HomeMy WebLinkAbout2012/06/19 Item 04CITY COUNCIL AGENDA STATEMENT ~,~;~ CITY OF CHUTA VISTA 6/19/12, Item "f ITEM TITLE: RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CHULA VISTA ACCEPTING BIDS, AWARDING THE CONTRACT FOR SIDEWALK INSTALLATION ALONG THE SOUTHERLY SIDE OF NAPLES STREET BETWEEN BROADWAY AND FIFTH AVENUE [CIP NO. STL364, FEDERAL PROJECT NO. HSII'L 5203 (032)]" PROJECT TO PORTILLO CONCRETE, INC. IN THE AMOUNT OF $160,571, WAIVING CITY COUNCIL POLICY 574-01, AND AUTHORSZING THE EXPENDITURE OF ALL AVAILABLE CONTINGENCY FUNDS IN AN AMOUNT NOT TO EXCEED $20,000 SUBMITTED BY: DIRECTOR OF PUBLIC WORKS ' REVIEWED BY: CITY MANAGER ASSISTANT CITY ANAGER 5~ 4/STHS VOTE: YES ^ NO SUMMARY On May 23, 2012, the Director of Public Works received six (6) sealed bids for the "Sidewalk Installation along Southerly Side of Naples Street between Broadway and Fifth Avenue [CIP No. STL364, Federal Project No. HSIPL 5203 (032)] project. The project will construct missing sidewalk along the south side of the 500 block of Naples Street. The proposed resolution, if approved, would award the contract for this project to the low bidder, Portillo Concrete, Inc. in the amount of $160,571, waive City Council Policy 574-01, and authorize the expenditure of all available contingency funds in an amount not to exceed $20,000. ENVIRONMENTAL REVIEW The Development Services Director has reviewed the proposed project for compliance with the California Environmental Quality Act (CEQA) and has determined that the project qualifies for a Class 1 categorical exemption pursuant to Section 15301 (Existing Facilities) of the State CEQA Guidelines because the proposed sidewalk installation involves negligible or no expansion of an existing use. Thus, no further CEQA environmental review is required. In addition, the Development Services Director has reviewed the proposed project for compliance with the 4-1 6/19/12, Item Page 2 of 4 National Environmental Policy Act (NEPA) in conjunction with the California Department of Transportation (Caltrans), the state department designated as Lead Environmental Agency by the U.S. Department of Transportation, Federal Highway Administration (FHWA) for federally funded street projects. It was determined that the project qualifies for a categorical exclusion pursuant to Title 23 Code of Federal Regulations (CFR) Section 771.117(d); activity:(d)(1) [Modernization of a Street by resurfacing, restoration, rehabilitation or reconstruction]. Thus, no further NEPA environmental review is required. RECOMMENDATION Council adopt the resolution. BOARDS/COMMISSION RECOMMENDATION Not applicable. DISCUSSION This project is included in the FY2010/FY2011 Capital Improvement Program. budget to construct missing infrastructure along the south side of the 500 Block of Naples Street. This project is funded under the Highway Safety Improvement Program (HSIP), Cycle 3 and TransNet funds. Caltrans authorized funding for Preliminary Engineering on November 8, 2010 and for Construction on May 18, 2012. The project includes the construction of curb, gutter, and sidewalk, ADA pedestrian ramps with truncated domes, and driveways The project is located along the south side of Naples Street between Broadway and Fifth Avenue in the Southwest Major Planning azea of Chula Vista. Prior to approving funding for the project, Federal Highway Administration staff conducted a walking audit in and around the project area and determined that a need existed to complete a safe pedestrian path between Fifth Avenue and Broadway. This project only received funding to construct the street improvements along the south side of Naples; staff is currently pursuing a grant to complete the sidewalk improvements along the north side of Naples Street. The project will serve Harborside and Rice Elementary Schools, Chula Vista Adult School, and the multi-family residential apartments located on both sides of Naples Street. On May 23, 2012, the Director of Public Works received the following six (6) sealed bids 4-2 6/19/12, Item ~' Page 3 of 4 CONTRACTOR SUBMITTAL EVALUATION BID TOTAL SUBMITTED 1 Portillo Concrete, Inc. -Lemon Requirements are met $160,571.00 Grove, CA 2 Palm Engineering Construction Re uirements aze met q $165,556.00 Company, Inc. -San Diego, CA Aria Design & Construction (1)Missing Certificate of Notification 3 Corp. -San Diego, CA to Contractor, (2) Signature $178,853.25 Disclosure of Lobb in Activities Tri-Group Construction and 4 Development, Ina -San Diego, Requirements are met $199,955.00 CA Corrected amount RMV Construction, Ina -San 1-Missing Noncollusion Affidavit, 2- $177,840.28 5 Diego, CA Math error ($204,041.08 originally submitted Koch-Armstrong General Corrected amount 6 Engineering, Inc. -Lakeside, Math error $207,360.80 ($207,383.80 originally CA submitted) The low bid submitted by Portillo Concrete, Inc. is below the Engineer's estimate of $208,852 by $48,281 (23% below the Engineer's estimate). Portillo Concrete, Inc. has installed similaz street improvement projects in the City with satisfactory performance. Staff reviewed the low bid and determined that the bid package is complete, with no errors or omissions. Therefore, staff recommends awarding the contract to Portillo Concrete, Inc. in the amount of $160,571. Portillo Concrete, Inc. is a Licensed General Engineering (Class A), General Building Contractor (Class B) and Concrete Contractor under California License No. 680144. Their license status is current and active per the Department of Consumer Affairs' Contractor State License Board. The proposed resolution would also authorize the Director of Public Works to approve change orders over and above existing policy limits. Under City Council Policy No. 574-01, if an individual change order causes the cumulative increase in change orders to exceed the Director's authority ("Maximum Aggregate Increase in Change Orders"), then City Council approval is required. The corresponding maximum aggregate contract increase that may be approved by the Director of Public Works under Policy No. 574-01 is $14,240. Approval of tonight's resolution would increase the Director of Public Works' authority to approve change orders, as necessary, up to the contingency amount of $20,000, an increase of $5,760 over Policy No. 574-01. Increasing the contingency funds will allow staff to continue the project without delay should unforeseen circumstances resulting in increased project costs arise during the course of construction, as well as make adjustments to bid item quantities. Unforeseen conditions include such items as utility conflicts, hazardous materials, other unexpected underground conditions, eta If the contingency funds are not used, then they will be returned to the project fund balance Disclosure Statement Attachment 1 is a copy of the contractor's Disclosure Statement. 4-3 6/19/12, Item Page 4 of 4 Waee Statement The sources of funding for this project are from the Highway Safety Improvement Program (HSIP) Program grant and TransNet (grant match). Contractors bidding this project are required to pay Federal and or State of California general prevailing wages to persons employed by them for the work under this project. DECISION MAKER CONFLICT Staff has reviewed the property holdings of the City Council anal has found no property holdings within 500 feet of the boundaries of the properties, which are the subject of this action. CURRENT YEAR FISCAL IMPACT A breakdown of the project costs is as follows: FUNDS REQUII2ED FOR CONSTRUCTION A. Contract Amount $160,571 B. Contingencies (approximately 12%) $ 20,000 C. Construction Inspection Staff Time (15%) $ 24,086 D. Desi Support/Survey/Monument Preservation $ 10,000 TOTAL FUNDS REQUIRED FOR CONSTRUCTION $214,657 Sufficient funds are available in the CIP project account STL364. There is no direct fiscal impact to the General Fund as the Transnet funds and the HSIP funds are appropriated in the project. ONGOING FISCAL IMPACT: Upon completion of the project, annual operating and maintenance cost is estimated to be lower than programmed. ATTACHMENTS 1. Contractor's Disclosure Statement Prepared by.' Boushra Salem, P.E., Senior Civil Engineer, Public Works Department J:\EngineerWGENDA\CAS2012\06-19-12\STL364 CAS AwardREV.doc 4-4 ,~rr,mt~N-r i CITY OF CHULA VISTA DISCLOSURE STATEIY1tE1\"T Pursuant to Council Policy 101-O1, prior to any action upon matters that will require discretionary action by the Council, Planning Commission and all other official bodies of the City, a statement of disclosure of certain ownership or financial interests, payments, or campaign contributions for a City of Chula Vista election must be filed. The following information must be disclosed: 1. List the names of all persons having a ftnancial interest in the property that is the subject of the application or the contract, e.g., owner, applicant, contractor, subcontractor, material supplier. ~R-L•o ~~ t l l ~ o I tt ~a r~(zT~ t t,o 2. If any person* identified pursuant to (1) above is a corporation or partnership, list the names of all individuals with a $2000 investment in the business (corporation partnership) entity. (Y1 ~~ ~~ rrrt c t,v T~.~ ~C2iLll(~ 3. If any person* identified pursuant to (1) above is a non-profit organization or trust, list the names of any person serving as director of the non-profit organization or as trustee or beneficiary or trust~of the trust. 4. Please identify every person, including any' agents, employees, consultants, or independent contractors you have assigned to represent you before the City in this matter. ~' 5. Has any person* associated with this contract had any financial dealings with an official** of the City of Chula Vista as it relates to this contract within the past 12 months? Yes_No (~~~s 22 Q~~Fn~neerinSWlProlcca~STL1SII.364 Naples(Broadway-5th)~SpecS~STI364FedSpecs-5nai.doc 4-5 If Yes, briefly describe the nature of the financial interest the official** may have in this contract. 6. Have you made a contribution of more than $250 within the past, twelve (12) months to a current member of the Chu]a Vista City Council? No _ Yes _ If yes, which Council member? 7. Have you provided more than $34D (or an item of equivalent value} to an official** of the City of Chula Vista in the past twelve (12) months? (This includes being a source of income, money to retire a legal debt, gift, loan, etc.) Yes _ No _ which officiai** and whatwas the nature of item provided? Date: ~J ~ I ~' ~r Lr / 1 V~'~"" ~~ Signature of Contractor/Applicant ~ ~w~O~it \ lb Print or type name of Contractor/Applicant Person is defined as: any individual, firm, co-parhtership, joint venture, association, social club, fraternal organization, corporation, estate, trust, receiver, syndicate, any other county, city, municipality, district, or other political subdivision; -or any other group or combination acting as a unit. ** Official includes, but is not limited to: Mayor, Council member, Planning Commissioner, Member of a boazd, commission, or committee of the City, employee, or staffmembers. 23 QaEa~immn~Wl ProjearlSTUSTL364 Napts(Broadway-SthjlSpecslST1364Fed5pecs-finat.doc 4-6 RESOLUTION NO. 2012- RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CHULA VISTA ACCEPTING BIDS, AWARDING THE CONTRACT FOR SIDEWALK INSTALLATION ALONG THE SOUTHERLY SIDE OF NAPLES STREET BETWEEN BROADWAY AND FIFTH AVENUE [CIP NO. STL364, FEDERAL PROJECT NO. HSIPL 5203 (032)]" PROJECT TO PORTILLO CONCRETE, INC. IN THE AMOUNT OF $160,571, WAIVING CITY COUNCIL POLICY 574-01, AND AUTHORIZING THE EXPENDITURE OF ALL AVAILABLE CONTINGENCY FUNDS IN AN AMOUNT NOT TO EXCEED $20,000 WHEREAS, on May 23, 2012, the Director of Public Works received six (6) sealed bids for the "Sidewalk Installation along Southerly side of Naples Street between Broadway and Fifth Avenue in the City of Chula Vista California"; and WHEREAS, the Director of Public Works received six (6) bids as follows: CONTRACTOR SUBMITTAL RESULTS TOTAL SUBMITTED 1 illo Concrete, Inc. - Lemon Grove, Requirements are met $160,571.00 CA 2 Palm Engineering Construction Requirements are met $165,556.00 Company, Inc. - San Diego, CA 1-Missing Certificate of 3 Aria Design & Construction Corp. - San Notification to Contractor, $178 853.25 Diego, CA 2-Signature Disclosure of , Lobb in Activities 4 Tri-Group Construction and Requirements are met $199 955.00 Development, Inc. - San Diego, CA , Corrected amount 1-Missing Noncollusion $177,840.28 5 RMV Construction - San Diego, CA Affidavit, 2-Math error ($204,041.08 originally submitted Corrected amount Koch Armstrong General Engineering, $207,360.80 6 Inc. - Lakeside, CA Math error ($207,383.80 originally submitted) WHEREAS, the low bid submitted by Portillo Concrete, Inc. is below the Engineer's estimate of $208,852 by $48,281, or approximately 23.0%; and 4-7 Resolution No. Page 2 WHEREAS, Portillo Concrete Inc. has installed similar street improvement projects in the City with satisfactory performance; and WHEREAS, staff has reviewed the low bid and recommends awarding a contract to Portillo Concrete, Inc.; and WHEREAS, in order to approve change orders as necessary, staff is requesting City Council waive Council Policy No. 574-01. NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Chula Vista does hereby accept bids and award a contract for the "Sidewalk Installation along Southerly side of Naples Street between Broadway and Fifth Avenue CIP No. STL364 (Federal Project No. HSIPL 5203 (032) Project to Portillo Concrete, Inc. in the amount of $160,571; and. BE IT FURTHER RESOLVED, that the City Council of the City of Chula Vista does hereby waive Council Policy 574-01 and authorize the Director of Public Works to approve change orders, as necessary, and expend all available contingency funds in an amount not to exceed $20,000 Presented by Richard A. Hopkins Director of Public Works 4-8