HomeMy WebLinkAboutAgenda Statement 1986/08/05 Item 7 COUNCIL AGENDA STATEMENT
Item 7
Meeting Date 8/5/86
ITEM TITLE: Resolution/, ' 93 Accepting the work on the remodeled
Management Services' offices in City Hall
SUBMITTED BY: Acting Director of Building an sing
Deputy City Manager Thomson /(/
REVIEWED BY: City Manager (4/5ths Vote: Yes No X )
On February 18, 1986, RONCO Construction Company was awarded the contract for
remodeling offices for the Management Services Department by the City
Council . Prior to his retirement, the Director of Building and Housing
inspected the work and found it to be satisfactory with the exception of a
short list of deficiencies. The company has since corrected all of these
deficiencies.
RECOMMENDATION: That Council adopt the resolution accepting the remodeled
Management Services' offices in City Hall .
BOARDS/COMMISSIONS RECOMMENDATION: Not Applicable
DISCUSSION:
Work on the remodeling project commenced on March 31 ,
1986. The project
completion date was June 25, 1986, when staff moved into the new offices. An
inspection of the work was extremely satisfied with the work and
aade � all of the
prepared. Overall , staff
listed deficiencies have been corrected.
Completion of the remodeling project was delayed a total of 32 working days.
This delay principally resulted from undertaking a reassessment of the planned
support structure for
identified after the project was underway.
do additional
repair work which was
IMPACT: The original contract budgeted a total of $42,281 .00 for the
remodeling project, which included $3,300 for contingencies. Of this amount,
a total of $42,245.00 in construction related expense was incurred. Field
Change Orders totaled $3,261 compared to the $3,300 budgeted for contingencies.
WPC 09051