HomeMy WebLinkAboutAgenda Statement 1986/08/12 Item 7 COUNCIL AGENDA STATEMENT
Item 7
Meeting Date 8/12/86
ITEM TITLE: Resolution J (76 Accepting contract work, Country Club
Sewer/Lighting Improvements, Country Club Drive to Hilltop
Drive between "K" Street and "L" Street
BY: Director of Public Works/City Engineer ,%
REVIEWED BY: City Manager (4/5ths Vote: Yes No X )
The Country Club sewer/lighting improvements contract was awarded by
Resolution 12396 on February 25, 1986, to Petar Artukovich Construction Co.
The contract date is March 17, 1986. The work is now completed.
RECOMMENDATION: That Council approve resolution accepting the contract work.
DISCUSSION:
Petar Artukovich completed the construction of the Country Club Sewer/Lighting
Improvement on July 23, 1986. A final inspection was made on July 31 , 1986,
and all work was found to be completed in accordance with the contract plans
and specifications and to the satisfaction of the City Engineer.
FINANCIAL STATEMENT:
Authorized Expenditure $403,100.00
Original Contract Amount $378,159.25
Construction Survey (Algert Eng. ) 5,355.00
Final Construction Cost 381 ,355.75
Balance of Authorized Expenditure $ 16,389.25
Staff time from point of inception to July 3, 1986 -- $27,894 times
Full Cost Recovery factor of 2.238 equals $62,427.
FISCAL IMPACT: City will maintain sewer and lighting and pay energy cost
for street lights estimated at $1 ,500 per year.
DMH:fp/AR014, BX033
WPC 2259E
)