding the changes to the Expenditure Plan, and
provided bond sale details and spending plan updates.
b. Present proposed Measure P Spending Plan which includes additional $18.7
million in bond proceeds issued by the Chula Vista Municipal Financing
Authority.
Finance Director Bilby spoke on the additional bond proceeds and where the proposed
allocations to the expenditure plan were made. The committee member’s asked questions,
and Finance Director Bilby and Public Works Director Hopkins responded. Committee
member’s provided comments.
ACTION: Committee Member Hunter moved to affirm the $18.7 million Measure P
Spending Plan is in compliance with the amended Infrastructure, Facilities and
Equipment Expenditure Plan. Committee Member Whitsell seconded the motion,
and it passed by the following vote:
Page 6 of 11
Page 3 | Measure P Citizens’ Oversight Committee Minutes July 28, 2017
Yes: 10 – Coleman, Doyle, Firsht, Freels, Hunter, Maldonado, Prater,
Redo, Sheridan, and Whitsell.
No: 0
Abstain: 0
STAFF PRESENTATIONS
6. DISCUSSION OF STAFF TIME REIMBURSEMENTS FOR ADMINISTRATION
AND DELIVERY OF MEASURE P PROJECTS
City Attorney Googins spoke regarding best practices for staff time reimbursement, and
Federal bond rules. Finance Director Bilby spoke on what the City intends to implement
for Measure P. Committee member’s asked questions, provided comments and staff
responded.
7. BROWN ACT AND ETHICS TRAINING
City Attorney Googins gave a presentation on the Brown Act and Ethics Training
requirements.
Committee Member Doyle left at 7:09 p.m.
Committee Member Robles arrived at 7:20 p.m.
8. MEASURE P PROJECT UPDATES
a. Progress report on projects completed and underway
Director of Public Works Hopkins gave a presentation on where the City is with spending
Measure P funds. Committee member’s asked questions, and staff responded.
b. Update on upcoming Measure P public events
Marketing & Communications Manager Steinberger gave a presentation on what the City
has completed and what we are looking toward completing. Committee member’s asked
questions and provided staff with comments. Staff responded to questions.
OTHER BUSINESS
9. STAFF COMMENTS
Director of Finance Bilby spoke on reinvestment of Bonds, audit item on January agenda,
and the reporting of grants and Measure P on a quarterly basis.
10. COMMITTEE MEMBERS’ COMMENTS
Committee member Hunter thanked staff; Assistant City Manager Kachadoorian thanked
the committee for providing valuable input. Committee members made comments to staff
and each other.
Page 7 of 11
Page 4 | Measure P Citizens’ Oversight Committee Minutes July 28, 2017
ADJOURNMENT
At 8:10 p.m. Chair Redo adjourned the meeting to the next Regular Meeting on September 28,
2017 at 6:00 p.m. at the Public Works Center, located at 1800 Maxwell Road, Chula Vista,
California.
____________________________________
Sandi Delap, Secretary
Page 8 of 11
Total by Major Category 10-Year Timeframe To Date Allocation Expended as of 6/30/17
Bond Sale Expenses $ - $ - $46,843
Total Bond Sale Expenses $ - $ - $46,843
Fire Stations Repairs/Replacement $22,839,549 $46,000 $10,911
Fire Response Vehicles (Apparatus) $19,847,580 $385,000 $207,619
Fire Safety Equipment $5,197,913 $183,000 $175,064
Total Fire Services $47,885,042 $614,000 $393,594
Police Response Vehicles $12,951,470 $463,940 $168,703
Public Safety Communication Systems $8,624,832 $1,414,120 $1,400,773 (Dispatch and Regional Communication Systems)
Police Facility Repairs $1,509,000 $9,000 $8,760
Total Police Services $23,085,302 $1,887,060 $1,578,236
Streets (Arterials/Collectors/Residential) $24,474,861 $363,940 $340,555
Other Public Infrast. (Storm Drains, $14,154,295 $ - $ -Drainage Systems, Sidewalks, Trees etc.)
Sports Fields and Courts $16,966,595 $85,000 $73,718
Non-Safety Vehicles (Public Works) $11,195,100 $ - $ -
Public Facilities (Senior Center, $13,100,000 $250,000 $111,901Recreation Centers, Libraries, Living Coast Discovery Center, Public Works Center, etc.)
Trac Signal Systems $7,000,000 $ - $ -
Park Infrastructure (Playground $7,682,740 $ - $ -Equipment, Gazebos, Restrooms, Benches, Parking, etc. )
Citywide Network Replacement $2,045,000 $ - $ -
Citywide Telecommunications $2,000,000 $ - $ -
Total Infrastructure $98,618,591 $698,940 $526,174
Total Proposed Allocations $169,588,935 $3,200,000 $2,544,848
42% allocated to Public Safety and 58% allocated to Citywide Infrastructure.
Actual allocations to specic projects will be brought forward as part of the annual budget with the intent to allocate resources in the major categories noted above.
To Date Allocation reects City Council approved allocations and amendments through 03/23/2017. (Resolution #2016-263 approved on 12/06/2016 and Resolution #2017-028 approved on 02/07/2017)
Expended To Date includes actual payments made from the Measure P Fund.
FY17 Revenue receipts totaled $2,859,862, allocation adjustments for shortfall will be made in FY18.
Measure P
Citywide Infrastructure, Facilities and Equipment Expenditure Plan
Half-cent Sales Tax Revenues over 10-year period
NOTES:
City of Chula Vista
Measure P
Your InfrastructureSales Tax at Work
Page 9 of 11
Measure P – Tennis and Basketball Court Resurfacing
Bid Awarded to Sequoia Surfacing & Engineering September 2017 in the amount of $174,200;
Estimated Completion Date: Winter 2017
PARK NAME ADDRESS TENNIS
BASKETBALL
FULL HALF
Heritage 1381 E. Palomar St. 1 2
Santa Cora 1365 Santa Cora Ave. 1 1
Santa Venetia 1500 Magdalena Ave. 2
All Seasons 1825 Magdalena Ave. 1
Windingwalk 1675 Exploration Falls Dr. 1 1
Veterans 785 E. Palomar St. 1 1
Horizon 970 E. Palomar St. 1
Terra Nova 450 Hidden Vista Dr. 2 1
Montevalle 840 Duncan Ranch Rd. 2
Mt. San Miguel 2335 Paseo Veracruz 1 1
Mt. Hawk 1475 Lake Crest Dr. 1
Salt Creek 2710 Otay Lakes Rd. 2
Mackenzie Creek 2775 Mackenzie Creek Rd. 2
Sunridge 952 Beechglen Dr. 1
Marisol 916 Rancho Del Rey Pkwy 2
Explorer Rancho Del Rey Pkwy/Norella St. 1
Eucalyptus Fourth Ave. / C St. 1
Valle Lindo 545 Sequoia Dr. 1
Lauderbach 333 Oxford St. 1
Los Ninos 150 Teal St. 1
SDG&E West 1450 Hilltop Dr. 1
Harborside 670 Oxford St. 2
Connoley 1559 Connoley Ave. 1
Total resurface count Tennis B/Ball Full Half
11 21 5
Page 10 of 11
•Chula Vista Civic Center – 34 —Fleet – 18 chargers—Employees – 16 chargers—$0 – disadvantaged community•Chula Vista Public Works – 37 —Fleet – 24 chargers —Employees – 13 chargers—$23,310 ($630 per charger)•Chula Vista Police Department – 52 —Fleet – 35 chargers —Employees – 17 chargers—$32,760 ($630 per charger)•Total: $56,030 (avg. $456 per charger) City of Chula Vista EV Charging – 123 A collaborative process with City staff to site chargers in the most optimum locations.Page 11 of 11
Project Status Updates
Measure P - In DroLress
Updated 09/28/2017 Page 1 of 3
F
Measure P
Category
CIP #
Facility (Project)
Description
Status
Allocation
Est. Completion Date
Public Safety Vehicles
Public Safety Vehicles
INA
I Fire Vehicles
Fire Vehicles In Progress $ 2,115,680
Winter 2017
Public Safety Vehicles
INA
I Police Vehicles
Police Vehicles lin Progress $ 2,262,700
lWinter 2017
Non -Safety City Vehicles
Non -Safety City Vehicles
NA
Non -Safety City Vehicles
Public Services Fleet and Public Works Equipment
In Progress
$ 2,818,000
Summer 2018
Contracted with SDG&E for 123
Electric Vehicle (EV) Chargers. List
of EV Charger locations attached.
Replacement of fuel stations
anticipted to be completed by
Non -Safety City Vehicles
IGG235
Non -Safety City Vehicles
Fleet Infrastructure (Replacement of fuel stations)
Design Phase
$ 1,000,000
Summer 2018
Fire Equipment
Breathing Apparatus was
purchased using FEMA Grant
Funds, however other fire
equipment is anticipated by Fall
Fire Equipment
NA
Fire Equipment
Rescue airbag replacement, radios, etc.
In Progress
$ 1,385,000
2018
Public Safety Buildings
Public Safety_Mclings _
GG232 _
Police Facility Repairs
Replacement of bulletproof glass in jail cell
Completed-
$ 9,000 Completed
Public Safety Buildings
GG232
Police Facility Repairs
Building Automation Systems (BAS)
_ _-
Design Phase 1 of 3 $ 500,000 Summer 2018
Public Safety Buildings
GG232
Police Facility Repairs
Fire Protection System
Design Phase 1 of 3 $ 110,000 Summer 2018
Public Safety Buildings
GG232
Police Facility Repairs
Electrical Service & Distribution (VFD)
Design Phase 1 of 3 $ 350,000 Summer 2018
Completed emergency
replacement of Turbocor Unit 1
Public Safety Buildings
GG232
Police Facility Repairs
Turbocor HVAC
In Progress $ 40,000 September 2017.
Public Safety Buildings
GG232
Police Facility Repairs
Various energy efficiency projects
In Progress Phase 1 $ 500,000 Summer 2018
GG229/
Fire Station 5: Secure properties, design and
Public Safety Buildings
GG230
Fire Stations Repairs/Replacements
construct
RFQ/Consultant /RFQ Design $ 6,523,000 Summer 2020
GG229/
Fire Station 9: Secure properties, design and
Public Safety Buildings
GG230
Fire Stations Repairs/Replacements
construct
RFQ/Consultant /RFQ Design $ 6,523,000 Summer 2020
Infrastructure
Irrigation and controller changeover at lighted
Infrastructure
NA
Sports Courts and Fields
Fields (5 Parks) _
Construction
$ 85,000
Winter 2017
Irrigation and controller changeover Citywide
Infrastructure
PR327
Sports Courts and Fields
sports fields
Design Phase
$ 2,000,000
Fall 2019
Sport complex amenities: multipurpose fields,
Infrastructure
PR327
Sports Courts and Fields
bleachers, handrails
Design Phase
$ 1,500,000
Spring 2020
Winter 2017. List of court
Infrastructure
PR327
Sports Courts and Fields
Resurfacing 38 courts Citywide
Award
$ 200,000
locations attached.
Updated 09/28/2017 Page 1 of 3
Updated 09/28/2017 Page 2 of 3
Measure P
Category
CIP #
Facility (Project)
Description
Status
Allocation
Est. Completion Date
Infrastructure
PR327
Sports Courts and Fields
Rohr Park: Reconstruction of Basketball Courts
Design Phase
$ 300,000
Fall 2019
Various energy efficiency projects. Citywide sports
Infrastructure
NA
Sports Courts and Fields
courts and fields lighting.
Effort has not commenced
$ 500,000
Summer 2020
Parkway - Replacement of Pool Decking and
Infrastructure
GG228
Park Infrastructure
interior and exterior wall repairs and painting.
Completed
$ 250,000
Completed
Replacement of Citywide playgrounds and resilient
Infrastructure
PR326
Park Infrastructure
surfacing
Design Phase
$ 1,500,000
Winter 2019
Infrastructure
PR326 JPark
Infrastructure
Smart controllers, irrigation, drainage Citywide
Design Phase
$ 2,000,000
Fall 2019
Park asset replacements: barbeque grills, benches,
Infrastructure
PR326 I
Park Infrastructure
drinking fountains, picnic tables, lights
Effort has not commenced
$ 500,000
Summer 2018
Path/walkway repairs and ADA access Citywide
Infrastructure
PR326
Park Infrastructure
parks and parking lots
Design Phase
$ 1,000,000
Spring 2019
Various energy efficiency projects. Citywide park
Infrastructure
NA
Park Infrastructure
pathway lighting.
Effort has not commenced
$ 500,000
Summer 2020
Pavement rehabilitation on various streets based
Completed Floyd Avenue in
on recommendations from City's Pavement
January 2017.
STL421/S
Management System for streets with pavement
Remaining streets estimated to
Infrastructure
TL427
Street Pavement
condition index (PCI) ranging from 0-25
Design Phase 1 of 2
$ 15,882,566
be completed by Summer 2018.
Infrastructure
TF408 ITraffic
Signal System-Fiber Network
Traffic signal replacements and improvements
Design Phase 1
$ 3,000,000
Summer 2018
Rehabilitation of aged Corrugated Metal Pipe
Other Infrastructure - CMP
(CMP) and other storm related repairs outside
Infrastructure
DR209
Rehabilitation Outside ROW
ROW
Design Phase 1 of 2
$ 6,760,000
Summer 2018
Perform drainage infrastructure assessments
Other Infrastructure - Drainage Pipe
Citywide of approximately 28,5000 LF of CMP
Infrastructure
DR210
Assessment Outside ROW
outside ROW
Awarded
$ 140,000
Winter 2017
Replace sidewalk damaged at various locations
Other Infrastructure -Sidewalk
based on recommendations from the Pedestrian
Infrastructure
STL428
Replacement Citywide
Connectivity Plan
Awarded Phase 1
$ 2,500,000
ISummer 2018
Police Equipment and
Capital
Lease Payments
System installed and went live
Police Communications &
Police Communications & Dispatch
July 2017. Debt Service payments
Dispatch Systems
NA
Systems
CAD Replacement
Completed
$ 371,159
will continue through FY2026-27.
Regional
Equipment purchase complete.
Communications Systems
Regional Communications Systems
Debt service payments will
(RCS)
NA
(RCS)
Portable and mobile radios
Completed
$ 1,931,460
continue through FY2026-27.
Debt Service payments will
Fire Response Vehicles
NA
Fire Response Vehicles
Pumper, Fire Engines, Ladder Truck Leases
Completed
$ 244,400
continue through FY2026-27.
Public Facilities
Civic Center Library and South Chula
Civic Center Library: Foyer bathroom remodel for
Public Facilities
GG231
Vista Library
ADA compliance
Bidding
$ 250,000
Winter 2017
Civic Center Library and South Chula
Civic Center Library: Adult and Children restrooms
Public Facilities
GG231
Vista Library
(4) remodel for ADA compliance
Design Phase
$ 500,000
Fall 2018
Civic Center Library and South Chula
Civic Center Library: Roof replacement and
Public Facilities
GG231
Vista Library
exterior stucco repairs
Design Phase
$ 550,000
Summer 2019
Updated 09/28/2017 Page 2 of 3
TOTAL PROJECT EXPENDITURES $ 82,445,965
In Progress
Completed
Updated 09/28/2017 Page 3 of 3
Measure P
Category
CIP #
Facility (Project)
Description
Status
Allocation
Est. Completion Date
Civic Center Library and South Chula
Public Facilities
GG231
Vista Library
South Chula Vista Library: Flooring
Design Phase
$ 300,000
Winter 2018
Civic Center Library and South Chula
Civic Center Library: Upgrades to electrical,
Public Facilities
GG231
Vista Library
lighting, HVAC
Design Phase 1 of 3
$ 900,000
Summer 2018
Civic Center Library and South Chula
South Chula Vista Library: Upgrades to electrical,
Public Facilities
GG231
Vista Library
HVAC
Design Phase 1 of 3
$ 500,000
Summer 2018
I
Loma Verde Recreation Center: Pool Plaster, Pool
Public Facilities
GG233
Recreation and Senior Center Repairs
Deck, pump and equipment
Design Phase
$ 600,000
Fall 2019
Loma Verde Recreation Center: Upgrades to
Public Facilities
GG233
Recreation and Senior Center Repairs
electrical, roof, exterior stucco, painting
Design Phase
$ 750,000
Fall 2019
Loma Verde Recreation Center: Replace
Public Facilities
GG233
Recreation and Senior Center Repairs
gymnasium flooring
Design Phase
$ 100,000
Spring 2018
Public Facilities
GG233
Recreation and Senior Center Repairs
Norman Park Center: Kitchen remodel
Design Phase
$ 100,000
Summer 2018
Public Facilities
GG233
Recreation and Senior Center Repairs
Norman Park Center: Women's restroom remodel
Design Phase
$ 250,000
Summer 2018
Public Facilities
GG233
Recreation and Senior Center Repairs
Norman Park Center: Flooring, decking, drainage
Design Phase
$ 550,000
Summer 2018
Women's Club: Upgrades to electrical, HVAC,
Public Facilities
GG233
Recreation and Senior Center Repairs
plumbing, roof
Design Phase 1 of 3
$ 400,000
Summer 2018
Energy efficiency projects: Recreation and Senior
Public Facilities
GG233
Recreation and Senior Center Repairs
Center
Design Phase
$ 2,250,000
Fall 2019
Animal Care Facility: electrical, HVAC, plumbing,
Public Facilities
GG234
Other Public Buildings
roofing other structures, trailer replacement
Effort has not commenced
$ 500,000
Summer 2020
Living Coast Discovery Center: alarm systems,
septic tank, decking and rail supports, sliding
doors, exterior retaining wall repair,
interior/exterior lighting, electrical, HVAC, roofing
Public Facilities
GG234
Other Public Buildings
and stucco repairs
Effort has not commenced
$ 1,000,000
Summer 2020
Ken Lee Building: roofing, HVAC, electrical, Fire
Public Facilities
GG234
Other Public Buildings
Protection System
Effort has not commenced
$ 250,000
Summer 2020
Public Works Corp Yard: HVAC, lighting, Building
Public Facilities
GG234 10ther
Public Buildings
Automation System, Fire Protection System
Effort has not commenced
$ 600,000
Summer 2020
Public Facilities
GG234
Other Public Buildings
Police Department: roof over dispatch
Design Phase 1 of 3
$ 250,000
Spring 2018
Building A in progress. Remaining
Civic Center buildings to be
Public Facilities
GG234
Other Public Buildings
Civic Center- Exterior wood surfaces
Bid _
$ 500,000
completed by Spring 2018
Various Energy efficiency projects: Citywide Public
Public Facilities
GG234
Other Public Buildings
Facilities
Effort has not commenced
$ 2,000,000
Spring 2020
Initial assessment completed,
TGG236
drafting RFP for network
Infrastructure
Citywide Network Replacement
Citywide network replacement
replacement 1
$ 2,045,000
Spring 2018
Infrastructure
GG237
Citywide Telecommunications
Citywide Telecommunications
Assessment in process 1
$ 2,000,000
Spring 2019
TOTAL PROJECT EXPENDITURES $ 82,445,965
In Progress
Completed
Updated 09/28/2017 Page 3 of 3
Project Status Updates
Measure P - In progress
ana►
Total infrastructure
-
^--�,... Total Completed 363,940
vn c.dn wnbuicdnc wncrdL.
GG229/
rServtce . _... . �....
RFQ/Consultant/RFQ Design ;Planned
E'stim ili diAvailab
Civil Engineering
Public Safety Buildings
GG230
I Fire Stations Repairs/Replacements
Fire Station 5: Secure properties, design and construct
Advertise Date 12/26/17
$ 6,523,000
Summer 2020
Scheduled to go to Council 11/7/17
GG229/
and contract drafting stage
Scoping/Planning in progress - no dates
Proposals received 9/20 — Next step is to
Scheduled to go to Council Dec 2017
Public Safety Buildings
GG230
Fire Stations Re airs/Re lacements
Fire Station 9: Secure roperties, desi nand construct
available atthis time.
$ 6,523,000
Summer 2020
Total Public safety Buildings S 13,046,000
,:
In'frastrittture
`., �. x�
H„111,1� .-, �,Y,
Pavement rehabilitation on various streets based on
Phase I - Planned Advertised Date: Nov -Dec
Infrastructure
STL427
Street Pavement
recommendations from City's Pavement Management
System for streets with pavement condition index (PCI)
2017
$ 9,000,000
Early Summer 2018.
Phase 11 - Planned Advertised Date: March -
Infrastructure
STL-)=
Street Pavement
ranging from 0-25
April 2018
$ 6,518,626
Late Summer 2018
Infrastructure
TF408
Traffic Signal System -Fiber Network
Traffic signal replacements and improvements
Design Phase I- To start 1st Qtr 2018
$ 3,000,000
Summer2018
Infrastructure
DR209
Other Infrastructure- CMP
Rehabilitation Outside ROW
Rehabilitation of aged Corrugated Metal Pipe (CMP) and
other storm related repairs outside ROW
Phase I -Planned Advertise Date: Nov 2017
$ 2,000,000
Early Spring 2018
Design Phase II -Advertise Date: June -July
Infrastructure
DR-)=
2018; Need CCTV (DR210)
$ 4,760,000
Late Summer 2018
Other Infrastructure - Drainage Pipe
Perform drainage infrastructure assessments Citywide
Infrastructure
DR210
Assessment Outside ROW
of approximately 28,5000 LF of CMP outside ROW
Awarded
$ 140,000
Early Spring 2018
Rep ace si ewadamaged at various locations based on
Pending Completion of Pedestrian
ISTL428
Other Infrastructure -Sidewalk
recommendations from the Pedestrian Connectivity
Connectivity Study (End of 2017)
Infrastructure
Replacement Citywide
Plan
$ 2,500,000
Summer 2018
Total infrastructure
-
^--�,... Total Completed 363,940
vn c.dn wnbuicdnc wncrdL.
mvduduie fur rvredbure r rruieccbt
rServtce . _... . �....
state M1.. ,r., .... ,�
E'stim ili diAvailab
Civil Engineering
Awarded 9/19/17
Now Available: Kimle -Horn; NV5; Rick Engineering Co. and, TY -LIN International.
Construction Mangement (Facilities
Interviews scheduled for 10/4/17
Scheduled to go to Council 11/21/17
Contract Management (Civil Projects)
Interviews completed 9/20. Negotiation
Scheduled to go to Council 11/7/17
and contract drafting stage
Intelligent Transportation Systems
Proposals received 9/20 — Next step is to
Scheduled to go to Council Dec 2017
Consultant (Traffic Engineering)
review proposals and determine short
list for interviews
Design Build Construction Teams
SOQs received 9/14/17. Meridian
Selection committee meeting scheduled for 10/5/17 (council approval not required)
Consultant currently evaluating.