HomeMy WebLinkAboutAgenda Statement 1973/05/08 Item 06AGENDA ITEM~NO. [ 6 ]
CHULA VISTA CITY COUNCIL MEETING OF: May 8, 197 3
ITEM TITLE: Resolution - Granting Extension of Time on "J" Street Storm
Drain and Sewer Project
INITIATED BY: Director of Public Works/City Engineer
BACKGROUND
Hubbard Construction Company has submitted a letter requesting
an extension of time of 6 working days for the construction of
storm drain and sewer facilities on "J" Street from East Park
Lane to Church Avenue.
The project is 98% completed. The Division of Engineering
recommends an additional extension of time of 11 working days
because of inclement weather and adverse working conditions.
All of the underground work has been completed. Surface clean up
is in progress along with placing concrete for the top portion
of the cleanout structures and curb inlet boxes. The additional
extension of time, if granted, will change the contract completion
date to May 11, 1973.
ATTACHED: Resolution [X] Ordinance [ ] Agreement [ ] Plat [ ]
See EXHIBITS [~] No. 1
Financial Statement:
Commission-Board Recommendation:
Department Head Recommendation:
N.A.
N.A.
Recommends approval for granting an extension of time of 11 working
days and changing the contract completion date to May 11, 1973.
City Manager Recommendation:
Concur
/' ~~~