HomeMy WebLinkAbout2013/05/07 Item 14CITY COUNCIL
AGENDA STATEMENT
-~ ~ ~ ~ ~~~ CITY OF
~~ CHULAVISTA
5/07/13, Item~~
ITEM TITLE: RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CHULA
VISTA REJECTING ALL BIDS RECEIVED FOR THE "CHULA
VISTA GOLF COURSE PEDESTRIAN TRAIL AND BRIDGE
IMPROVEMENTS IN THE CITY OF CHULA VISTA, CA (CIP NO.
PR318)" PROJECT AND DIRECTING STAFF TO RE-BID THE
PROJECT _
SUBMITTED BY: DIRECTOR OF PUBLIC WORKS ,rl/f~d~'q_
ASSISTANT DIRECTOR OF ENGINEERING ~ ~,P.(~/
REVIEWED BY: CITY MANAGER
ASSISTANT CITY MANAGER
4/STHS VOTE: YES ^ NO
SUMMARY
On April 24, 2013, the Director of Public Works received fourteen (14) sealed bids for the
"Chula Vista and Golf Course Pedestrian Trail and Bridge Improvements in the City of Chula
Vista, CA (CIP No. PR318)" project. One of the requirements of the bid request was that
bidders list the name of the bridge prefabricator that would supply the bridge for the project. Of
the fourteen bids received, only the sixth- and eighth-ranked bidders listed the bridge
prefabricator in their bid packages. Therefore, staff determined that this requirement was uncleaz
to bidders and hereby recommends, in the best interests of the public, that all bids received be
rejected and that the project be re-bid with improved instructions to bidders.
ENVIRONMENTAL REVIEW
The Development Services Director has reviewed the proposed activity for compliance with the
California Environmental Quality Act (CEQA) and has determined that the proposed action of
rejecting all bids received for a trail and bridge improvement project is not a "Project" as defined
under Section 15378 of the State CEQA Guidelines because said action consists of
administrative activities of government that will not result in direct or indirect physical changes
to the environment. Therefore, pursuant to Section 15060(c) (3) of the State CEQA Guidelines
the rejection of all consultant bids is not subject to CEQA. Thus, no environmental review is
required at this time.
14-1
5/07/13, Item ~~{-
Page 2 of 3
RECOMMENDATION
Council adopt the resolution.
BOARDS/COMMISSION RECOMMENDATION
Not applicable.
DISCUSSION
On April 24, 2013, the Director of Public Works received fourteen (14) sealed bids from the
following contractors:
Bidder
Valley Coast Construction, Inc.
Just Construction
Alvand Construction, Inc.
Blue Pacific Engineering & Construction
Portillo Concrete
Hazard Construction
Ted Enterprises, Inc.
Fordyce Construction
Piperin Corporation
HTA Engineering & Construction, Inc.
Streamline Engineering
Jaycor Construction
PAL General Engineering, Inc.
The Richards Group
Listed Bride Fabricator?
No
No
No
No
No
Yes
No
Yes
No
No
No
No
No
No
Only the sixth- and eighth-ranked bidders listed the bridge prefabricator that would supply the
bridge for the project, as was required in the bid request. However, staff determined that this bid
requirement was not clearly identified, having been placed in an appendix rather than within the
main body of the bid request. The lack of clarity in the bid request is further supported by the
fact that only two bids out of fourteen (approx. 14%) received (those bids received from the
sixth- and eighth-ranked bidders) listed the bridge prefabricator in their bid packages. In light of
the placement of the requirement for the bid submittals and the supporting statistical evidence
that the requirement was unclear, staff recommends that all bids received be rejected in the best
interests of the public and that the project be re-bid with improved instructions to bidders.
DECISION MAKER CONFLICT
Staff has reviewed the property holdings of the City Council and has found no property holdings
within 500 feet of the boundaries of the property which is the subject of this action. Staff is not
independently aware, nor has staff been informed by any City Council member, of airy other fact
that may constitute a basis for a decision maker conflict of interest in this matter.
14-2
5/07/13, Item1
Page 3 of 3
CURRENT YEAR FISCAL IMPACT
The construction cost for the bridge and trail improvements is paid through a $185,000 County
of San Diego Neighborhood Reinvestment Program Grant received through Supervisor Cox's
office. All City staff costs for this project are funded from the General Fund (approximately
$7,800 to date) and represent the City's grant match. The City will incur approximately $2,500
in additional General Fund costs as a result of the proposed action to reject all bids and to re-bid
the project.
ONGOING FISCAL IMPACT:
There are no ongoing fiscal impacts resulting from the proposed action.
ATTACHMENTS
None.
Prepared by: Kirk Anz~wermnn, P.E.. Prlneipal Cini7 Ewgineer. P¢~b7Pe Works Department
J:\Engineer\AGENDA\CAS2013\OS-07-13\PR318 -Reject Bids & Re-BidFTNAL.doc
14-3
RESOLUTION NO. 2013-
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
CHULA VISTA REJECTING ALL BIDS RECEIVED FOR THE
"CHULA VISTA GOLF COURSE PEDESTRIAN TRAIL AND
BRIDGE IMPROVEMENTS IN THE CITY OF CHULA VISTA,
CALIFORNIA (CIP NO.: PR318)" PROJECT AND DIRECTING
STAFF TO RE-BID THE PROJECT
WHEREAS, on April 24, 2013, the Director of Public Works received fourteen (14)
sealed bids for the "Chula Vista and Golf Course Pedestrian Trail and Bridge Improvements in
the City of Chula Vista, California (CIP No.: PR 318)" project; and,
WHEREAS, one of the requirements of the bid request was thaTbidders list the name of
the bridge prefabricator that would supply the bridge for the project; and,
WHEREAS, this bid requirement was not clearly identified, having been placed in an
appendix rather than within the main body of the bid request; and
WHEREAS, the lack of clarity is supported by the evidence that only two bids out of
fourteen (approx. 14%) received (those from the sixth- and eighth-ranked bidders) listed the
bridge prefabricator in their bid packages; and,
WHEREAS, in light of the placement of the requirement for the bid submittals and the
supporting statistical evidence that the requirement was unclear, staff recommends that all bids
received be rejected in the best interests of the public and that, the project be re-bid with
improved instructions to bidders.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Chula
Vista does hereby reject all bids received for the "Chula Vista Golf Course Pedestrian Trail and
Bridge Improvements in the City of Chula Vista, California (CIP No.: PR318)" project and
direct staffto re-bid the project
Presented by
Richard A. Hopkins
Director of Public Works
14-4