HomeMy WebLinkAboutReso 1990-15527 RESOLUTION NO. 15527
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CHULA
VISTA APPROVING SECOND MODIFICATION TO THE AGREEMENT
BETWEEN THE CITY OF CHULA VISTA, ROBERT BEIN, WILLIAM
FROST & ASSOCIATES AND BALDWIN VISTA ASSOCIATES, L.P.
AND AUTHORIZING THE MAYOR TO EXECUTE SAID MODIFICATION
The City Council of the City of Chula Vista does hereby resolve
as fol 1 ows:
WHEREAS, the City of Chula Vista is the agency designated to
approve consulting contracts for the Otay Ranch Project, and
WHEREAS, Robert Bein, William Frost & Associates and Baldwin
Vista Associates is the firm preparing the Goals, Objectives and Policies, and
WHEREAS, additional work needs to be performed by RBF over and
above the original scope-of-work for the preparation of a Project Team
Alternative, up to three EIR alternatives and a Public Participation Program.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City
of Chula Vista does hereby approve the Second Modfication to the Agreement
between the City of Chula Vista, Robert Bein, William Frost & Associates and
Baldwin Vista Associates, L.P., designated as city document, Contract Number
90-20.
BE IT FURTHER RESOLVED that the Mayor of the City of Chula Vista
be, and he is hereby authorized and directed to execute said modification for
and on behalf of the City of Chula Vista.
Presented by: Approved as to form by:
s J. Har ~
Robert A. Leiter
Director of Planning City Attorn
Resolution No. 15527
Page 2
PASSED, APPROVED, and ADOPTED by the City Council of the City of
Chula Vista, California, this 27th day of February, 1990 by the following vote:
AYES: Councilmembers: Malcolm, Moore, Nader, Cox
NOES: Councilmembers: None
ABSENT: Councilmembers: McCandliss
ABSTAIN: Councilmembers: None
Grego~ F~, May6r
ATTEST:
STATE OF CALIFORNIA
COUNTY OF SAN DIEGO ss.
CITY OF CHULA VISTA
I, Beverly A. Authelet, City Clerk of the City of Chula Vista, California, do
hereby certify that the foregoing Resolution No. 15527 was duly passed,
approved, and adopted by the City Council of the City of Chula Vista,
California, at a regular meeting of said City Council held on the 27th day of
February, 1990.
Executed this 27th day of February 1990.
SECOND AMENDMENT TO THE AGREEMENT BETWEEN
THE CITY OF CHULA VISTA, ROBERT BEIN, WILLIAM FROST AND
ASSOCIATES CONSULTANTS AND BALDWIN VISTA ASSOCIATES, L.P.
FOR PROFESSIONAL PLANNING SERVICES FOR THE OTAY RANCH PROJECT
WHEREAS, Section ~YIIV of the above-noted Agreement provides for any
changes in the scope of services subject to the mutual agreement of the City,
Consultant and Applicant; and
WHEREAS, the Executive Staff Committee and Interjurisdictional Task Force
have requested additional work in the preparation of a Project Team
Alternative, up to three EIR alternatives and a Public Participation Program;
and
WHEREAS, the firm of Robert Bein, William Frost and Associates (RBF) has
indicated that the cost of the work shall not exceed $180,000.00; and
WHEREAS, the work to be performed is described in that certain Scope-of-
Work, dated February 7, 1990 ("Scope-of-Work");
NOW, THEREFORE, BE IT RESOLVED that the CITY OF CHULA VISTA; the firm
RBF; and the BALDWIN VISTA ASSOCIATES, L.P., do hereby mutually agree as
follows:
1. Baldwin Vista Associates, L.P. shall pay the City up to a maximum of
$180,000.00 in accordance with the terms contained in Section XIII,
COMPENSATION, of the Agreement, to pay for the work outlined in the
Scope-of-Work.
2. RBF will invoice the City for up to 2,404 additional hours of work
on the tasks of preparing a Project Team Alternative, up to three
EIR alternatives and a Public Participation Program as described in
the Scope-of-Work.
3. The City shall pay RBF up to a maximum of $180,000.00 in accordance
with the terms contained in Section XIII, COMPENSATION, of the
Agreement to pay for the work outlined in the Scope-of-Work.
IN WITNESS HEREOF, the parties hereto have executed this Agreement on the
jZ_Z_tjlday of February 1990.
Contractor: Proponent:
Robert Bein, William Frost & Assoc. Baldwin Vista Associates, L.P.,
a California Limited Partnership
By Baldwin Builders,
Claudia Troisi
Senior Vice President
i
, . -
Attachment
EXHIBIT
SCOPE OF SERVICES
ALTERNATIVE 1AND USE PLANS
OTAY RANCH
JN 504)295
Robert Bein, Willi.am Frost & Associates (Consultant) agrees to perform the following
services related to the development of the "Project Team Alternative" and up to three E.I.R.
alternatives, as defined below:
PHASE I DEFINING THE ALTERNATIVES
1. . Develop Detailed Outline of Alternatives
Consultant shall in concert with the project team list the items
anticipated to be included on each Alternative Land Use Map, and
provide an outline of topics and issues to be included in the written
text accompanying each alternative. The consultant would also list the
major Goals, Objectives and Policies that would be considered in the
development of each alternative. The alternatives to be defined are:
A. Project Team Alternative - General Plan level of detail.
B, Low Density Alternative - E.I.R. level of detail.
C. Environmental Alternative - E.I.R. level of detail.
D. This last alternative is to be defined after the others and its
purpose would be to fill in any perceived gaps in the
alternatives.
2. Outlines Reviewed
The outlines for the various alternatives would be reviewed by the
Land Use Committee and one set of revisions made if necessary.
Example alternatives would be mapped so as to demonstrate the level
of detail proposed, and to promote discussion.
3. Public Workshop
A Workshop would be held with the Interjurisdictional Task Force and
the public to go over the alternative outlines and the example maps
to elicit their input. The workshop is envisioned to be an open and
free working interchange between the Task Force and the project team,
The workshop would be structured to focus on the alternatives and the
major issues facing the development of the Otay Ranch.
It should be noted that Client's other consultant, Dames & Moore, will
participate in the alternatives listed above and additional alternatives
which are not included in this scope of services. Any budget for
Dames & Moore's services is specifically excluded from this agreement
and should be covered under a separate agreement between Client and
Dames & Moore. Other alternatives which may be a part of their
scope, but are excluded herein; include the No Project Alternative, the
City/County General Plans Alternative; and other EIR Alternatives as
appropriate.
4. Revisions
Revisions would be made to the outlines and reviewed by the Land
Use Committee and the Executive Task Force.
A total of 300 manhours has been budgeted for the Phase I effort.
PHASE II , DEVELOP THE ALTERNATIVES
1. Project Team Alternative
The consultant and project team will work together to develop the
project team alternatives. The team will consult and confer with the
established Circulation Committee, Biology Committee, Sewer and
Water Committee, and the yet to be established Parks and Recreation
Committee; School Committee; Service Revenue Committee; and
Vision Committee. Two Public Workshops will be held on the Project
Team alternative. (See Phase III).
A total of 1,320 manhours has been budgeted for this effort. This
budget may change in that the work effort envisioned at this time may
increase due to the input received during Phase I.
2. Low Density Alternative
The consultant will develop this alternative per the approved outline
with consultation with the project team and other appropriate
committees.
A total of 200 map. hours has been budgeted for this effort.
3. Environmental Alternative
Consultant will develop this alternative per the approved outline with
consultation with the project team and the Biology Committee.
A total of 280 manhours has been budgeted for this effort.
4. Alternative D
Consultant will develop this alternative per the approved outline with
consultation with the project team and other appropriate committees.
A total of 200 manhours has been budgeted for this effort.
PHASE III PUBLIC PARTICIPATION PROGRAM
A. [ Meeting Preparation and Organization
Consultant will organize and conduct a total of four public meetings for the
purpose of providing information and a forum for comments from citizens and
I landowners wishing to participate in the planning process of the O~ay Ranch
!Project.
1. Meeting Preparation
The preparation of the public meetings will consist of the following
items:
a. A newspaper announcement for local newspapers for four public
meetings will be prepared. The cost of the newspaper ad space
would be a reimbursable item.
b. Data Collection, presentation preparation and dry run
presentation for the 4 public workshops. The Project Team
would prepare a summary and fact sheet regarding the EIR and
GDP; and related forums.
c. Preparation of one slide announcement of the Otay Ranch
Project public meetings.
d. Consultant graphic displays and slides would be prepared for the
meetings if needed as additional services, for an additional fee.
This would only happen if Baldwin Vista did not already have
the needed displays or slides. The Executive Task Force would
make the determination of needed displays and slides.
2. Meeting Organization a~nd Participation
The first three public meetings would consist of members of the
general public as well as representatives of interested local
organizations such as the Sierra Club, Audubon Society, etc.
//
Workshop #1
· This half day (4 hour) workshop would be held approximately the last
week of February. The workshop would include a presentation of the
Baldwin Vista submittal, the RBF review of the submittal, and Dames
& Moore's E.I.R. findings. There would be a discussion after the
alternative I_~nd Use Plan process and an opportunity for the public
to ask questions and discuss issues. Inquiries would be made to see
if there were citizen interest in establishing Ad Hoc Committees.
Workshop #2
This half day (4 hour) workshop would take place in approximately
mid-April. The preliminary Project Team Alternative would be
presented to the forum and the public's input would be solicited.
Workshop #3
This half day (4 hour) workshop would take place in approximately the
last week of May. The Draft Project Team Alternative would be
presented to the forum and the public's input would be solicited.
Workshop #4 - Surrounding Landowners
This meeting would consist of large (over 50 acres) landowners
surrounding the Otay Ranch properties. The focus of the meeting
would primarily be the development plans and phasing of the Otay
Ranch Development, and the planning process of the Interjurisdictional
Task Force as it relates to the region. Meeting time would be
approximately in mid-July.
B. Documentation of Public Input
A summary report documenting the public comments and responses to
comments will be prepared by RBF and the Project Team and will be printed
and submitted to the Interjurisdictional Task Force for their information.
(This report will not be a transcript, but a general approximation of the
discussion issues.)
A total of 164 man.hours has been budgeted for Phase III.
Optional Services
1. If requested by Client, Consultant shall coordinate Client's hiring of a
consultant to prepare, distribute, collect and interpret a public survey program
anticipated to incorporate questionnaire style mailings. Any services related
to this survey will be handled as Additional Services for an additional fee.
2. Any Transportation Engineering Services by JHK is specifically excluded from
this scope of services. If Client determines that JHK's services are necessary,
these services will be provided as Additional Services for an additional fee.
Additional Services
Any additional services beyond the manh0ur budgets provided herein are specifically
excluded, but may be added for an additional fee.
Reimbursables
All r~imbursable items including (but not limited to) photocopying, reproduction,
photo; mylar processes are extra and will be billed separately from this authorization.
For Client's budgeting purposes, however, reproduction expenses could be $15,000
Or Ffiore.
./
EXHIBIT "B"
COMPENSATION
OTAY RANCH
JN 500295
B. Client agrees to compensate Consultant for services described in Exhibit "A" as
follows:
Monthly on a time and materials basis based upon 2.85 times the wages paid for all
personnel working on the project, with a max/mum budget of $183,500, plus the
direct' cost of reimbursable expenses. An estimated budget for each work phase is
included below. Consultant reserves the right to transfer budget amounts between
work phases based on project workload.
: Estimated Estimated
Work Phase Manhour Budget
PHASE I - Defining the Alternatives
1. Develop Detailed Outline of
Alternatives 165 12,500
" Outlines Reviewed 35 2,500
3, ; Public Workshop 65 5,000
4. iRevisions ~5 2.500
Subtotal 300 $ 22,500
PHASE II - ' Develop the Alternatives
1. Project Team Alternative 1,320 98,000
2. Low Density Alternative 200 15,000
3. Environmental 280 21,000
4. Alternative D 200 15.000
Subtotal 2,000 $149,000
PHASE III - Public Participation Program
1. Meeting Preparation and Organization 40 3,000
2. Workshop #1 16 1,250
3. Workshop #2 16 1,250
4. Workshop #3 16 1,250
5. Workshop #4 16 1,250
6. Documentation of Public Input 60 4.000
Subtotal 164 $ 12,000
TOTAL $183,500
EXHIBIT 'B' (Continued)
COMPENSATION
OTAY RANCH
JN 500295
Progress billings will be forwarded to the Client on a monthly basis. These billings will
include the fees earned for the billing period plus all direct costs advanced by Consultant.
The Client shall make every reasonable effort to review invoices within fifteen (15) working
days from the date of receipt of the invoices and notify Consultant in writing of any
particular item that is alleged to be incorrect.
The fees proposed herein shall apply until February 1, 1991. Due to ever-changing costs,
Consultant w~ll increase those portions of the contract fee for which work must still be
completed after February 1, 1991, by ten-percent (10%).
PRELIMINARY ESTIMATED SCHEDULE
Task
Phase I Define Alternatives I
Develop Detailed Oatlines
Outlines ReMewed
Public Workshop Task Force
Revisions to Outlines I J
I
Phase II Develop Alternattve~ I
Project Team Alternative i I
Low Density Alternative I
Environmental AZte'native
Alternative D [ I [
I I I _.J_~.~
Phase III P~blic Par~cipation I [ [
Meeting Preparation
Wo,+,shop #1
W~kshop #2 I I
Workshop #3 [ I I
Workshop #4 [ I I
Documentation of Input I /J I
J I
I
Note: This schedule is preliminary and should be used for discussion
purposes only. Actual timing may va~/cof~sidetabJy.
/.
Ranch EIR Land Use Alternatives
I
___ I
I
I
I
JN 500295-2993