HomeMy WebLinkAboutAgenda Statement 1972/11/21 Item 05Agenda Item No. 5
November 21, 1972
CHULA VISTA CITY COUNCIL MEETING OF: November 21, 1972
ITEM TITLE: Resolution - Granting Extension of Time for "J" Street Widening,
I-5 Freeway to East Park Lane
INITIATED BY: Director of Public Works/City Engineer `~---~
~~
BACKGROUND:
On November 9, 1972, T. B. Penick & Sons, Inc., 864 - 34th
Street, San Diego 92102, contractor for the widening project
on "J" Street between I-5 Freeway and East Park Lane, sub-
mitted a letter requesting a time extension of 40 days. The
contractor stated that additional time is warranted due to
delay in commencement of work because of utility relocations,
delays by utility crews after commencement of work and
inclement weather.
Under the contract, the contractor is to complete his work
by November 26, 1972. The reasons for the requested 40-day
delay have been investigated by the Engineering Division and
have been verified as reasonable. A 40-day extension of time,
if granted, will extend the completion date to January 5, 1973.
ATTACHED: Resolution [X] Ordinance [ ] Agreement [ ] Plat [ ]
See EXHIBITS [X] No~ 1
Financial Statement:.
N.A.
Commission-Board Recommendation:
N.A.
Department Head Recommendation:
Recommends granting of 40 days extension of time to January 5,
1973.
City Manager Recommendation:
Recommend approval