Pacific Engineers, the contractor for constructing the improvements
at Halecrest and Hilltop-Telegraph Canyon Parks, has requested a
20-day extension of time to complete their contract. The project
was to be completed on June 12, 1973. Their request for a 20-day
extension is based upon additional time required for the construction
of a retaining wall not covered in the original contract and delays
caused by relocation of utilities and work being performed by City
forces.
The Division of Engineering has determined that the 20-day extension
is justified. The extension of time, if granted, will change the
contract completion date to July 3, 1973.
ATTACHED: Resolution [x] Ordinance [ ] Agreement [ ] Plat [ ]
See EXHIBITS [ X] No. 1
Financial Statement:
N.A.
Commission-Board Recommendation:
N.A.
Department Head Recommendation:
Recommends approval of the extension of 20 days to the contract,
changing the contract completion date to July 3, 1973. The Director
of Parks & Recreation concurs with the recommendation.
City Manager Recommendation:
Concur with Department Head
~~~~