HomeMy WebLinkAboutAgenda Statement 1984/01/10 Item 6 COUNCIL AGENDA STATEMENT
Item 6
Meeting Date 1/10/84
ITEM TITLE: Resolution 745-495/ Approving Change Orders 26, 28, 30, 31,
33, 35 and 36 for the Town Centre Parking Structure
SUBMITTED BY: Director of Building & Housi -'{=l"-/5ths Vote: Yes No x )
REVIEWED BY: City Manager
On December 21 , 1982, the Redevelopment Agency awarded a contract to
C. E. Wylie Construction Company in the amount of $2,468,000 to construct the
Town Centre Parking Structure. Work began in April 1983. As a result of the
bond issue to underwrite the construction, the City Council took over the
responsibility to oversee the parking structure construction and subsequent
use. Now the structure is estimated at 90% complete and there are several
changes that are determined necessary to the ultimate goal of a well-
structured facility.
RECOMMENDATION: That the Council approve the attached resolution approving
Change Orders 26, 28, 30, 31, 33, 35 and 36 in the amount of $27,314.
BOARDS/COMMISSIONS RECOMMENDATION: Not applicable.
DISCUSSION:
Change Order No. 26
The architect completed his plans prior to finalization of the easterly
property line between Lots 4 and 7. Consequently, the pedestrian bridge that
connects the structure to the Village needed to have an additional 6 ft.
length added to adequately span an area that is intended for additional
parking. This work had been done to assure the structural integrity of the
bridge. $2400.17.
Change Order No. 28
Additional catch basins are required to ensure adequate drainage for the
facility based upon recommendation of the consultant engineer. $2,160
Change Order No. 30
The consultant soils engineer has recommended the reinforcing of the ground
level slab within the structure and in the service road to the east of it.
Originally, the reinforcing wire mesh was not shown in the construction
drawings as an unintentional omission. The large mass of concrete, which
includes the ground floor level of the parking structure, service road and
approaches from "F" Street and Third Avenue, will develop hairline cracks due
to contraction and expansion; and without reinforcing wire mesh, the cracks
will open up causing separation of the concrete and differential settlement.
This should be remedied by the addition of such wire reinforcing in the
service road. $11,004
Page 2, Item 6
Meeting Date 1/10/84
Change Order No. 31
Because of the recent rains and the allowable use of the service road by more
than one contractor, the service road grade had been significantly altered.
It is necessary to bring back the grade to the level at which the slab for the
service road can be poured. $1,067
Change Order No. 33
Excavations for concrete bases for the light standards must occur to a certain
minimum depth. The architect did not show a footing detail for the lighting
in the landscaped area. Such excavating will cost $1,147.
Change Orders No. 35 and 36
The elevator shaft on the parking structure is not enclosed. This is not an
uncommon practice. It was the architect's original intent to not enclose the
shaft. However, several concerns were raised by staff as to vandalism and
safety of the equipment that led the architect to suggest a tempered glass
enclosure that will allow the occupant of the elevator to look out towards the
Village and the theatre. It should be noted that the rear wall of the
elevator cab is all glass. $9,516
It should also be noted that the City is receiving credits for:
Change Order No. 23 - Credit of $630 for subcontractor errors in constructing
a shear wall near the west camp.
Change Order No. 37 - Credit of $6,328 for the elimination of 11 bollards to
be placed along the service road as proposed in the original design. By
changing the rolled curb orginally called for to a typical raised 6 ft. curb,
the purpose for the bollards was eliminated, and these monies were saved.
The total of change orders requested to be approved is $27,314.
FISCAL IMPACT: A contingency amount of $125,000 was set aside from the
parking structure bond proceeds for the express purpose of funding change
orders. The amount of these change orders including the current requested
change orders is $97,991 , leaving a balance of $27,000 unexpended.
Contract Amount $2,468,000
Previous Change Orders 96,721
$2,564,721
Field Change Orders Nos. 27, 32, and 34 1 ,270
$2,565,991
Current Change Orders 27,314
Total $2,593,305
Change Orders Separately Funded and Approved 189,775
Contract Sub-Total $2,783,080
Less: Credits on Change Orders 23 and 37 6,958
Contract Total $2,776,122
DZ:fp