CITY OF CHULA VISTA ITEM N0.
• - COUNCIL AGENDA STATEMENT ~~ 12/16/75
FOR MEETING OF:
ITEM TITLE: RESOLUTION #7976 : Authorizing Change Order #30 to th
Construction Contract for the Chula Vista Library
SUBMITTED BYE Director of Public Works, City Engineer ~~)
U-
ITEM EXPLANATION
The Director of Building/Housing and the Library Project
Coordinator support the architect`s recommendation that
Change Order #30 to the Chula Vista Library Construction
Contract be approved.
This change order involves the installation of condensate
drains for six air-conditioning units located on the roof o
the library. The drains are an absolute necessity which we e
not included in the library plans due to an oversight by th
architect's mechanical engineer.
Since the mechanical engineer is at fault for not including the
drains, he has agreed to pay the difference in the cost of n-
stallation now and what it would have been prior to the lib ary
construction. This amounts to about 20% of the $2,644 cost
for labor and materials, or $533. An invoice has been sent to
the mechanical engineer in this amount.
The following change orders have been approved thus far:
continued on Supplemental Page
EXHIBITS ATTACHED
Agreement Resolution x Ordinance Plot
Environmental Document: Attached Submitted on
STAFF RECOMMENDATION:
Approve Change Order No. 30.
BOARD/ COMMISSION RECOMMENDATION:
COUNCIL ACTION
APPROVED
b3- the
City Council
of
Chula Vista. California
Two
Form A-113 (Rev 5-75)
C.O. #
Purpose
Supplemental
Amount Item
Page
A~~r 13
Two
ved b
1 Deletion of storm drain cleanouts $(1,010 Res.! 7861
2 Tree removal -0- D W
3 Removal & replacement of unsuitable soil 989 D ~
W
4 Additional demolition 2,713 Res.~ 7861
5 Conduit change (800) D W
6 Upgrade door frames 185 D W
7 Additional sound board 408 D W
8 Reroute waste lines 479 D W
9 Relocate 3" cold water pipe 382 D W
10 Eliminate fire proofing (2,050) Res.' 7919
11 Revise clocks -0- D W
12 Revise floor finish schedule 460 D W
13 Enlarge & fence-in utility pad 5,870 Res. 7935
14 Sliding doors modification 328 D ~
W
15 Change interior walls from gypsum
plaster to gypsum drywall (1,125) Res. 7935
b
16 Strainer in chilled water header 850 D W
17 Colonnade plaster 5,267 Res.~ 7943
18 Tile anchors 557 D W
19 Delete "T" type fixtures (567) D W
20 Door latch sets 64 D pW
21 Extension services-room,ceiling,lighting 2,692 Res.' 7965
22 Steel angles for metal studs 885 D W
23 Steel plates for roof 980 D W
24 Steel roof hips 854 D W
25 Steel angles for roof deck 972 D W
26 Floor sink for condensate 806 D W
27 Additional electrical service 1,678 Res.j 7965
28 Drywall for basement stairs 265 D W
29 Backflow prevention box 551 D W
31 Delete concrete encasement for conduit (300) D W
$22,378
Financial Statement: ~
Appropri ated in account #63-7003-5569 $1,886,470
Original contract cost $1,758,300
Prior ch ange orders 22,378
Proposed Change Order #30 2,664
i
1,783,342
~~~~