HomeMy WebLinkAboutAgenda Statement 1986/07/15 Item 11 COUNCIL AGENDA STATEMENT
Item 11
Meeting Date 7/15/86
ITEM TITLE: Resolution /a(2°5‘ Accepting contract work, Traffic Signal ,
East "H" Street and Hidden Vista Drive
SUBMITTED BY: Director of Public Works/City Engineer . /`
REVIEWED BY: City Manag:ui'' (4/5ths Vote: Yes No X )
McCain Construction Co. was awarded the contract for Construction of Traffic
Signal at East "H" Street and Hidden Vista Drive, Resolution 12430 dated
April 8, 1986. The contract is dated April 17, 1986. The work was completed
on June 27, 1986.
RECOMMENDATION: That Council adopt resolution accepting the contract work.
BOARDS/COMMISSIONS RECOMMENDATION: Not applicable.
DISCUSSION:
McCain Construction Co. completed the construction for the traffic signal at
East "H" Street and Hidden Vista Drive. A final inspection was made on
June 30, 1986, and all work was found to be completed in accordance with the
plans and specifications and to the satisfaction of the City Engineer.
FINANCIAL STATEMENT
Authorized Expenditure $48,706.00
Original Contract Amount $39,706.00
Change Order No. One, Additional Conduit 2,282.75
Final Construction Cost $41 ,988.75 $41 ,988.75
Plan Preparation by Consultant 4,000.00
Balance Authorized Expenditures $ 2,717.25
FISCAL IMPACT: City will assume annual maintenance and energy cost,
approximately $4,000.00/year.