HomeMy WebLinkAboutAgenda Statement 1975/04/08 Item 04AGENDA ITEM N0. [ 4 ]
CHULA VISTA CITY COUNCIL MEETING OF: Apri 1 8, 197 5
ITEM TITLE: Resolution - Granting an Extension of Time to B. E. Wilson
Contracting Corporation for the Albany Avenue
Contract
INITIATED BY: Director of Public Works/City Engineer
uarxrunrtnrn
B. E. Wilson Contracting Corporation, on March 24, 1975, requested a
15 day extension of time to their contract dated February 11, 1975
for the construction of street improvements on Albany Avenue between
Tremont and Main Streets.
The Divison of Engineering has investigated their request and has
determined that the extension of time is justified because the con-
tractor was unable to work on account of rain. The 15 day extension
will extend the contract completion date to May 2, 1975.
ATTACHED: Resolution [X] Ordinance [ ] Agreement [ ] Plat [ ]
See EXHIBITS [ X] No. 1
Financial Statement:
N.A.
Commission-Board Recommendation:
N.A.
Department Head Recommendation:
City Council grant a 15 day extension of time, changing the contract
completion date to May 2, 1975.
City Manager Recommendation: Concur