HomeMy WebLinkAboutAgenda Statement 1983/12/13 Item 5,5a COUNCIL AGENDA STATEMENT
Item 5. 5a
Meeting Date 12/13/83
ITEM TITLE: Public Hearing: Conditional Use Permit PCC-84-5; request to
construct a 207 unit senior citizen apartment complex at 334
"C" Street - Greenwich Development Company
a. Resolution //'1,1 Approving a senior citizen apartment
complex at 334 "C" Street
SUBMITTED BY: Planning Director J: (4/5ths Vote: Yes No X )
REVIEWED BY: City Manager
The applicant is requesting permission to construct a 207 unit senior citizen
apartment complex on 5 acres located at 334 "C" Street in the R-3-G-D, C-0 and
R-1 zone. The applicant has also filed an application to rezone the R-1 area
to R-3 which is the preceding item.
RECOMMENDATION: That Council concur with Planning Commission recommendation.
BOARDS/COMMISSIONS RECOMMENDATION: On November 30, 1983, the Planning
Commission voted 6-0 with one absent recommending that the City Council
approve the senior citizen apartment complex in accordance with Resolution
PCC-84-5. Attached is a letter from the Commission on Aging endorsing the
project.
DISCUSSION:
Adjacent zoning and land use
North MHP Mobile home park
South C-0 and R-1 Commercial offices and single family dwellings
East R-1 South Bay Pioneers (AA) and single family dwellings
West C-0 Commercial office and Department of Motor Vehicles
Existing site characteristics
The project site consists of four parcels (totalling approximately 5 acres)
located on the south side of "C" Street just east of North Glover Avenue. The
site extends through to Third Avenue Extension with 156 feet of frontage along
that street and 660 feet along "C" Street. There are two existing
single-family dwellings on the subject property as well as an existing parking
area once used by the Department of Motor Vehicles prior to their relocation
to the northwest corner of Third Avenue Extension and North Glover Avenue.
Topographically, the site is characterized as very irregular having steep
slopes, some bluffs and a minor natural drainage swale which runs generally
from an east to west direction. The most prominent topographic feature is a
small knoll which is located near the middle of the property. Portions of the
property lie within the Sweetwater 100-flood plain. The site ranges in
elevation from a low of 15 feet at the west end to a high of 60 feet at the
east end.
Page 2, Item 5, 5a
Meeting Date 12/13/S3
Proposed use
The applicant proposes to construct a 207-unit senior citizen apartment
project consisting of 180 one-bedroom units and 27 two-bedroom units. The
units will be housed in 6 buildings ranging from one story to three stories in
height. The building at the northwest corner of the site (near North Glover
Avenue) will be a combination two- and three-story structure and is located
approximately 16 feet from the front property line. The other buildings along
the "C" Street frontage will be one and two stories in height with the
one-story portions of the building located nearest the street. The one-story
portions of the building set back approximately 16 feet from the property line
and the two-story portions approximately 25 feet. The Building Line Map has
established a 25-foot setback along "C" Street whereas the Municipal Code
requires a 15-foot setback for R-3 zoning. The remaining structures will be
located along the southerly portion of the site and will be two and three
stories in height. The portions of the building nearest the south property
line will be two stories. The three-story buildings will have elevators. The
building heights of the southerly buildings are lower to provide more light
and air within the interior court of the building complexes extending along
the south property line.
Parking for 150 cars and one bus stop will be provided on-site, a ratio of
approximately 3 spaces for 4 units. The parking will consist of 92 standard
size spaces and 58 compact spaces. Access is provided by two driveways along
"C" Street and one driveway on Third Avenue Extension, serving 12 parking
spaces. The remaining parking is located in the center of the project and at
the entry driveway creating an interior circular circulation system on-site.
In addition, parking for approximately 22 cars can be accommodated along "C"
Street within the public right-of-way.
Other amenities include a single-story recreation building near the southwest
corner of the site and open space courtyard areas located throughout the
project. Each unit will also have a private balcony or patio.
Grading will result in a maximum depth of cut of 15 feet and the maximum fill
of approximately 14 feet. Since a portion of the site lies within the
Sweetwater flood plain, the building pads will be at elevation 22 feet (one
foot above the 100-year flood level) or higher.
ANALYSIS:
From a locational standpoint, the project site is well suited for a senior
citizen housing development. It is located on a local bus route (Third Avenue
Extension) and near the San Diego Transit line (Fourth Avenue) . Except for
grocery shopping, there are a number of commercial services in the immediate
area. It is also near a community park (Eucalyptus Park).
The Planning Department surveyed a number of existing senior projects in the
City of San Diego to study parking. It was determined that those projects
which had a parking ratio of one space for every two units experienced little
or no problems, whereas those with a parking ratio of one space for every
three units did have limited problems. The survey supports the adequacy of
/9-firir
Page 3, Item 5, 5a
Meeting Date 12/13/83
providing one parking space for every two one-bedroom unit. It should be
noted that only one project surveyed had two-bedroom units and that was two
units out of 29 units. The "C" Street project has 27 units or 13% two-bedroom
units. For this reason the staff has recommended the parking ratio based on
the number of bedrooms rather than units, recommending a parking ratio of one
space for every two bedrooms (234 bedrooms = 2 = 117 spaces) .
The 150 spaces provided on-site represents 92 standard-size parking spaces and
58 compact parking spaces (which is 38% of the total parking) . Using a
parking ratio of one space for every two bedrooms, 117 spaces would be
required on-site and normally in a standard apartment project, the Code would
permit 10% of the total (or 12 spaces) to be compact-size parking spaces.
Normally, staff would recommend 105 standard parking spaces, but as noted
previously, the 660 feet of frontage on "C" Street provides for approximately
22 standard spaces at the curb which, to some degree, offsets the higher
percentage of compact spaces provided on-site.
The staff had two areas of major concern with the original design of the
project. These concerns were: 1) adequate light and air for residents of the
three-story units; 2) the visual impact of the project from the public streets
and upon single-family dwellings to the south.
On November 17 the project was presented to the Chula Vista Design Review
Committee to review and provide input to the Planning Commission. Prior to
the meeting, the Planning Department provided the applicant and Committee
members with an analysis of the plan citing problems relating to the lack of
light within the common courtyard areas and the need to reduce building
heights to protect view sheds.
The applicant's architect prepared a revised plan which was presented to the
Review Board at the meeting. The revised plan addressed the vast majority of
the Planning Department' s concerns and received the support of the Design
Review Committee. The project will be submitted to the Design Review
Committee for final approval on January 5, 1984.
FISCAL IMPACT: None.