HomeMy WebLinkAboutAgenda Statement 1973/05/15 Item 09aAGENDA ITEM N0. [ ga )
CHULA VISTA CITY COUNCIL MEETING OF: May 15, 1973
ITEM TITLE: Resolution - Granting Extension of Time to Pacific Engineers
for Construction of Parking Lots and Parking Facilities,
Halecrest and Hilltop-Telegraph Canyon Parks
INITIATED BY: Director of Public Works/City Engineer
RAC'K(;RnliNil
Change in contract #1 for park improvements in Halecrest and Hilltop-
Telegraph Canyon Parks requires additional work to the improvement of
the Telegraph Canyon drainage channel. Pacific Engineers has requested
four additional days to perform their extra work.
The Division of Engineering has determined that the 4-day extension is
justified, The extension of contract time, if granted, will change the
contract completion date to June 12, 1973.
ATTACHED: Resolution [ ~ Ordinance [ ] Agreement [ ] Plat [ ]
See EXHIBITS [X] No. 1
Financial Statement:
N.A.
Commission-Board Recommendation:
N.A.
Department Head Recommendation:
Recommends approval of the extension of 4 working days to the contract,
changing the contract completion date to June 12, 1973.
City Manager Recommendation: Concur