HomeMy WebLinkAboutAgenda Statement 1984/08/14 Item 8 • COUNCIL AGENDA STATEMENT
Item 8
Meeting Date 8/14/84
ITEM TITLE: Resolution //7 7 Accepting the work on the renovation of
the Park Way Gym and Pool
SUBMITTED BY: Building & Housing Directo _ . s Vote: Yes No )
REVIEWED BY: City Manager
On November 22, 1983, the City Council passed Resolution 11468 awarding a
contract to O'Neill and Perry Construction Company in the amount of $295,804
to renovate the Park Way Gym and Pool. The work has been completed and
inspected by the Building Department and found to be satisfactory.
RECOMMENDATION: That Council approve this resolution accepting the
renovation of the Park Way Gym and Pool .
BOARDS/COMMISSIONS RECOMMENDATION: Not applicable.
DISCUSSION:
On November 22, 1983, the City Council passed Resolution 11468 awarding a
contract to O'Neill and Perry Construction Company in the amount of $295,804
to renovate the Park Way Gym and Pool . The contract was amended on
February 7, 1984, by Resolution 11535 authorizing Change Orders 1 , 2, 3, 4, 6
and 7 and again on March 20, 1984, by Resolution 11571 authorizing Change
Orders 8 and 9. The contract was once again amended on June 6, 1984, by
Resolution 11642 authorizing Change Order 10. The majority of these change
orders were necessitated by severe moisture damage to concrete slabs and metal
wall studs which did not become apparent until after the renovation commenced
on the thirty-year-old building.
All work has been performed and found to be in accordance with the plans and
specifications and to the satisfaction of the Director of Building and Housing.
FINANCIAL STATEMENT
Authorized Expenditure
Contract Amount $295,804
Contingencies 29,580
TOTAL $325,384
Actual Construction Cost
Original Contract $295,804
Field Change Order #1 through #4 2,737
Change Orders #1 through #10 38,954
Credit - 3,075
TOTAL $334,420
FISCAL IMPACT: Life expectancy of renovation 20 to 30 years.