HomeMy WebLinkAboutReso 1998-19196 RESOLUTION NO. 19196
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CHULA
VISTA APPROVING THE ADDITION OF A CAPITAL
IMPROVEMENT PROJECT TO COMPLETE ENVIRONMENTAL
AND ENGINEERING WORK REQUIRED FOR THE CONSTRUCTION
OF THE SALT CREEK TRUNK SEWER AND APPROPRIATING
$150,000 FROM THE TRUNK SEWER CAPITAL RESERVE
FUNDS (FUND NO. 222) AND $150,000 FROM THE SALT
CREEK SEWER BASIN DEVELOPMENT IMPACT FEE FUND (FUND
NO. 670) TO COVER THE COST OF SAID WORK
WHEREAS, the Salt Creek Trunk Sewer has been proposed for the transport of
wastewater from new developments in eastern Chula Vista and to provide additional capacity
for the existing wastewater collection systems in southern Chula Vista; and
WHEREAS, on December 6, 1994, the City Council established the Salt Creek Sewer
Basin Development Fee to fund a large portion of this trunk sewer; and
WHEREAS, the proposed interceptor will generally parallel Salt Creek and the Otay
Valley River beginning just west of Upper Otay Reservoir and terminating at the City of San
Diego's Metro Sewer west of Interstate 5; and
WHEREAS, approval of this resolution will establish a Capital Improvement Project for
the preliminary design to determine the environmental constraints and alignment for
subsequent final design and construction of the interceptor; and
WHEREAS, preliminary design will also provide an overall project cost and schedule; and
WHEREAS, the overall project cost estimate will include costs for environmental
documentation and mitigation, pipeline final design, and construction; and
WHEREAS, preliminary cost estimates for the overall project costs based on initial
sewer studies indicate that the total project cost is approximately $20 million.
NOW, THEREFORE, BE IT RESOLVED the City Council of the City of Chula Vista does
hereby approve the addition of a capital improvement project to complete environmental and
engineering work required for the construction of the Salt Creek Trunk Sewer.
BE IT FURTHER RESOLVED that $150,000 is hereby appropriated from the Trunk
Sewer Capital Reserve Fund (Fund No. 222) and $150,000 from the Salt Creek Sewer Basin
Development Impact Fund (Fund No. 670) to cover the cost of said work.
Presented by Approved as to form by
P Li 't ireetorM. Kaheny
rney
Resolution 19196
Page 2
PASSED, APPROVED, and ADOPTED by the City Council of the City of Chula Vista,
California, this 6th day of October, 1998, by the following vote:
AYES: Councilmembers: Moot, Padilia, Salas and Horton
NAYS: Councilmembers: None
ABSENT: Councilmembers: Rindone
ABSTAIN: Councilmembers: None
Sh~"MA~ayor~
ATTEST:
~Authelet, City Clerk
STATE OF CALIFORNIA )
COUNTY OF SAN DIEGO )
CITY OF CHULA VISTA )
I, Beverly A. Authelet, City Clerk of Chula Vista, California, do hereby certify that the
foregoing Resolution No. 19196 was duly passed, approved, and adopted by the City Council
at a regular meeting of the Chula Vista City Council held on the 6th day of October, 1998.
Executed this 6th day of October, 1998.