HomeMy WebLinkAboutReso 1987-13033 RESOLUTION NO. 13033
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
CHULA VISTA APPROVING EXTENSION OF CONTRACT
TIME FOR THE EASTLAKE ASSESSMENT DISTRICT 85-2
PROJECTS
The City Council Of the City of Chula Vista does hereby
resolve as follows:
WHEREAS, on April 14, 1987, the City Council by
Resolution No. 12979 approved an extension of contract time for
the four projects contained in the EastLake Assessment District
85-2, and
WHEREAS, the four contracts were extended to May 15,
1987, due to a delay in the delivery of a telemetry cable to be
installed by each contractor, and
WHEREAS, the telemetry cable arrived the last week of
April as promised by the supplier, Aero K.A.P., Inc. of Los
Angeles, however, the cable was not color coded as specified and
required by the Otay Water District, and
WHEREAS, the cable manufacturer (American Insulated Wire
Corp.), can not deliver replacement cable until the second week
of June 1987, and
WHEREAS, the Otay Water District, in a letter dated
May 8, 1987, recommends a contract time extension for the
projects to July 31, 1987 so that by extending the contract times
an additional month more than required for the telemetry cable to
arrive and be installed, the contractors will be able to correct
any problems which may show up and will have to be corrected.
NOW, THEREFORE, BE IT RESOLVED that the City Council of
the City of Chula Vista does hereby approve an extension of
contract time for the EastLake Assessment District 85-2 projects
to and until July 31, 1987.
Presented by Approved as to form by
Joh P. Li of D. Richard Rudolf ant
Pub ks/City Engineer City Attorney
2884a
ADOPTED AND APPROVED BY THE CITY COUNCIL OF THE CITY OF
CHULA VISTA, CALIFORNIA, this 19th day of May
19 87 , by the following vote, to-wit:
AYES: Councilmembers Malcolm, McCandllss, Cox, Moo~:e,
NAYES: Councilmembers None
ABSTAIN: Counci 1 members No~e
ABSENT: Councilmembers None
~o~ul~
Mayor of
~ i y ~l~rk~
S..FE OF CALIFORNIA )
COUNTY OF SAN DIEGO ) sS.
CITY OF CHULA VISTA )
I, JENNIE M. FULASZ, CMC, CITY CLERK Of the City of Chula Vista, California,
DO HEREBY CERTIFY that the above and foregoing is a full, true and correct copy of
RESOLUTION NO. 13033
,and that the some has not been amended or repealed,
DATED
Cify Clerk
CrlY OF
CHULA VIS'I'A
CC-660
BOX 87483 · SAN DIEGO CALIFORNIA 92138 · {tjl 9) 4502~800
9747 OLSON DRIVE · SAN DIEGO CALIFORNIA 9212~
April 29, 1987
City of Chula Vista
Engineering Dept.
276 Fourth Ave.
Chula Vista, CA 92010
Attn: Mr. John P. Lippitt
Ref. Project: Eastlake Pump Station
980 Zone, Phase II
Eastlake Water & Sewer Piping III A
Assessment District 85-2
Dear Mr. Lippitt:
This letter is in regards to the telemetering wire for the above
referenced projects. Otay District approved a particular wire
manufactured by American Insulated Wire Corporation. The wire
was specified with a special color code, special insulation and
coating.
This wire was pruchased through Aero K.A.P., Inc. in Los Angeles;
Mr. Bob Stabler; 1-818-574-1704.
The manufacturer took an exceptionally long time to make this
wire.
We understand that all three projects at Eastlake received the
same wire and it was all manufactured incorrectly. The six pairs
were not color coded. The pairs were only numbered.
We immediately checked with Otay Water District for approval to
use the wire as received.
The wire was unacceptable to the District and replacement wire
was immediately ordered.
Attached, please find American Insulated Wire Corporation letter
dated April 23, 1987 which is the latest information we have on
delivery of the replacement wire.
We would very much like to make some kind of arrangements to file
a Notice of Completion on these two pro3ects. We would agree to
the City witholding twice the value of the telemetering wire
until it was completed and accepted.
If you have any other suggestions, we would like to discuss them.
Very truly yours,
OLSON CONSTRUCTION COMPANY
T.N. Cooper
Pro3ect Manager
TNC/kk
cc: Otay Water district
Eastlake Development
File
AMERICAN c i v s D
INSULATEO WIRE CClRP,
APR 27 1987
0LSON CONStRiJC~ION C0.
Apr~Z 23, ~987
OZsen Construction Co.
P, O, Box 87483
San D~ego, CA 92~38
A~n: ~, Tom Coope~
Dear Mr. Cooper:
This is in response to your phone call concerning the delivery
of Aero Kap's replacement order; pleasebe advised that our
Production Facility estimates the delivery of the replacement
to be the second week of June, 1987.
As you may or may not be aware of the specifications were mis-
interpreted at the factory and the wire, while it was completed
on time, was the wrong color code. We have authorized Aero Kap
to return the wire to American at a great loss to us since this
wire will have to be scrapped.
I can understand your problem with~the City questioning what wen~
wrong. Therefore, I am writing to you to advise that while we
shipped on a timely basis it was the wrong color code and Aero
Kap advised me that the City cannot use this wire although my
Engineering People advised me that it is color coded quite dis-
tinctly and it could'be used although it is not exactly to spec.
~; ..= , Very truly yours,
~ AMERICAN INSULATED WIRE CORP.
Georg~QeA.~e
GAL:fr
cc: Gil Dubois
Maria Varejao
Bruce Wasser
10595 JAMACHA BOULEVARD, SPRING VALLEY, CALIFORNIA 92078
TELEPHONE: 462-2222, AREA CODE 619
Mr. Roberto Saucedo
Department of Public Works
276 Fourth Avenue
Chula Vista, CA 92010
Subject: Contract Time Extensions
EastLake Business Park, Contract IIIA- W.O. 1653
980 Zone Pump Station - W.O. 1701
20" Offsite Water Main - Contract IIIB - W.O. 1702
5 MG Reservoir - W.O. 1701
Dear Mr. Saucedo:
Earlier this week you requested a response from me concerning
time extensions for the subject projects. You also requested I
consider an alternative to accepting the projects prior to in-
stallation of the telemetry cable which is scheduled to arrive
the first week of June. In reference to the latter, District
staff agrees with my decision to postpone acceptance until the
cable arrives, is installed, and tested satisfactorily and all
other related work on the projects are complete.
As you know, the District and Olson Construction Company are in
the process of starting up the pump station. At this time, a few
electrical problems have to be resolved to continue start-up oper-
ations next week. Yesterday, a 4160 volt to 110 volt step-down
transformer blew out. This item will take six to eight weeks to
replace. Also, 24-volt power to the Murphy control panel was not
functioning properly. During running of the diesel engine, over-
heating occurred which has to be resolved.
As you can see, it is very difficult to estimate a completion date
for these projects with so many unknowns. My best attempt is to
pick some time in July, say July 31, 1987, to allow for the trans-
former to be replaced. At that time, the items in question "should"
be resolved and the projects ready to accept. Some may very well
be ready to accept prior to that date.
Please call if you have questions.
Construction Engineer
LJD:cp
CC: Tom Cooper, Olson Construction Co.
Curt Smith, EastLake Development Co.