RESOLUTION N0. EIR-85-3
RESOLUTION OF THE CITY PLANNING COMMISSION
CERTIFYING ENVIRONMENTAL IMPACT REPORT
WHEREAS, the City of Chula Vista has previously certified Master ~
Environmental Impact Report on the Eastlake Planned Community and the Eastlake
I Sectional Planning Area (EIR 81-03 and EIR 84-01), and
WHEREAS, it is necessary to provide certain water delivery systems to
service the Eastlake I Sectional Planning Area, and
tdHEREAS, it has been determined that the City. of Chula Vista should
assume the lead agency role in the preparation of the necessary environmental
documents for these water delivery systems, and
WHEREAS, it was determined that these projects could have a significant
environmental impact and it was therefore necessary to prepare an
Environmental Impact Report on this overall project, and
WHEREAS, the Environmental Review Coordinator of the City of Chula Vista
obtained an estimated cost for the preparation of the EIR and selected WESTEC
Services, Incorporated to prepare the documents, and
IdHEREAS, Eastlake Development Company deposited the necessary funds to
reimburse the Environmental Review Consultant for the preparation of the
documents, and
WHEREAS, a notice of preparation was circulated to the State Clearing-
house, all responsible agencies, agencies with jurisdiction by law, and all
other interested parties for a period in excess of 30 days, and
WHEREAS, after independent review and analysis, a Draft EIR was circulated
for review and analysis through the State Clearinghouse, responsible agencies, ~
agencies having jurisdiction by law, all other interested parties and made ,
available for review at the Chula Vista Library for a period in excess of 30
days, and
WHEREAS, legal Notice of Availability of the Draft Environmental Impact
Report for review and analysis was given through publication in a newspaper of
general circulation and by notification to all property owners within 300 feet
of the project area, and
WHEREAS, a Notice of Completion was filed with the Secretary for Resources
of the State of California, and
WHEREAS, the Planning Commission of the City of Chula Vista held a public
hearing on the adequacy of the Draft Environmental Impact Report on
September 11, 1985, and
WHEREAS, comments were received at said public hearing and have been
responded to in the Final EIR.
NOW, THEREFORE, BE IT RESOLVED as follows:
From the facts presented to the Planning Commission, the Commission finds
that EIR 85-3 has been prepared in compliance with the California
Environmental Quality Act of 1970 as amended, the State CEQA Guidelines, and
the Environmental Review Procedures of the City of Chula Vista.
PASSED AND APPROVED by the City Planning Commission of Chula Vista, 'i
California, this 25th day of September 1985, by the following vote, to-wit:
AYES: Cannon, Carson, Grasser, Green, Guiles, Shipe, Tugenber
NOES: None
ABSENT: None
~
L i
~ is annon, hairman
ATTEST:
ut Smit ecretary