Loading...
HomeMy WebLinkAboutAgenda Statement 1985/05/14 Item 10 COUNCIL AGENDA STATEMENT Item in Meeting Date 5/14/85 ITEM TITLE: Resolution 4;4944Z—Accepting public improvements, Third Avenue Street lights from "K" Street to "L" Street SUBMITTED BY: Director of Public Works/City Engineer 9e./. REVIEWED BY: City Manager (4/5ths Vote: Yes No x ) Perry Electric was awarded the contract for the installation of street lights on Third Avenue between "K" and "L" Streets on December 11 , 1984, Resolution No. 11868. The contract is dated December 26, 1984. This work is now completed. RECOMMENDATION: That Council adopt resolution accepting the public improvements. DISCUSSION: Perry Electric has completed the construction of the street lights on Third Avenue between "K" and "L" Streets. A final inspection was made on April 30 and all work was found to be completed in accordance to the plans and specifications and to the satisfaction of the City Engineer. FINANCIAL STATEMENT: Authorized expenditure $17,000.00 Original contract amount 15,390.00 Final contract amount 15,340.00 Balance of authorized expenditure 1 ,660.00 Engineering staff time from point of inception through 4/11/85 -- $ 2,459.71 x $ 4,329.09 full cost recovery factor of 1 .76 = FISCAL IMPACT: City will assume maintenance of these improvements upon acceptance. DMH:fp/BX029 �� WPC 1512E / . . ..... . . .... .. .. . . .