HomeMy WebLinkAboutAgenda Statement 1984/05/15 Item 11 COUNCIL AGENDA STATEMENT
Item 11
Meeting Date 5/15/84
ITEM TITLE: Resolution `/ ' Approving agreement between the City of
Chula Vista and the County of San Diego for construction and
operation of Chula Vista Bayfront Station
SUBMITTED BY: City Engineer (p0,/ (4/5ths Vote: Yes No X )
REVIEWED BY: City Manager 9/
A tri-party agreement among the City of Chula Vista, the Metropolitan Transit
Development Board (MTDB) and the County of San Diego for development of the
Chula Vista "E" Street Trolley Station (hereinafter referred to as the Chula
Vista Bayfront Station) was approved by the MTDB on January 24, 1983, by the
City of Chula Vista on January 25, 1983, and by the County of San Diego on
March 1 , 1983. This tri-party agreement is a cooperative effort that
previously defines issues pertaining to planning of the station. This new
agreement between the City of Chula Vista and the County of San Diego
addresses issues pertaining to station construction, maintenance and
operation. This agenda statement will discuss:
1 . A summary of the Bayfront Station planning process; and
2. Specific components of the agreement between the City of Chula Vista and
County of San Diego.
RECOMMENDATION: That Council approve agreement between the City of Chula
Vista and County of San Diego for construction and operation of the Chula
Vista Bayfront Station.
BOARDS/COMMISSIONS RECOMMENDATION: Not Applicable.
DISCUSSION:
1 . BACKGROUND/PLANNING PROCESS
In March 1983, the County Board of Supervisors entered into an agreement
with the City of Chula Vista and MTDB for development of the Chula Vista
Bayfront trolley station. The County approved $1 .2 million for planning
and construction of the station. The consulting firm of Sedway Cooke and
Associates was selected by the County of San Diego to undertake the
planning study for the station. A Project Steering Committee was also
established to review, evaluate, and provide input into the planning
process. The Steering Committee consists of representatives from the City
of Chula Vista, County of San Diego, and the MTDB. The consultant started
work on the study in June 1983. The first part of the study involved
Page 2, Item 11
Meeting Date 5/15/84
looking at options for station location both on the north and south sides
of "E" Street. In August 1983, the Steering Committee selected the south
side of "E" Street as the preferred location of the station. A draft
report was completed in November 1983, and a final report was issued in
February 1984.
The consultant report included the following findings, conclusions, and
recommendations relative to the project:
- A station location mid-block between "E" and "F" Street.
- Vehicular access from both "E" Street and Woodlawn Avenue.
- Parking for approximately 130 cars should be provided as part of the
initial development program.
- A phased parking area expansion program should be pursued.
- A total of 4.146 acres of land is recommended for acquisition
including the insurance stand lot, the gas station, vacant lot on "E"
Street, the bowling alley, and a portion of the City Public Works
Yard.
- A joint development program with the Chamber of Commerce is
compatible with trolley operations and site constraints.
- Although not all of the 4.146 acres is necessary for initial
development of the trolley station, the entire area is necessary to
accommodate the longer-term parking requirements that the station is
expected to generate.
- Total acquisition of this land will ensure that sufficient land is
acquired to meet the long term parking needs and guarantee the
necessary access to both "E" Street and Woodlawn Avenue to minimize
circulation conflicts.
The cost to develop the station as proposed by the consultant was
estimated at approximately $4.5 million. This cost included immediate
demolition of the bowling alley, and construction of the station. Since
the County of San Diego had allocated $1 .2 million to this project,
developing the Bayfront Station as proposed by the consultant would result
in a project shortfall of approximately $3.4 million. For the past few
months, the staffs of the City of Chula Vista and County of San Diego have
been investigating various financing and planning options that would
permit development of the station. These options included: modifying the
scope of the project; and looking at numerous alternatives for financing
the station, such as participation from MTDB, Federal funds, and issuing
certificates of participation.
11
Page 3, Item
Meeting Date 5/15/84
The staffs reached consensus first on the issue of project scope. It was
agreed that the key element for a south side of "E" Street location was
acquisiton of the land recommended by the consultant. The cost of the
land acquisition is estimated at $2.2 million, based on an appraisal by
Hilliard, Lipman and Associates. Approximately $1 million of this $2.2
million is for acquisition of the bowling alley. Staff evaluated the
possibility of not purchasing all the land as recommended by the
consultant, but rather working out a joint parking arrangement with the
bowling alley. It was concluded, however, that such a joint arrangement
might be feasible initially, but not indefinitely due to projected parking
demand at the station. Therefore, acquisition of the property as
recommended by the consultant is a necessary component of the Bayfront
Station development at this site.
The staffs then investigated ways to finance the station. It was
concluded that a phased development program would be feasible. Under this
approach, the property recommended for acquisition by the consultant would
be acquired and a station would be built; however, the bowling alley and
the gas station would remain in operation for some time into the future
until it becomes necessary to expand parking at the site. This phased
approach has two main advantages: it reduces the initial project cost
from an estimated $4.5 million to approximately $3.4 million; and revenue
from bowling alley and gas station leases would generate approximately
$180,000 annually ($130,000 from the bowling alley and $54,000 from the
gas station). This development proposal was presented to and approved by
the Steering Committee on April 13, 1984. Following is a summary of the
major components of the proposal :
A. Development Plan for Station
1 . A development plan for the station was presented to the
Committee. This plan has the following major changes from the
plan developed by the consultant:
a. The bowling alley and the gas station can continue
operation until such time as it becomes necessary to expand
the area for additional on-site parking.
b. Bus access to the station will be off Woodlawn Avenue only
instead of "E" Street and Woodlawn Avenue.
c. The station has been located closer to "E" Street rather
than mid-block between "E" and "F" Street.
2. The Bayfront Station development plan has three phases, each
related to parking demand:
a. Phase I: Acquisition of five parcels. Station development
in the SD&AE right-of-way. Parking shared with the bowling
alley.
/2-- //� z2
Page 4, Item 11
Meeting Date 5/15/84
b. Phase II (1988-1990): Gas station removed for additional
parking/site development.
c. Phase III (1992-1994): Bowling Alley removed for
additional parking/site development.
Exhibit 1 shows projected parking demand at the station.
Initial peak parking demand at the station is estimated at 135
spaces. This demand is projected to increase to 175 by 1990,
250 by 1994, and 370 in 2000. Parking demand estimates include
demand at the new station, and overflow from the "H" Street
Station, which is projected to reach capacity by 1990.
Approximately 175 spaces can be provided initially at the
Bayfront Station, which will be sufficient to serve peak parking
demand for both the trolley patrons and bowlers.
3. The total cost to develop the station under this phased approach
has been estimated by the County at $3,417,000.
B. Financing the Station Development
It was proposed to the Steering Committee that the City and County
share on an equal basis the cost of developing the
station,maintenance outside the MTDB right-of-way, and any future
revenues that would be generated from the station. The County,
therefore, has proposed to increase its commitment of $1 .2 million to
$1 .7 million; the approximately $1 .7 million from the City of Chula
Vista would be contributed from the following two sources: the
$145,000 appraisal for right-of-way through the Public Works Yard for
an access road off Woodlawn Avenue would be counted toward the City's
contribution; and the Redevelopment Agency would contribute the
estimated remaining amount of $1 ,555,000 from Tax Allocation Bond
Issue funds.
Exhibit 2 shows disbursement of funds for the initial phase of the
project. Under this proposal , approximately $2.3 million would be
required through January 1985. An additional $1 .0 million would be
required through March 1986. The County would supply the majority of
the initial funding (about $1 .6 of the $2.3 million) , while the City
would hold the bulk of its contribution in reserve until
construction. This arrangement maximizes interest to the City on its
redevelopment funds, and the County cannot earn interest on its
Transportation Development Act (TDA) funds.
C. Development Schedule
Exhibit 2 also shows the proposed development schedule for Phase I of
the trolley station. As indicated on this bar chart, the necessary
environmental documents and approval , and final appraisal would be
completed by September 1984; land acquisition and construction plans
would be completed by June 1985; construction would begin in
September 1985; and the station would be completed by March 1986.
Page 5, Item 11
Meeting Date 5/15/84
In summary, this phased approach to the Bayfront Station development has
the following advantages compared with a total initial development:
- Lower initial project cost.
- Potential to generate revenue from leases for future station
development.
- Flexibilty for future development on-site is maintained. Potential
options for future development include: air rights and/or tying in
development with the City's Public Works Yard site.
2. MAJOR COMPONENTS OF NEW AGREEMENT BETWEEN COUNTY AND CITY
A. (Section 1 ) County agrees to:
- Provide a project manager who reports to the Project Steering
Committee (PSC), and to provide other staff support to insure
continued, cooperative, comprehensive coordination for the
implementation of an LRT station adjacent to the Bayfront
Redevelopment Area at "E" Street in the City of Chula Vista,
hereinafter referred to as the Chula Vista Bayfront Trolley
Station (BFTS) .
- Appoint one County Supervisor to the PSC. County Supervisor
will act as officiating member of this Committee.
- Act as lead agency in preparation of documents, facility design,
right-of-way acquisition, and construction.
- Provide TDA fund support to the extent of 50% of the station
total development cost.
- Utilize the PSC to review plans, projects, and procedures.
- Share ownership of the facility equally with the City.
- Share operating and maintenance costs equally with the City for
that portion of the facility outside the SD&AE right of way.
- Share revenue from leases equally with City.
B. (Section 2) City agrees to:
- Provide Project Coordinator.
- Appoint a City Council member to the PSC.
- Submit all project input through the PSC and the project manager
to insure continued, cooperative and comprehensive coordination
during implementation of the station.
/—//ice 2--
Page 6, Item 11
Meeting Date 5/15/84
- Act as the responsible agency, if required, during the
right-of-way acquisition phase. This would include initiation
and administration through the PSC and condemnation proceedings
should any such proceedings be necessary.
- Act as the lead agency in obtaining environmental approvals.
- Provide necessary staff support as required by the project
manager during preparation of environmental documents, facilty
design, right-of-way acquisition, and construction liaison.
- Share ownership of the facility equally with the County.
- Share total development costs of the station equally with the
County.
- Share operating and maintenance costs equally with the County
for that portion of the facility outside the SD&AE right-of-way.
- Share revenue from leases equally with the County.
- Provide management for operations and maintenance and
administration of leases.
C. (Section 3) It is mutually understood and agreed:
- That project management for facility implementation shall be the
responsibility of the County.
- That the project manager will supervise and manage the
day-to-day operation of all work associated with the
implementation of the station.
- That project direction shall be accomplished with a Project
Steering Committee (PSC) with one representative each from the
County and City. The PSC will periodically review the progress
of the project and make policy determinations as necessary. The
County 's project manager will provide staff services to this
committee. Each committee member will act as liaison to his/her
respective agency.
- That all project development costs will be supported by funds to
be provided equally by the County and the City. The County
shall manage the payment of all project development costs
incurred by the City and the County. Reimbursement of costs may
be subject to review by the PSC.
- That the City and County will jointly seek MTDB agreement to
operate and maintain that portion of the facility outside the
SD&AE right-of-way.
Page 7, Item 11
Meeting Date 5/15/84
- That in the event the project preparation or the facility
implemented in this agreement is abandoned for public use, the
County and the City will be claimants on recovering their
investments from the project termination or facility abandonment
in proportion to the amount of their respective investments. A
determination of abandonment or termination shall be agreed to
by the PSC.
- In the event of project termination or abandonment, the
disposition of any property on which the facility will lie shall
be in compliance with the terms and conditions of the agencies
from which the funds were received to implement the facility.
FISCAL IMPACT: Under this agreement, the County of San Diego and City of
Chula Vista will share equally in the cost of constructing, operating, and
maintaining the Bayfront Station. County and City also will share equally in
any revenue generated from the facility.
WMG:nr/DS-038
WPC 0399T
byte iv ,j
Chum Vim - tir
Dated