HomeMy WebLinkAboutReso 1914-8-H RESOLUTION #8-H
Original Resolution Missing
Excerpt from minutes of Board of Trustees Meeting of
April 16, 1914
On motion duly seconded, the following Resolution was
adopted:
Whereas, the C.L.Hyde Construction Company has been
awarded two certain contracts for the grading and surfacing
of certain streets in the City of Chula Vista dated
respectively, February 3, 1914, and April 16, 1914, and
whereas by reason of the fact that said Construction Company,
has been delayed and hindered in the performance of said
contracts by reason of the failure of the San Diego &
Southeastern Tailway Company, to move its poles from certain
of said streets to be so improved, and by reason of the
failure of the Sweetwater Water Company and the San Diego
Consolidated Gas & Electric Company, to lower their pipes
and mains in certain of said streets, which lowering is
necessary in order to permit the performance and completion
of said work; and whereas the said Construction Company
was compelled to remove a portion of its grading outfit
from said work to other work on the 27th day of March, 1914;
and whereas said poles have not yet been removed from said
streets and said pipes and mains have not yet been lowered
therein, so as to permit the working of said streets under
said contract;
Now therefore, be it resolved that the time fixed
in and by said contracts for the performance and completion
of the said work is hereby extended for such length of time
as shall correspond with the length of time that said Hyde
Construction Company has so unavoidably and without fault on
its part been delayed in the completion of said work by
reason of the failure of said companies as aforesaid to
remove their poles and pipes and mains from said streets
so as to permit the further work and completion of said
roads under said contract; such extension of time not to
exceed however the period of forty days in all. The Resolution
is adopted, all voting aye.