ITEM TITLE: Resolution /2 5 9/ Accepting contract work, reconstruction of
swimming pool deck, Loma Verde Park
SUBMITTED BY: Director of Public Works/City Engineer pg'//
REVIEWED BY: City Manager. (4/5ths Vote: Yes No X )
Fritz A. Nachant, Inc. was awarded the contract for reconstruction of the Loma
Verde swimming pool deck by Resolution 12308 on December 18, 1985. The
contract is dated January 10, 1986. The contract completion date was
April 23, 1986.
RECOMMENDATION: That Council adopt resolution accepting the contract work.
BOARDS/COMMISSIONS RECOMMENDATION: Not applicable.
DISCUSSION:
Fritz A. Nachant, Inc. completed the placing of the new concrete deck and
appurtenances on April 14, 1986. A final inspection was made on April 16,
1986, and a list of discrepancies was prepared consisting of general with
and
cleaning. Meetings were held on April 30, 1986 and May 1 ,
representatives of Parks and Recreation and several items of concern were
discussed. Fritz A. Nachant, Inc. completed the additional items and Parks
and Recreation began filling the pool on May 5, 1986.
Although use of the pool was delayed approximately ten days beyond the
scheduled use, we do not recommend that the Contractor be charged a penalty
since staff was a contributor in the delay. Parks and Recreation has
estimated that they lost approximately $289 in revenue.
The work has been completed in accordance with the plans and specifications
and to the satisfaction of the City Engineer.
FINANCIAL STATEMENT:
Authorized Expenditure $83,600.00
Original Contract Amount $68,744.00
Change Order One, Drains & Cleanouts 1 ,977.54
Change Order Two 4,495.72
Extra Work, Time & Material 1 ,051.43
Total $76,268.69 $76,268.69
Balance Authorized Expenditure
$ 7,331 .31
FISCAL IMPACT: City will continue maintenance of the pool facilities.