ITEM TITLE: Resolution #7921 -Approving Change Order No. 2 for Rosebank Sewer
1911 Act Improvement District 75-1
SUBMITTED BY~ Director of Public Works/City Engineer
ITEM EXPLANATION
On August 8, 1975 a letter was mailed to the property owners within the Rose-
bank Sewer District. The letter outlined two methods that-the owners could
use to have their sewer laterals constructed.
1. The lateral constructed by the Improvement District contractor and
the cost assessed exclusively against their property, or
2. The lateral constructed by the City in accordance with our sewer
lateral ordinance.
The City received 8 responses indicating the property owners desire to have
the contractor construct the sewer lateral and 51 responses indicating the
owners desire to have the City construct the sewer lateral. Of the 8
responses to have the contractor construct the lateral, 3 property owners
cancelled because of the excessive cost and 5 property owners have executed
a contract with the contractor for their lateral construction.
Change Order No. 2 has been prepared to accommodate the 5 property owners
and will increase the contract amount for sewer lateral construction by
$1764. In addition, the City caused the contractor to construct 6 sewer
lateral stub-outs to protrude from the manholes to serve future lateral
construction in the cul-de-sac ends of Casselman Place and Corte Maria Avenue.
The stub-outs cost an additional $20 each for a total of $120.
_. _..._.-_ ____ _..__ (continued on supplemental p.2
C1~r11D1 I J HI I Hl~l"ICU
Agreement Resolution X Ordinance Plat Other
Environmental Document: Attached Submitted on
STAFF RECOMMENDATION:
Approve resolution.
BOARD/ COMMISSION RECOMMENDATION
COUNCIL ACTION
T ~ ~ rl
~-y -u ~..
~z
r_ .,.,~;
7 h .~ c
~:Z V ~' /~r~~NNi•i~iNNIINI/NMIY~
a. r ~,.
y a 4 ~ y-- ---- ---- ---------_..
Form A-113 (Rev 5 - 75)
w
. Item No. 7
.Supplemental page 2
The total increase in the contract amount is $1,884, as shown in Change
Order No. 2. This will change the total contract cost to $108,014.70.
Change Order No. 2 also allows for a 35-day extension of time to allow
for the extra work. The extension of time will change the contract
completion date to November 10, 1975.
~ ~~~