HomeMy WebLinkAboutAgenda Statement 1987/01/06 Item 15 COUNCIL AGENDA STATEMENT
Item 15
Meeting Date 1/6/87
ITEM TITLE: Resolution I ., Appropriating $121 ,000 from unappropriated
General Fund Surplus to complete the upgrading of the Police
Department Air Conditioning system as part of the Crime Lab
Construction Project.
SUBMITTED BY: Director of Public Works/Cit Engineer p1/1/Director of Public Safetyt�J
V�
REVIEWED BY: City Manager (4/5ths Vote: Yes X No )
The mechanical consultants working on the plans for the Police Crime Lab and
Communications Center project identified a serious deficiency in the
building' s air conditioning system. Those deficiencies will become critical
when the new Communications Center and other first floor remodeling is
completed unless the deficiencies are corrected. Apparently, the air
conditioning system at the Police Department, which was built approximately 17
years ago, was not designed to accommodate full usage of the building as now
proposed to be occupied. A study to determine the best method of upgrading
the air conditioning system has been completed.
RECOMMENDATION: That the City Council adopt Resolution appropriating
$121 ,000 from unappropriated General Fund Reserves to Capital Improvement
Project No. RS61 , Public Safety Communication Center.
BOARDS/COMMISSIONS RECOMMENDATION: Not applicable.
DISCUSSION:
City staff worked with a mechanical engineer to review the existing Police
Department air conditioning system and to make recommendations for necessary
upgrades to eliminate the deficiencies. The Engineer' s report evaluated the
system for potential operating cost savings and operational corrections.
The existing air conditioning system, consisting of terminal reheat in the
first floor and multizone in the basement, was compared to two alternatives
involving system modifications. Alternative No. 1 is the existing system.
Alternative No. 2 is conversion of the first floor to a fan powered variable
air volume system, with no changes to the basement system. Alternative No. 3
includes the variable air volume modification, addition of a one hundred
percent outside air economy cycle for both floors and a backup system for the
computer and communications equipment. A fourth alternative involving the
addition of cogeneration equipment was evaluated. There is a potential for up
to four buildings at the site to be served by a cogeneration facility.
Page 2, Item 15
Meeting Date 1/6/87
Following is a summary of economic data on each alternative:
Alternative Installed Cost Life Cycle Cost Payback Period
1 0 $1 ,347,582
2 3 $155,165,000 1 ,297,784 4
1 ,287,409 5
4 495,560 1 ,105,879 5
The life cycle cost analysis includes the annual utility and maintenance costs
over a six year life cycle. The payback period is the amount of time required
to payback the initial installation costs through energy savings.
Two benefits in addition to operational cost savings and improved comfort
level will be achieved with Alternative No. 3. The use of an outside air
economy cycle will reduce the maximum air conditioning load to a level which
will allow the existing chiller equipment to accommodate the new load
generated by the proposed expansion. Secondly, in the event of a chiller
failure most of the building will be able to operate with little or no
discomfort until repairs are completed. The backup systems will provide
protection for the more critical computer and Communications operations.
It is recommended that Alternative No. 3 be implemented as part of the
Facility Expansion. If the Expansion Project scope were to include
Alternative No. 3, the cost impact and inconvenience to the Police staff will
be minimized. Implementation of Alternative No. 3 will also eliminate the
existing temperature control problems which exist in the Police facility. If
this Alternative is completed in conjunction with the first floor and basement
expansion projects, it will minimize the first cost financial impact and
inconvenience to Police personnel during construction. Outside air intakes
for the economy cycle would be incorporated into the first floor expansion
project construction, offsetting the need for additional holes in the existing
roof structure. Once the economy cycle is operational , chiller capacity will
be available for the entire expansion project.
A site cogeneration facility could have as low as a five year payback. First
cost of the facility will be affected greatly by S.D.G.&E. requirements. The
cogeneration facility could be added to the system at any time with no adverse
effect on the Police Facility Expansion. It is recommended that this be
considered as a separate project at greater depth and evaluated on its own
merits.
FISCAL IMPACT: The total additional cost of the recommended installation is
$165,000. The current budget includes $41 ,983 for the Data Processing air
condition system and $2,054 for the rehabilitation of the Police Department
air conditioning system which can be used for this project. The additional
amount necessary is approximately $121 ,000. That amount should be
appropriated from the unappropriated General Fund reserves to account number
600-6000 RS61 .
WPC 0020S
Item 15
ATTACHMENT
HVAC SYSTEM DESCRIPTIONS
TERMINAL REHEAT SYSTEM
The first floor of the Police Facility is served by a terminal reheat system.
Air handling units with chilled water coils supply cold air to all spaces.
Each zone is served by a reheat coil controlled by a zone thermostat. All air
from each air handler is cooled sufficiently to satisfy the hottest zone and
then reheated at each individual zone to satisfy all the other zones. This
system is very energy inefficient and hard to control . In some cases the
demand for cooling is as high in winter as summer. An unreasonable load is
placed on the system chiller and its support equipment.
MULTIZONE SYSTEM
The basement of the Police Facility is served by a multizone system. Hot and
cold air are mixed at the air handler for delivery to each zone. Chilled
water is supplied by a reciprocating chiller and hot water is supplied by a
boiler. The heated and chilled water is used to heat and cool air which is
mixed in different proportions at the air handler to provide air at the
correct temperature for each zone. The chiller and boiler units are always
maintained full on. This system is more efficient than a terminal reheat
system.
FAN POWERED VARIABLE AIR VOLUME SYSTEM
This system utilizes a fan powered variable air volume device (VAV box) to
control individual zones. The VAV box restricts the flow of cold air from the
air handler as necessary to satisfy the temperature requirements of the zone.
A small fan within the VAV box mixes the required cold air and return plenum
air to maintain a constant volume of air to the space. The need for heated
air is drastically reduced because heat is picked up from the room itself.
This constant air flow eliminates previous complaints arising from the
perception by users of a decrease in air movement associated with a decrease
in cooling requirement.
The Outside Economy Cycle will modulate return air and outside air to minimize
the system cooling requirements. Because of the facility's 24-hours-a-day
operation, there is a high percentage of total hours in which no cooling other
than outside air will be required.
WPC 0021S