Loading...
HomeMy WebLinkAboutAgenda Statement 1987/02/24 Item 8 COUNCIL AGENDA STATEMENT Item 8 Meeting Date 2/24/87 ITEM TITLE: Resolution/' 7�,% Approving extension of contract time for the EastLake Assessment District N . 85-2 projects SUBMITTED BY: Director of Public Works/City E A:Y ne er REVIEWED BY: City Manager y1;,/ (4/5ths Vote: Yes No X ) EastLake Assessment District No. 85-2 consists of four contract projects. The projects are: 1 . Phase 1 , 5 M.G. Steel Reservoir, Trusco Tank Co. , Contractor 2. Phase 2, 980 Zone Pump Station, Olson Construction Co. , Contractor 3. Phase 3-A, Construction of Otay Lakes Road, sewer, and water lines and all appurtenances, Olson Construction Co. , Contractor 4. Phase 3-B, 20" off-site water pipeline, Thibodo Construction Co. , Contractor On November 4, 1986, Council , by Resolution No. 12804, approved an extension of contract time (to February 28, 1987) for projects 1 , 2 and 4 above. Contract No. 3 was also extended to February 28 at a later time by the City Council (Resolution No. 12849, adopted on December 16, 1986). The extension of the contract time for each project was due to a delay in the delivery of the telemetry cable which must interface in size, color coding and number and is to be installed by each contractor. Olson Construction Co. , the contractor for the 980 Zone pump station project, has requested another extension of time for this project. Their request is again due to equipment delivery delays. This time, they have encountered difficulty in obtaining delivery of electrical switch gear for the pump (see attached letter) . Their request is to extend the contract to April 15, 1987. This request is considered appropriate and is recommended by the Otay Water District. The pump station completion date affects the completion of work under the other three contracts. The Otay Water District also recommends that the other three contracts be extended as well (see attached letter). RECOMMENDATION: That Council adopt a resolution approving extension of contract time to April 15, 1987, for the EastLake Assessment District 85-2 contracts. Page 2, Item 8 Meeting Date 2/24/87 DISCUSSION: EastLake Assessment District 85-2 involves construction of major infrastructure facilities needed to serve the EastLake Planned Development. The work now under construction was awarded by the City in four separate, but closely interrelated contracts amounting to about $7.8 million. The contracts are at various stages of construction and are proceeding in a timely manner, considering the fact that several contractors, agencies and developers are involved. Conflicts have been reduced to a minimum through the cooperation that exists amongst all parties concerned. The EastLake Assessment District 85-2 projects were approved by both the City and Otay Water District on a "fast track" basis. One of the difficulties generally encountered when projects are processed in a "fast track" basis is that contractors encounter problems obtaining equipment on time to meet their contractual obligations. This has occurred once already with the delivery of a telemetry cable acceptable to Otay Water District and needed to provide communications between equipment at the reservoir and the pump station. Accordingly, Council was requested to approve contract time extensions to accommodate the cable delivery time delay. Olson Construction Co. has requested a second extension of time for their 980 zone pump station project. They have submitted information which shows a diligent effort in obtaining the electrical motor control equipment they are to install per their contract. We have met with the contractor, Otay Water District representatives, and EastLake Development Company officials to discuss the time extension request. We concur with the validity of the request and recommend that the contract be extended to April 15, 1987, as requested. The extension of time for the 980 Zone pump station contract, however, affects the contractual time obligations of the other three projects. Otay Water District requires that the reservoir and water main connecting it to the pump station be bacteria tested and chlorinated at the same time. The reservoir, however, cannot be filled until the pump station is operational . Thus, although the reservoir and water line projects are virtually complete, Otay Water District has requested that the other three contracts be extended to accommodate the pump station project. Since the Otay Water District will be the ultimate owner of the water facilities, we concur with their recommendation. We have contacted the contractors affected by the contract time extensions and they have no objection to the proposal . It should be noted, however, that the Otay Water district is responsible for providing a control panel for the pump station. They are having problems obtaining the panel and may request a further extension of the pump station contract. The pump can be operated without this panel and will not affect the acceptance of the work under the other contracts. We have a question as to the responsibility for the installation of the panel . The Contractor has stated that the installation is not part of his contract. Since neither the plans nor the specifications are clear on this item, we may have to negotiate Page 3, Item 8 Meeting Date 2/24/87 a change order with Olson Construction for the installation of the panel . Any additional costs due to the installation and/or time delays may have to be paid by either the Otay Water district and/or the EastLake Development Company, unless it is decided that the Assessment District proceedings are legally bound to cover this possible extra cost. This is provided to you as informational material only. We are looking to successfully resolve the installation of the panel without either a cost increase or time extensions. FISCAL IMPACT: EastLake Assessment District 85-2 will pay the added cost for staff time necessary to conduct the required inspection and administration of the contract work. There will be no direct cost to the City for granting the extension of contract time to April 15, 1987. WPC 2610E • the City Council of Chula Vista, California Dated o2 y— r P O BOX 87483 • SAN DIEGO. CALIFORNIA 02138 • 1619) 450 9800 9747 OLSON DRIVE • SAN DIEGO. CALIFORNIA 92121 Ocn cbnidion January 26 , 1987 pang CITY OF CHULA VISTA Engineering Dept . 276 Fourth Ave. c-- Chula Vista, CA 92010 °~ i Attn: Roberto Saucedo Ref. Project : Eastlake Pump Station 980 Zone - Phase II (4. 4T wt Dear Roberto , This letter will summarize actions taken in an effort to expedite the electrical motor control equipment on the above referenced project . On May 8 , 1986 , contractor requested a meeting with all concerned as Westinghouse was questioning the requirements. This meeting was held at SDG&E meter shop. Those present were Paul Saxton and Dan Vannice of SDG&E , Jim Wagenman of Lowry and Associates, Chuck Dobbins of Blackhawk Ind., , Inc. , Larry Doyle and Manual Arroya of Otay Water District , Mark Balan of Balan & Associates , Frank Herget of Westinghouse Corp. , and Will Pflugh , Jay Whalen and Tom Cooper of Olson Construction Co. All items in question were discussed and the meeting concluded with what we thought was a clear understanding of what was required and acceptable. Electrical submittals were promised and expected to be in between 8 and 12 weeks. There were many calls made by contractor to subcontractor and many from subcontractor to Westinghouse as evidenced by attached Blackhawk letter dated January 21 , 1987. Many of which 'i`rxi sure did not get recorded. Finally, on August 28 , 1986 we received a partial and more followed until complete MCC equipment submittals were in, October 18 , 1986. Each submittal was hand carried to Otay Water District the day they were received by the contractor. Otay Water District reviewed the complete package (MCC equipment submittals) and we received it back November 4 , 1986 approved with corrections noted (corrections were very minor) . Olson ' s letter dated October 23 , 1986 to the City of Chula Vista alerted of our first notification of an extended lead time. At that time, we requested the city or their consultant to assist in expediting delivery of equipment by talking to Westinghouse because they were the specifiers. We have previously contacted Larry Doyle at Otay Water District and Rod Myers of Eastlake Development both to assist by calling Westinghouse. On December 22 , 1986 , we received, through Blackhawk Ind. , a letter from Westinghouse dated December 17 , 1986 which we sent to Otay Water District with a copy to you. We have always and are still trying to expedite delivery of this equipment . Attached, please find a copy of Blackhawk Ind. , Inc . memo dated January 8 , 1987 pushing the delivery date of the longest lead item piece of equipment up to February 27 , 1987 in lieu of Westinghouse ' s previously notification of March 31 , 1987. With this new delivery date from Westinghouse , if it is met , our request for extention time would be for contract completion April 15 , 1987 in lieu of May 15 , 1987 , previously requested in ourletter of December 24 , 1986 . If there is any other information required to extend the contract time , please do not hesitate to call . Very truly yours , OLSON CONSTRUCTION COMPANY 7/i7 T.N. COOP R Project Manager TNC/kk cc: Otay Water District Attn : Larry Doyle 4'A QTAY ...�Dedieated to Community Sertviee i-• 4 10595 JAMACHA BOULEVARD,SPRING VALLEY,CALIFORNIA 92078 L_ ��@ �G TELEPHONE:462-2222,AREA CODE 619 I- C February 12 , 1987 E Mr. Roberto Saucedo City of Chula Vista Public Works Department 276 Fourth Avenue Chula Vista, CA 92010 Subject : Contract Time Extensions EastLake Business Park, Contract IIIA - W.O. 1653 980 Zone Pump Station - W.O. 1701 20" Offsite Water Main - Contract IIIB - W.O. 1702 5 MG Reservoir - W.O. 1703 Dear Mr. Saucedo: This letter is to corroborate our conversation of this date concerning time extensions for the subject projects. In reference to Mr. Tom Cooper ' s letter from Olson Construction Company, dated January 26, 1987 and addressed to you, the revised schedule for completion of the pump station is April 15, 1987. The extension is due to the late delivery of the Westinghouse electrical panels. Additionally, Contract IIIA, Contract IIIB, and the 5 MG Reservoir projects are dependent upon water being available from the pump station to maintain a minimum bacteriological requirement of the water within the water mains and the reservoir. Following availability of water to the reser- voir , a minimum of four weeks time is required to obtain Health Department approval of the water sample analyses. Therefore, the District recommends that all four contracts be extended to the April 15, 1987 completion date. Please call if you have any questions. Very truly y14, 0:,.Zlp ' Larry re oyle Construction Engineer dm cc: Olson Construction Company Thibodo Construction Company Trusco Tank Company COUNCIL AGENDA STATEMENT Item 10 Meeting Date 2/24/87 ITEM TITLE: Resolution / Accepting informal bids and awarding contract for Traffic Signal Installation at East "H" Street and I-805 Northbound Off-Ramp in City of Chula Vista, CA SUBMITTED BY: Director of Public Works/City Engineer 4/74 REVIEWED BY: City Manager N (4/5ths Vote: Yes No X ) Informal bids were received from three (3) qualified electrical contractors to install the traffic signal at East "H" Street and I-805 northbound off-ramp to replace the existing three-way stop. The project was included in the 1986-87 CIP. The project consists of installation of a new fully actuated traffic signal . RECOMMENDATION: That Council accept the bids and award the informal contract to MCR in the amount of $22,197.00. BOARDS/COMMISSIONS RECOMMENDATION: Not applicable. DISCUSSION: Bids were received from three contractors as follows: 1 . MCR Electrical Contractors, Inc. , Imperial Beach $22,197.00 2. Cal-Vista Electric, Chula Vista 25,625.00 3. TCB Electric, Spring Valley 28,800.00 The low bid by MCR was below the engineer' s estimate of $23,000.00 by $803.00 or 3. 5%. We have reviewed the low bid and believe it to be excellent and recommend awarding the contract to MCR Electrical Contractors, Inc. The CalTrans permit to allow our contractor to work in State right-of-way is expected to be received by Friday, February 20, 1987. FINANCIAL STATEMENT: Funds are available from the following account: Project #TF-115 Traffic Signal-H and I-805 $112,000.00 Funds required for construction: a. Contract Amount $ 22,197.00 b. Contingencies (approx. 10%) 2,220.00 Total Funds for Construction of Project $ 24,417.00 FISCAL IMPACT: City share of maintenance and energy costs. MJD:nr/BR-020 WPC 2620E ) yithe City Council of Chula Vista, California Dated _ _