CHULA VISTA CITY COUNCIL MEETING OF: April 24, 1973
ITEM TITLE: Resolution - Granting an Extension of Time, Shuffleboard
Courts, Norman Park Center
INITIATED BY: Director of Public Works/City Engineer
BACKGROUND
T. B. Penick ~ Sons, Inc. has submitted a letter requesting an extension
of contract time to complete the shuffleboard courts at Norman Park
Center. They request an extension of time due to inclement weather.
In addition, the Director of Parks and Recreation has arranged for
additional work to be performed.
The Division of Engineering has verified 17 working days of inclement
weather and has determined that a 20 day extension of time is justified.
An additional 5 days is necessary for the scheduling of the added work
of honing the two courts and cutting grooved markings into the scoring
triangle.
The extension of time, if granted, will extend the contract completion
date to May 4, 1973.
ATTACHED: Resolution [ ] Ordinance [ ]
Financial Statement: N.A.
Commission-Board Recommendation: :1,A,
Department Head Recommendation:
Agreement [ ] Plat [ ]
See EXHIBITS [X] No. 1
Recommends approval of the extension of 25 working days and changing the
completion date of the contract to May 4, 1973.