HomeMy WebLinkAboutAgenda Statement 1973/01/23 Item 07AGENDA ITEM N0. [ 7 ]
CHULA VISTA CITY COUNCIL MEETING OF: January 23 , 1973
ITEM TITLE: Resolution - Granting an Extension of Time for Hilltop Drive-
Palomar Street Widening - Gas Tax Project #147
INITIATED BY: Director of Public Works/City Engineer ~~ . . -- ~.-,
nnrYr_nnrrntn
On January 4, 1973, W. H. Ledbetter and Sons, 4902 Market Street,
San Diego 92102, contractor for the widening project on Hilltop
Drive from Palomar Street south and on Palomar Street from Third
Avenue to Hilltop Drive, submitted a letter requesting an extensic
of time on his contract of 9 working days. The contractor stated
that additional time is warranted due to delays caused by
inclement weather. Under the contract, the work is to be
completed by February 1, 1973.
The request for the 9 day extension has been investigated by the
Division of Engineering and has been verified as reasonable.
The 9 day extension of time, if granted, will extend the
completion date of the contract to February 14, 1973.
ATTACHED:
Ordinance Agreement [ ] Plat [ ]
Resolution [ X] [ ]
See EXHIBITS [X] No. 1
Financial Statement:
N.A.
Commission-Board Recommendation:
N.A.
Department Head Recommendation:
Recommends approval of the request extending the contract nine (9)
working days and changing the completion date to February 14, 1973.
City Manager Recommendation: Concur
i