HomeMy WebLinkAboutReso 1973-6741RESOLUTION N0. 6741
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CHULA
VISTA GRANTING AN EXTENSION OF TIME FOR THE COMPLETION
OF THE "J" STREET STORM DRAIN AND SEWER PROJECT
The City Council of the City of Chula Vista does hereby
resolve as follows:
WHEREAS, the contractor for the "J" Street storm drain
and sewer project has requested an extension of time for a period
of 11 working days because of delays caused by inclement weather,
and
WHEREAS, in addition, the Public Works Department believes
that an additional 12 working days extension should be granted as
a result of sandy soil conditions existing within the storm drain
trench, and
WHEREAS, based upon both conditions the Division of
Engineering recommends that an extension of 23 working days be
granted which would establish the completion date of the contract
at March 23, 1973.
NOW, THEREFORE, BE IT RESOLVED by the City Council of
the City of Chula Vista that the time for the completion of the
contract for the "J" Street storm drain and sewer project be, and
the same is hereby extended to and until March 23, 1973.
Presented by
~~~
ane F. Cole, Director of
Public Works
Approved as to form by
~~
~',~ ~
George Lin berg, City Attor
ADOPTED AND APPROVED by the CITY COUNCIL of the CITY OF CHULA
VISTA, CALIFORNIA, this 13th day of February , 19 73 . by
the following vote, to-wit:
AYES : Councilmen Scott, Hobel, Hamilton, Hyde, Egdahl
NAYES: Councilmen None
AB:
AT `.
STATE OF CALIFORNIA )
COUNTY OF SAN DIEGO ) ss.
CITY OF CHULA VISTA )
I , City Clerk of the City of
Chula Vista, California, DO HEREBY CERTIFY that tandabhat theasamelhas not
true and correct copy of Resolution No. ,
been amended or repealed. DATED
City Clerk