HomeMy WebLinkAbout2013/04/23 Item 08CITY COUNCIL
~I~ AGENDA STATEMENT
~~~ CITY OF
~'~~ CHULAVISTA
4/23/2013, Item
ITEM TITLE: PUBLIC HEARING TO CONSIDER WAIVING A MINOR
MATHEMATICAL ERROR IN THE BID RECEIVED FOR THE
"MOSS STREET SEWER IMPROVEMENTS AT RAILROAD
CROSSING (SW272)" PROJECT PER CITY CHARTER SECTION
1009
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CHULA
VISTA WAIVING A MINOR MATHEMATICAL ERROR,
ACCEPTING BIDS, AND AWARDING A CONTRACT FOR THE
"MOSS STREET SEWER IMPROVEMENTS AT RAILROAD
CROSSING (SW272)" PROJECT TO RMV CONSTRUCTION INC. IN
THE AMOUNT OF $224,400, WAIVING CITY COUNCIL POLICY
574-01 AND AUTHORIZING THE EXPENDITURE OF ALL
AVAILABLE CONTINGENCY FIN AN AMOUNT NOT TO
EXCEED $60,000
SUBMITTED BY: DIRECTOR OF PUBLIC WORK `` ~~
ASSISTANT DIREC OF ENGINEERING ~~V ~..~
REVIEWED BY:
SUMMARY
CITY MANA
ASSISTANT CITY ANAGER ~~
4/STHS VOTE: YES ^ NO
On April 3, 2013, the Director of Public Works received nine (9) sealed bids for the "Moss Street
Sewer Improvements at Railroad Crossing (SW272)" Project. The work to be done consists of
the replacement of approximately 265 feet of 10-inch vitrified clay pipe (VCP) with 12-inch
PVC sewer pipe within Moss Street and Industrial Boulevazd. The proposed resolution, if
approved, would: (a) waive a minor mathematical error; (b) awazd a public works contract to
RMV Construction, Inc. in the amount of $224,400; (c) waive Council Policy 574-01; and, (d)
authorize the Director of Public Works to approve change orders up to the contingency amount
of $60,000.
ENVIRONMENTAL REVIEW
The Development Services Director has reviewed the proposed project for compliance with the
California Environmental Quality Act (CEQA) and has determined that the project qualifies for a
Class 2 (c) categorical exemption pursuant to Section 15302 (Replacement or Reconstruction) of
the State CEQA Guidelines because the project consists of replacement of an undersized 10-inch
sewer line with atwelve-inch sewer line. The existing ten-inch sewer line is presently fed by a
12 inch sewer line and connects downstream to a 15-inch sewer line. Therefore, no increase in
sewer capacity is proposed. Thus, no further environmental review is required.
8-1
4/23/2013, Item_~
Page 2 of 4
RECOMMENDATION
Council conduct the public hearing and adopt the resolution.
BOARDS/COMMISSION RECOMMENDATION
Not applicable.
DISCUSSION
The "Moss Street Sewer Improvements at Railroad Crossing (SW272)" Project consists of the
replacement of approximately 265 feet of 10-inch vitrified clay pipe (VCP) with 12-inch PVC
sewer pipe within Moss Street and Industrial Boulevard. The work includes open-trench
construction, jack-and-bore construction below existing railway, sewer line and manhole
improvements, asphalt concrete pavement, removal and disposal of existing improvements,
traffic control, other miscellaneous work, and all labor, material, equipment, and transportation
necessary for the project, and as described in the contract documents.
On April 3, 2013, the Director of Public Works received a total of nine (9) bids for the project.
The following table summarizes the bids received:
CONTRACTOR TOTAL SUBMITTED BID
1 RMV Construction, Inc. -San Diego, CA $224,400*
($230,400 on final bid ro osal
2 Grfco Inc. -Moreno Valley, CA $242,450
3 MJC Construction, Ina -Bonita, CA $280,200
4 Piperin Corporation -San Marcos, CA $289,800
5 Just Construction -San Diego, CA $295,000
6 Blue Pacific Engineering & Construction- San Diego,
CA $309,100
7 Transtar Pipeline Inc. -San Diego, CA $354,200
8 El Cajon Grading & Engineering Co. -Lakeside, CA $367,510
9 Schilling Paradise Inc. - El Cajon, CA $384,5 ] 0
*The submitted bid proposal contained mathematical errors that did not affect the unit price, but affected the
total bid amount. Correction of bid totals did not change the outcome and ranking of the bids.
Staff reviewed the apparent low bid proposal in the amount of $230,400 submitted by RMV
Construction Inc. During review of the RMV Construction bid proposal, staff found the
contractor made a mathematical error that did not affect the unit price, but affected the total bid
amount. The corrected grand total bid amount is $224,400, which is $6,000 less than the total
listed by the contractor in his original proposal.
RMV Construction Inc. has submitted a letter dated Apri14, 2013 (Attachment 1) acknowledging
their mathematical error and agreeing to the lower corrected total bid of $224,400.
The low bid submitted by RMV Construction Inc. is below the Engineer's estimate of $290,000
by $65,600, or approximately 23%. RMV Construction, Inc. has satisfactorily performed
8-2
4/23/2013, Item 2
Page 3 of 4
construction projects of similar scope for the City in the past. RMV Construction, Inc. is a
licensed General Engineering Contractor. Their License No. 892389 is current and active.
Staff reviewed the low bid and determined the bid package is complete, with no errors or
omissions, other than the above-mentioned minor mathematical error. Therefore, staff
recommends waiving the minor mathematical error and awarding a contract in the amount of
$224,400 to RMV Construction, Inc.
The proposed resolution would also authorize the Director of Public Works to approve change
orders over and above existing policy limits. Under City Council Policy No. 574-01, if an
individual change order causes the cumulative increase in change orders to exceed the Director's
authority ("Maximum Aggregate Increase in Change Orders"), then City Council approval is
required. The corresponding maximum aggregate contract increase that may be approved by the
Director of Public Works under Policy No. 574-01 is $18,708, based upon the base contract
amount of $224,400. Approval of the proposed resolution would increase the Director of Public
Works' authority to approve change orders, as necessary, up to the contingency amount of
$60,000, which is an increase of $41,292 over the limits set by Policy No. 574-01. Increasing
the contingency amount would allow staff to continue the project without delay should
unforeseen circumstances resulting in increased project costs arise during the course of
construction, as well as make adjustments to bid item quantities. Unforeseen conditions include
such items as utility conflicts, hazardous materials, unexpected underground conflicts, etc. If the
contingency funds are not used, then they will be returned to the project fund balance.
Wade Statement
The contractors who bid on this project are not required to pay prevailing wages to persons
employed by them for the work performed under this project. However, a "Notice to
Contractors" was sent to various trade publications in order to encourage disadvantaged
businesses to bid on the project.
Disclosure Statement
Attached is a copy of the Contractor's Disclosure Statement (Attachment 2).
DECISION MAKER CONFLICT
Staff has reviewed the property holdings of the City Council and has found no property holdings
within 500 feet of the boundaries of the properties, which are the subject of this action. Staff is
not independently aware, nor has staff been informed by any Councilmember, of any other fact
that may constitute a basis for a decision maker conflict of interest in this matter.
CURRENT YEAR FISCAL IMPACT
A breakdown of the project construction costs is as follows:
FUNDS REQUIRED FOR CONSTRUCTION CONTRACT
A. Base Contract Amount $224,400
B. Contract Contingencies $ 60,000
C. Construction Inspections Staff Costs $ 40,000
D. Desi n Su por[/Survey/Monument Preservation $ 10,000
TOTAL FUNDS REQUIRED FOR CONSTRUCTION CONTRACT $334,400
8-3
4/23/2013, Item ~L'
Page 4 of 4
Sufficient funds aze available in CIP project account SW272 to complete the Moss Street Sewer
Improvements at Railroad Crossing Project. There is no direct fiscal impact to the General Fund
as the Sewer Facility Replacement Fund provides funding for this project.
ONGOING FISCAL IMPACT
Upon completion of the project, the improvements will require only routine City sewer
maintenance, which aze funded through the Sewer Service Fund; therefore, there aze no ongoing
impacts to the General Fund.
ATTACHMENTS
1. Bid Correction Letter from RMV Construction, Inc. dated Apri14, 2013
2. Disclosure Statement from RMV Construction, Inc.
Prepared by: Boushra Salem, Senior Civil Engineer, Public Works Department -Engineering
J: IEngineerlAGENDAICAS2073104-23-131SW272 Award CASdocz
8-4
ATTACHMENT ~ ~~a~2
®, RMVCONSTRUCTIbN
0
Data-04! 04/ 2013
Project Number• SW272
Project Name- Moss St. Sewer Improvements
Mr, William Valle,
RMV Construction Inc, acknowledges the bid discrepancy on item #2 of the submitted bid. We agree with
the $20 per LF inr shoring, and agree to the lower grand total of $224,400.00. We would like to proceed with
the award process. Thanks for your cooperation and we look forward to working. with you. If you have any
questions or concerns please feel free to give ma a call.
Sincerely,
Mike Vasil
President/CEO
X
r
4079 HuerFano Ave, Suite 118 • San Diego California 92117
858-581-3488 PHONE * 858-769-0272 FAX
California license #892389
8-5
Specs.pdf
http://onlineplanservice. com/bidding/SDDT263 59/Specs/Spec s, pdf
ATTACHMENT "a `t 5'~a~-2
CITY OF CIiULA VISTA DISCLOSURE STATEMENT
Pursuant to Council Policy 101-O1, prior to any action upon matters That will require discretionary action by the
CouncIl, Planning Conunission and all other o#Iicial bodies of the City, a statement of aiscloswe of certain
ownership or financial interests, payments, or campaign contributions for a Gity of Chula Vista election nxust be
filed. The following information must be disclosed:
1. List the names of alt persons having a financial interest in the property that is the subject of the
application or the contract, e.g., owner, applicant, contractor, subcontractor, material suppltcr.
/~ /A
2. if any person"` identified pursuant to (I} above is a corporation or partnership, list the names of all
indi~~duals with a $2000 investment in the business {corporation/partnership} entity.
Nan
3. if any person" identified pursuant to {1}above is anon-profit organization or trust, list the names of any
person serving as director of tlxe non-profit organization or as trustee or beneficiary or irustor of the
trust. ~ { gd
I"1 r` _
4. Please identify every person, including any agents, employees, consultants, or independent contractors
you have assigned to represent you before the City in this matter.
~/~
5. Acs any person'" associated with this contract had any financial dealings widx an official** of the City
of Chula Vi/s~ta as it relates to this contract within the past 12 months? Yes_ No~
33
Qi\Hngine¢ing\All Proj~roslSN'1Sw372 p~luss St ~ RR CrossinglContract S Spces\SN272 Finnl Contmct.doc
8_6
21 of 205 3/28/2013 4:05 PM
Specs.pdf
http: //onlineplans ervice. com/bidding/SDDT263 59/Specs/Specs.pdf
if Yes, briefly describe rite nature of dte fmanciat interest the official"* may have in this contract.
6. Have you made a contribution of more than S2~d within the past twelve {l2) months to a cursent
member of the Chula Vista Ci[y Council? No .Yes _ If yes, which Council member?
7. Have you provided more than 530 (or azt item of equivalent value) to an official** of the City of
Chula Vista ut the past twelve (12) months? (This includes being a source of income, money to retire a
legal debt, gifr, loan, etc.) Yes _ No
if Yes, which official*' and what was the nature of item provided?
Date:~~ _
Signature
name
Person is defined as: any individual, firm, co-parmership, joint venture, association, social club,
fraternal organization, corporation, estate, trust, receiver, syndicate, any other county, city,
municipality, district, or other political subdivision, -or any other group or combination acting as a
unit.
** Official includes, but is not limited to: Mayor, Council member, Planning Commissioner; Member of
a board, commission, or committee of the City, employee, or staff members.
35
Q:\.Gngineering'v~.11 Projects\S}MSW272 Moss St l4' RP. CrossingiContract & Specs\SlY2i2 Final Caotract.doc
8-7
22 of 205 3/28/2013 4:05 PM
RESOLUTION NO. 2013-
RESOLUTION OF THE CITY COUNCIL. OF THE CITY OF
CHULA VISTA WAIVING A MINOR MATHEMATICAL
ERROR, ACCEPTING BIDS, AND AWARDING A
CONTRACT FOR THE "MOSS STREET SEWER
IMPROVEMENTS AT RAILROAD CROSSING (SW272)"
PROJECT TO RMV CONSTRUCTION INC. IN THE AMOUNT
OF $224,400, WAIVING CITY COUNCIL POLICY 574-O1 AND
AUTHORIZING THE EXPENDITURE OF ALL AVAILABLE
CONTINGENCY FUNDS IN AN AMOUNT NOT TO EXCEED
$60,000
WHEREAS, on April 3, 2013, the Director of Public Works received nine (9) sealed bids
for the "Moss Street Sewer Improvements at Railroad Crossing (SW272)" Project; and
WHEREAS, the work to be done consists of the replacement of approximately 265 feet
of 10-inch vitrified clay pipe (VCP) with 12-inch PVC sewer pipe within Moss Street and
Industrial Boulevard; and
WHEREAS, the Director of Public Works received nine (9) sealed bids as follow:
CONTRACTOR TOTAL SUBMITTED BID
1 RMV Construction, Inc. -San Diego, CA $224,400*
($230,400 on final bid ro osal)
2 Grfco Inc. -Moreno Valle CA
y, 242 450
$ ,
3 MJC Construction, Inc: -Bonita, CA $280,200
4 Piperin Corporation -San Marcos, CA $289,800
5 Just Construction -San Diego, CA $295,000
6 Blue Pacific Engineering & Construction- San Diego,
CA $309,1.00
7 Transtar Pipeline Inc. -San Diego, CA $354,200
8 EI Cajon Grading & Engineering Co. -Lakeside, CA $367,510
9 Schilling Paradise Inc. - EI Cajon, CA $384,510
*The submitted bid proposal contained mathematical errors that did not affect the unit price, but affected the
total bid amount. Correction of bid totals did not change the outcome and ranking of the bids.
WHEREAS, staff reviewed the apparent low bid proposal in the amount of $230,400
submitted by RMV Construction Inc. During review of the RMV Construction bid proposal,
staff found the contractor made a mathematical error that did not affect the unit price, but
affected the total bid amount. The corrected grand total bid amount is $224,400, which is $6,000
less than the total listed by the contractor in his original proposal; and
a-a
Resolution No.
Page 2
WHEREAS, RMV Construction Inc. has submitted a letter dated April 4, 2013
(Attachment 1) acknowledging their mathematical error and agreeing to the lower corrected total
bid of $224,400; and
WHEREAS, the low bid submitted by RMV Construction, Inc. is below the Engineer's
estimate of $290,000 by $65,600 (23% lower); and
WHEREAS, RMV Construction, Inc. has satisfactorily performed construction projects
of similar scope for the City in the past; and
WHEREAS, staff has reviewed the low bid and recommends awarding the contract to
RMV Construction, Inc. of San Diego, California.
WHEREAS, in order to approve change orders as necessary, staff is requesting City
Council waive Council Policy No. 574-01.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Chula
Vista does hereby waive minor mathematical error, accepts bids; awards the contract for the
"Moss Street Sewer Improvements at Railroad Crossing (SW272)" Project, to RMV
Construction, Inc. in the amount of $ 224,400.
BE IT FURTHER RESOLVED that the City Council of the City of Chula Vista does
hereby waive Council Policy 574-01 and authorize the director of Public Works to approve
change orders, as necessary, up to the contingency amount of $60,000 and expend all available
funds in the project. ///
Presented by
as to
Richard A. Hopkins + ~Cr n R. Goog
Director of Public Works / C ty Attorney
8-9