HomeMy WebLinkAboutAgenda Statement 1978/05/23 Item 17 Item No. 17
May 23, 1978
Ordinance 1797
Excavation Grading and Fills
CITY OF CHULA VISTA � :�, , �-. � .
� � � � �� ' COUNCIL AGENDA STATEMEiVT Item No. -��17
5/23/7�- -
For meeting of �����.y
ITEM TITLE Ordinance H1797 Amending Chapter 15. 04 of the City Code in
Regard to Excavation, Grading and Fills
S[CO\D P,�=,";�I';�: ,r-�.�;u ,='.�O�TION
SUBMITTED BY Director of Public Works/City Engineer (���
U �
ITEM EXPLANATION (4/5TH'S VOTE REQUIRED YES X NO )
The last major change in the City' s Grading Ordinance took place on
March 28, 1973. During the past 4-1/2 years of use, the need for
several modifications to the ordinance has become apparent. Addi-
tionally, the City has adopted a new Landscape Manual which in turn
necessitates some of the proposed changes. The Public Works Depart-
ment has reviewed the grading ordinance in its entirety. It has
also received input from selected private engineers and interested
County-c�ide organizations. The major changes from the existing or-
, dinance are outlined as follows:
1. The maximum normal steepness of cut slopes was flattened £rom
1-1/2 : 1 slope to 2 : 1 slope. This change was required .primarily
to facilitate the landscaping and maintenance of slopes. This
change will also bring the local ordinance into conformity with
the Uniform Building Code in regard to slope steepness.
2 . A provision was included that all grading shall be in accordance.
with the City Landscape Manual. .
3. A new section entitled "Inspection of Grading Operations - Re-
sponsibility Therefor" sets fort}i the responsibilities of the
City Engineer, the private engineer, the soils engineer and
the landscape architect to conduct various inspections during
the course of the work.
4. A new section eilc.i�led , "Release of Bonds and Security" re-
quires the certification as appropriate by a private engineer,
soils engineer and landscape architect that the work ,
EXHIBITS -�°a �
Agreement Resolution_ Ordinance� Plat_ Notification List_
Other ENVIRONMENTAL DOCUMENT: Attached Submitted on
fINANCIAL IMPACT
Changes have been made in the proportion of the fee collected at the
time of submittal of the plans for checking. However, only minor
changes have been made in the overall fees collected. No significant
financial impact to the City is anticipated.
STAFF RECOMMENDATION
Place Ordinance on first reading.
. � � Yg .O �� ��
by. the
BOARD/COMMISSION RECOhU1ENDATION �QUnci1
Cit�
�� r Yti'�
��Y ������ Ea;13:.OT
COUNCIL ACTION
�3 - �d.:... ..:::::...._
_ ....
4� Placed on first reading S/16/7S �� '
.n�iu,"�--............................ •
. ,'. , - � , . AGENDA IfiEM "NO. . .10 "
' � � Supplemental �Page 2
For Meeting of 5/16/,78
has been completed in accordance with the plans and the permit
, in accordance with their respective areas of responsibility
(see attached Form PW-E-106) .
5. A new section entitled "Transfer of Responsibility for Ap-
proval" requires that if the private enqineer, soils engineer,
landscape architect, or engineering geologist of record are
. changed during the course of the work, the work shall be
stopped until the replacement has agreed to accept the re-
sponsibility within the area of their technical competence
for approval upon completion of the work.
6. Section 15. 04 . 100 entitled "Building Construction-Land Develop-
ment Permit Required - Prerequisite to Building Permit, " has
been modified to require certification that rough grading has
been completed prior to issuance of a building permit. See
attached forms PW-E-106A and PW-E-106B.
7. Several sections of the existing code deal with the establish-
, ment of a board of land development appeals. These sections
have been eliminated from the oridnance. No appeal to con-
ditions imposed has been made since adoption of the grading x
ordinance. The proposed ordinance provides simply that an
applicant may appeal the City Engineer' s denial or conditions
of approval of a plan directly to the City Council.
8. An upward revision has been made in the amount of fee to be
collected at the time of submittal of the plans. The revi-
sion will assure reasonable compensation to the City when a
development. fails to proceed beyond plan .checking. The overall
permit fee has not been significantly changed. The revised
ordinance requires that 508 of the permit fee be collected at
the time o£ submission of the plans for review by the Public
Works Department. This fee is non-refundable. At the present
time, an application £ee of only $15 is charged for plan check-
ing and review. This revised plan checking fee will generally
reflect the cost incurred by the City.
9 . Various other sections were modified so as to (a) increase the
responsibility by the private technical consultants and (b)
assure a higher degree of conformity with plans, permits and
City standards and regulations.
Private engineers and construction industry representatives who pro-
' vided input during formulation of this ordinance were generally in
' opposition to the change from �l-1/2: 1 maximum slope steepness to a
, 2 : 1 ratio. However, staff has utilized the flatter slope in the '
ordinance for the following reasons: '
1. The 2 : 1 ratio is now used by most agencies in this area; �
2 . The 2: 1 ratio is in conformity with the Uniform Building Code;
3. The 2: 1 ratio is far more practical in terms of installation and
maintenance of landscaping.
4. Flatter slopes are characteristically less subject to structural
failure and erosion.
A steeper-than-standard slope is, however, still permitted since the
proposed ordinance provides for deviations from slope ratio standards
to be approved by the City Engineer when so justified through the
submission of technical supportive data.
Another major area of concern by private engineers and construction
industry representatives involves the timing of landscape planting.
That group was generally in opposition to landscaping slopes prior
to completion of dewlling unit construction. However, in the past�
i147
� , . • ;, . AGENDA ITEM� NO, 10
� Supplemental Page 3
� For Meeting of '�5/16/78
the City has experienced several instances where severe erosion
occurred prior to landscaping but during construction of the
dwelling units. The subsequent repairs and planting were unneces-
• sarily difficult to obtain. Consequently, the proposed ordinance
provides that at least the slopes in excess of 15 feet in height will
� be planted prior to issuance of building permits.
I A copy of this report and proposed ordinance have been sent to those
on the attached notification list indicating that this item will be
on the agenda.
�� 4�
�
* y • , ., , � i7
. , .,, _ �. - > 3- 7�
�ATE:� ., , . . ,
TO: Director of Public �9orks
City of Chula Vista
P. O. Box 1087
Chula Vista, CA 92012
FROM:
SUBJECT: Request for Release of Bonds - Land Development
Permit No.
The Pollowing statements are furnished as evidence of having completed
the land development authorized under the conditions of subject permit:
SOILS ENGZNEER STATEI�IENT
(To be completed i£ Soils Engineer required)
I hereby state that inspections and tests were made by me, or under my
supervision, and that in my professional opinion all embankments have
been compacted to an indicated 8 relative compaction and in
accordance with the earthwork specifications for the project, subject
land development permit, and the applicable sections of the City Code
applying to the above statement.
Signature R.C.E. Date
CIVIL ENGINEER STATEMENT
(TO be completed in all instances)
I hereby state that in my professional opinion all work incorporated in
the gradinq and drainage plans, authorized under subject permit to
include grading, drainage and construction of appurtenant structures
have been constructed to the lines and grades in substantial conformance
with the approved plans and any approved revisions thereto, subject
land development permit and the applicable sections of the City Code
applying to the above statement.
Signature R.C.E. Date
LANDSCAPE ARCHITECT STATEMENT
(To be completed if required)
I hereby state that in my professional opinion all work incorporated
in the landscape and irrigation plans authorized under subject permit
have been constructed in accordance with the �approved plans and any
revisions thereto, subject land development permit and the applicable
sections of the City Code applying to the above statement.
Signature Landscape Architect � Date
I hereby request release of all bonds and deposits posted as guarantee
I - of performance of subject work.
q1 PW-E-106
1 (Rev. 4/76)
I �
T . .� • ' : �, �
• . . , � �/ ... .
. . • ,C' � - � • '
DATE: File : FY 002
EY
T0: Field Inspection
Department of Public works
City of Chula Vista
P. O. BOx 1087
Chula Vista, California 92012
FROM:
SUBJECT: Request for Issuance of Building Permit
Land Development Permit G
Location:
Lot Numbers : .through
The following statements are furnished as evidence of having
completed the rough grading for Land Development authorized
under the conditions of subject permit.
SOILS ENGINEER STATEMENT
(To be completed if Soils Engineer required)
I hereby state that inspections and tests were made by me, or
under my supervision, and that in my professional opinion all
embankments have been compacted to an indicated 8
relative compaction and in accordance with the earthwork speci-
fications for the project, subject land development permit, and
the applicable sections of the City Code applying to the above
statement.
Signature R.C.E. Date
CIVIL ENGINEER STATEMENT
(TO be completed in all instances)
Z hereby state that I have checked the building pads, cut and
fill slopes and related grading as shown on the grading plans
for subject permit. That in my professional judgment the
grading has been completed to the lines and grades in substan-
tial conformance with}the approved plans, land development
permit an3 applicable sections of the Chula Vista Municipal
Code. All work required on Form PW-E-106B has been completed.
Signature R.C.E. Date
I
�� PW-E-106A
. . . . � ;� � _. .
• . • ,. ,r. � - . �
Grading Permit No.
TO:
FROM:
The purpose of this notice is to £ormally notify you that your
building permit will not be issued until the rough grading
phase of the work has been approved.
To obtain an approval of the rough grading phase, the follow-
ing items must be completed and approved:
1 . A compaction report when required by the permit.
2. Form PW-E-106A.
3. All drainage facilities and rough grading per the approved
plans.
4 . The property lines flagged and staked.
5. Al1 cut and fill slopes in excess of 15 feet vertically
planted. Required irigation system shall be installed at
the discretion of the City official. Zn addition, at the
discretion of the City official , any slope that is consid-
ered a potential erosion hazard must also be planted.
When all the above work is completed, please contact the Depart-
ment of Public Works, Construction Inspection Division, tele-
phoned 575-5028 , for an inspection.
PW-E-106B
q1