HomeMy WebLinkAboutAgenda Statement 1987/04/07 Item 10 COUNCIL AGENDA STATEMENT
Item 10
Meeting Date 4/7/87
ITEM TITLE: Resolution42951 Accepting contract work, "Pavement of
asphalt concrete overlay (1986-87 program) at various
locations in the City of Chula California"
SUBMITTED BY: Director of Public Works/City Engineer
(p1///
REVIEWED BY: City Manager (4/5ths Vote: Yes No X )
On December 9, 1986, the City Council by Resolution No. 12839 awarded the
contract for "pavement of asphalt concrete overlay (1986-87 program) at
various locations in the City of Chula Vista" to Daley Corporation. The
contract is dated December 4, 1986. The work is now completed.
RECOMMENDATION: That Council approve a resolution accepting the contract
work.
BOARDS/COMMISSIONS RECOMMENDATION: Not applicable.
DISCUSSION:
Daley Corporation completed the pavement overlay work on February 27, 1987
with a final inspection made on the same day. All work was found to be
completed in accordance with the contract plans and specifications. The work
was accomplished to the satisfaction of the City Engineer.
The streets listed below were overlaid with this project.
Millan Street - Gretchen Road to Myra Avenue (City)
Inkopah Street - Melrose Avenue to Nacion Avenue (City)
Mission Court - East "J" Street to end of cul-de-sac (City)
30th Street - "L" Street to Edgemere Avenue (City)
Sierra Way - Broadway to Cedar Avenue (City
Oxford Street - Third Avenue to Alpine Avenue (Montgomery)
Glenhaven Way - First Avenue to Elm Avenue (Montgomery)
Elm Avenue - Glenhaven Way to Amy Street (Montgomery)
Amy Street - Elm Avenue to end (Montgomery)
First Avenue - Palomar Street to Oxford Street (Montgomery)
Tobias Drive - Palomar Street to Orlando Court (Montgomery)
Oxford Street - Tobias Drive to Hilltop Drive (Montgomery)
Third Avenue - "L" Street to Moss Street (Montgomery)
FINANCIAL STATEMENT:
Authorized Expenditure:
a. Third Avenue - 250-2501 -GT215 $ 59,850.00
b. City Streets - 250-2501-GT217 112,090.00
c. Montgomery Streets - 250-2501 -GT218 91 ,740.00
$263,680.00
Page 2, Item 10
Meeting Date 4/7/87
Original Contract Amount: $239,716.25
Final Construction Cost:
a. Third Avenue - 250-2501 -GT21 5 $ 71 ,889. 16
b. City Streets - 250-2501-GT217 81 ,316.20
c. Montgomery Streets - 250-2.501 -GT218 96,816.04
$250,021 .40
Staff Time from Point of Inception to January 15, 1987:
a. Third Avenue - AX093
$3406. 53 x 1 . 73 (full cost recovery factor) = $ 5,893.30
b. City Streets - AX091
$3297. 65 x 1 . 73 (full cost recovery factor) = 5,704.93
c. Montgomery Streets - AX095
$945. 95 x 1 . 73 (full cost recovery factor) = 1 ,634.49
$13,232.72
FISCAL IMPACT: Overlay will extend life of pavement and reduce maintenance
costs.
RS:fp/
WPC 2686E