HomeMy WebLinkAboutAgenda Statement 1983/10/11 Item 10 COUNCIL AGENDA STATEMENT
Item 10
Meeting Date 10/11/83
ITEM TITLE: Resolution /! ' 442''` Accepting Public Improvements -
Construction of Sidewalk Ramps 1982-83 Program in the Feaster,
Mueller and Vista Square Areas
SUBMITTED BY: City Engineer 7 (4/5ths Vote: Yes No x )
REVIEWED BY: City Manager ;r6J
G. Spikes Masonry and Cement Contractor was awarded the contract for the
construction of sidewalk ramps, 1982-83 program. The award was made June 7,
1983, by Resolution 11266. The contract was dated June 30, 1983. This work
has now been completed.
RECOMMENDATION: That City Council adopt resolution accepting the public
improvements.
BOARDS/COMMISSIONS RECOMMENDATION: Not applicable.
DISCUSSION:
G. Spikes, under the contract for the sidewalk ramps, constructed 39 ramps in
the Feaster, Mueller and Vista Square areas of the City. This work was
completed on September 21, 1983. A final inspection was made on September 23
and all work was found to be in accordance with the plans and specifications
and to the satisfaction of the City Engineer. It is now appropriate to accept
these public improvements.
FINANCIAL STATEMENT:
Authorized expenditure $26,131 .28
Approximate contract amount 22,000.00
Inspection and contingencies 4,131 .28
$26,131.38
Actual contract cost 19,859.95
Engineering staff time from point of
conception through September 15, 1983 3,261.56
Full cost recovery at 1.76 5,740.34
Total project cost $25,600.29
FISCAL IMPACT: This project is a Federally-assisted construction project
under the Community Block Grant Program. The City will assume responsibility
for maintenance.
DMH:f p/A0028
WPC 0695E
by the City C :inch of
Chula Vista, California