HomeMy WebLinkAboutReso 1973-6742RESOLUTION NO. 6742
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CHULA
VISTA GRANTING AN EXTENSION OF TIME FOR THE COMPLETION
OF TRAFFIC SIGNAL INSTALLATION AND INTERSECTION
MODIFICATION - GAS TAX PROJECT #174
The City Council of the City of Chula Vista does hereby
resolve as follows:
WHEREAS, the contractor for the installation of traffic
signals and intersection modification at Broadway and "H" Street,
Broadway and "E" Street and Fourth. Avenue and "C" Street has re-
quested an extension of time on his contract for a period of 31
working days, and
WHEREAS, the request stipulates the following conditions
causing the delays:
1. Inclement weather 17 days
2. Utility relocation 3 days
3. Pipe manufacturer 4 days
4. Traffic signal equipment delivery 7 days
Total 31 days
and
WHEREAS, the Division of Engineering recommends said
extension as a reasonable period of time, which will now set the
completion date of the contract at April 3, 1973.
NOW, THEREFORE, BE IT RESOLVED by the City Council of
the City of Chula Vista that the time for the completion of the
contract for the installation of traffic signals and intersection
modification - Gas Tax Project #174 be, and the same is hereby
extended to and until April 3, 1973.
Presented by Approved as to form by
~,. ' /, /
//
Lane F. Cole, Director of George Lindberg, City Atto y
Public Works
ADOPTED AND APPROVED by the CITY COUNCIL of
VISTA, CALIFORNIA, this 13th day of February
the following vote, to-wit:
the CITY OF CHULA
19 73 , by
AYES : Councilmen Scott, Hobel, Hamilton, Hyde, Egdahl
NAYES: Councilmen None
ARRF.NT• ('nnnni lman Nnna
AT T:
STATE OF CALIFORNIA )
COUNTY OF SAN DIEGO ) ss.
CITY OF CHULA VISTA )
I, , City Clerk of the City of
Chula Vista, California, DO HEREBY CERTIFY that the above is a full,
true and correct copy of Resolution No. , and that the same has not
been amended or repealed. DATED
City Clerk