Loading...
HomeMy WebLinkAboutAgenda Statement 1972/11/14 Item 10Item No. 10 November 14, 1972 AGENDA ITEM NOo [10] CHULA VISTA CITY COUNCIL MEETING OF: November 14, 1972 ITEM TITLE: Resolution - Granting Extension of Time for Installation of Gravity Sewer and Pump Station in Hilltop Drive between "L" Street and Donahoe Street INITIATED BY Rnr.xr,Rnrnvn• Director of Public Works/City Engineer ~= On November 7, 1972, the contractor for the installation of the sewer and pump station in Hilltop Drive between "L" Street and Donahoe, submitted a letter requesting a time extension of 8 days for the subject project. The contractor stated that the additional time is requested due to three days lost during in inclement weather, and five days lost time in locating special pipe fittings required for the pumping station. Under the contract, the contractor was to commence work on September 18, 1972, and to complete his work by November 16, 1972. Delays due to weather and parts availability have been confirmed by the Department of Public Works. The Director of Public Works recommends an 8-day extension of time as requested. If granted, the new completion deadline will be November 24, 1972. ATTACHED: Resolution [X] Ordinance [ ] Agreement [ ] Plat [ ] See EXHIBITS [X ] Noo 1 Financial Statement:. N.A. Commission-Board Recommendation: N.A. Department Head Recommendation: Grant 8-day extension to November 24, 1972, City Manager Recommendation: Approval of extension CC/~