HomeMy WebLinkAboutAgenda Statement 1973/02/13 Item 13AGENDA ITEM N0. [ 13 ]
CHULA VISTA CITY COUNCIL MEETING OF: February 13, 1973
ITEM TITLE: Resolution - Granting an Extension of Time for Traffic
Signal Installation and Intersection Modification
Gas Tax Project #174
INITIATED BY: Director of Public Works/City Engineer /~ l ; ~;,/
t~ :.
BACKGROUND
On January 7, 1973, Perry Electric Company, contractor for the in-
stallation of traffic signals and intersection modification at Broadway
and "H" Street, Broadway and "E" Street and Fourth Avenue and "C"
Street, submitted a letter requesting an extension of time on his
contract of 31 working days. The contractor stated that additional
time is warranted due to the following delays:
1. Inclement weather 17 days
2. Utility relocation 3 days
3. Pipe manufacturer 4 days
4. Traffic signal equipment delivery 7 days
Total 31 days
The request for the 31 day extension has been investigated by the
Division of Engineering and has been verified as being reasonable.
The 31 day extension, if granted, will extend the completion date of
the contract to April 3, 1973.
ATTACHED: Resolution [X] Ordinance [ ] Agreement [ ] Plat [ ]
See EXHIBITS [X] No. 1
Financial Statement:
N.A.
Commission-Board Recommendation:
N.A.
Department Head Recommendation:
Recommends approval of the request extending the contract 31 working
days and changing the completion date to April 3, 1973.
City Manager Recommendation:
Concur with Department Head
~~ ~~~