HomeMy WebLinkAboutAgenda Statement 1987/04/14 Item 19 COUNCIL AGENDA STATEMENT
Item 19
Meeting Date 4/14/87
ITEM TITLE: Resolution AZ77 Approving extension of contract time for
the EastLake Assessment District -2 projects
SUBMITTED BY: Director of Public Works/City Engineer
REVIEWED BY: City Manage (4/5ths Vote: Yes No X )
On February 24, 1987, the City Council by Resolution No. 12913 approved an
extension of contract time for the four projects contained in the EastLake
Assessment District 85-2. The four contracts were extended to April 15, 1987,
due to a delay in the delivery of a telemetry cable to be installed by each
contractor.
Olson Construction Co. , the contractor for two of the four contracts, has
requested another extension of time for their projects (see attached letter
dated March 16, 1987). The basis for their request is that electrical power
is not currently available from SDG&E. SDG&E has informed the contractor that
the electrical power supply won't be available for another two weeks. Thus,
Olson Construction has requested a time extension to May 15, 1987, to allow
them to complete their work once the electrical power supply is available.
RECOMMENDATION: That Council adopt a resolution approving extension of
contract time to May 15, 1987 for the EastLake District 85-2 contracts.
BOARDS/COMMISSIONS RECOMMENDATION:
DISCUSSION:
EastLake Assessment District 85-2 consists of four contract projects. The
projects are:
1 - Phase 1 , 5MG Steel Reservoir, Trusco Tank Co. , Contractor
2 - Phase 2, 980 Zone Pump Station, Olson Construction Co. , Contractor
3 - Phase 3A, Construction of Otay Lakes Road, sewer, and waterlines and all
appurtenances, Olson Construction Co. , Contractor
4 - Phase 3B, 20 in. off-site water pipeline, Thibodo Construction, Co. ,
Contractor
The four projects are closely interrelated as they each contain portions of
the water improvement infrastructure needed to serve the EastLake Planned
Development. All the work is virtually complete. However, the improvements
cannot be accepted until all the water facilities are operational and tested
by the Otay Water District. The unavailability of electrical power required
Page 2, Item 19
Meeting Date 4/14/8/
to operate the pump station affects all the contracts. Without electrical
power, the pump station improvements cannot be checked for proper operation.
The pump station (Phase 2 contract) is needed to fill the 5MG Reservoir (Phase
I contract) via the 20 in. off-site water pipeline (Phase 3A & 3B contracts).
The Otay Water District has requested that the extension be approved for all
contracts as they prefer to accept all the improvements at the same time. The
EastLake Development Company has been contacted and informed of the proposed
action. They concur with the time extension as they are also affected by the
unavailability of electrical power (see attached letter dated April 8, 1987).
FISCAL IMPACT: EastLake Assessment District 85-2 will pay the added cost
for staff time necessary to conduct the required inspection and administration
of the contract work. There will be no direct cost to the City for granting
the extension of contract time to May 15, 1987.
WPC 2715E
�y the City Council of
Chula Vis La, California
Dated 1C --f
Olson Construction Company
P. 0. Box 87483
San Diego, CA 92138
Attn: Mr. Tom Cooper
Ij
Otay Water District a *
10595 Jamacha Boulevard
Spring Valley, CA 92078 j
Attn: Mr. Larry Doyle
Trusco Tank Company
4388 Santa Fe Road
San Luis Obispo, CA 93401
EastLake Development Company
p P yl
701 "B" Street ! I
San Diego, CA 920101
Attn: Mr. Robert Santos H
EastLake Development Company
701 "B" Street
San Diego, CA 92101
Attn: Mr. Rod Myers it
, I I
Thibodo Construction Company
1505 Sycamore Avenue
Vista, CA 92083
I . I
it I
I �
� + I
' I I
) 1
1
i I
I �
' I I
! I
' I
P O. BOX 81483 • SAN DIEGO, CALIFORNIA 92138 • W1914.)0 9800
9747 OLSON DRIVE • SAN DIEGO, CALIFORNIA 92121
C� on
March 26, 1987
(. crrifDiy
City of Chula Vista
Engineering Dept .
276 Fourth Ave. _
Chula Vista, CA 92010
Attn: Roberto Saucedo
Ref. Projects: Eastlake Pump Station
and Eastlake Piping III A.
Subject : Contract Completion Time
Dear Roberto:
We come to you once again to request a time extension on the
contract completion date on both the above projects .
By the completion date we have (April 15) , we should be complete
on the Pump Station contract except for start-up of anything that
is electrical and the installation of the roll-up door. The
district demanded the Atlas roll-up door in lieu of the Pacific
rolling door as submitted. However, both of these doors were
specified. The electrical power supply, of course, we ,have no.
control over. If we had power this week, which is out of the
question, it would be tight in getting all the electrical checked
out under the existing completion date. -
The Piping III A contract should be physically complete, however,
we are not sure we will have power to check the operation of the
electrical items.
I have talked to Eastlake Development and Otay Water District
and they share our concerns .
We respectfully request the contract time be extended to May 15,
1987 (one additional month) on both projects . We sincerely -hope
all the additional time will not be used. However, anything less
may necessitate another Council action for more time.
We appreciate your continued co-operation and assistance.
Very truly yours ,
OLSON CONSTRUCTION COMPANY
7112 ac/Aa_A...r,)
T. N. Cooper
Project Manager
CC• o T-y 4.4..i/,1-7- 2 !7/3;72/0.-
April 8, 1987
fJ [ A,'i -3 ni'1 i1- 08
Mr. Roberto Saucedo
The City of Chula Vista
276 Fourth Avenue
Chula Vista, CA 92010
Dear Mr. Saucedo:
This letter is to inform you of the delay to the 980 zone
Pump Station pertaining to San Diego Gas and Electric as
understand it. The sequence of events necessary to permit
delivery of electrical power to the Pump Station was quite
complicated. The timing of these many events as they
dovetailed with each other was critical.
The contractors who performed most of the work were
either under EastLake Development Company's supervision �` `
or working for the City of Chula Vista under the ` "'ff,�,I
Assessment District contract. The majority of the
work took place as planned, but the most critical element
(electrical wiring) was, or course, to be installed by �/�
San Diego Gas and Electric crews. As you most likely are EASTLAKE
aware, the scheduling of SDG&E crews to commence work DEVELOPMENT
as well as the day-to-day progress of the work are events COMPANY
over which we have little control.
When the work was ready for the wiring crews to commence,
this data was simply put "in line" with whatever other jobs
were available within SDG&E's sphere of influence. This meant
that the wiring crews were dispatched to this project when all
other prior commitments had been met. Waiting for crew -
availability incurred approximately 11 weeks of delay. Additionally,
crew progress is critical to delivery of power as well.
As with most construction, problems are bound to arise, and
this is the case with SDG&E as well. Wiring crews have encountered
a few problems of their own which will also add some time. Exactly
how much time , however, is unknown because the planned construction
time is unknown.
In order to be fully aware of the latest projections for power delivery
to the Pump Station as well as other projects within the EastLake
-business Center, 1 keep in close contact with representatives of SDG&E.
As of today, SDG&E expects to have power to the Pump Station late
in the week of April 13, 1987.
Feel free to contact me with any questions or comments you may have.
S'r5cerel ,
Curt Smith
701 Street
Construction Manager Suite 730
San Diego,CA 92101
C N S:dt (619)231-2858
_ Copy to Gary Kashing