HomeMy WebLinkAboutAgenda Statement 1975/10/14 Item 05• ~ CITY OF CHULA VISTA
COUNCIL AGENDA STATEMENT
ITEM N0. ~' ~ 5
FOR MEETING OF:10 14 75
ITEM TITLE: Resolution #7919 -Approving Change in Contract for .the Chula Vista
City Library
SUBMhTTED BY~ Director of Public Works/City Engineer J_)
ITEM EXPLANATION
The Director of Building and Housing supports an architect's recommendation
that a draft stop be installed in the attic area of the new library. The
draft stop will effectively seal off the attic area, thereby eliminating the
necessity to fireproof the attic beams and columns. The net cost reduction
for the draft stop installation and the elimination of the Monokote fire-
proofing of the beams and columns is $2,050. Proposed Change Order #10
covers the above items of work.
In addition to the proposed Change Order #10, the following change orders
have been approved for library construction thus far:
C.O. #
1
2
3
4
5
6
7
8
9
11
12
Approved
Purpose by
Deletion of storm drain cleanouts ($1,010) Res. 7861
Tree removal -0- DPW
Removal & replacement of unsuitable soil $989 "
Additional demolition $2,713 Res. 7861
Conduit change ($800) DPW
Upgrade door frames $185 "
Additional sound board $408 "
Reroute waste lines $479 "
Relocate 3" cold water pipe $382 "
Revise clocks -0- "
Revise floor finish schedule $460 "
EXHIBITS ATTACHED -
Agreement Resolution X Ordinance Plot Other
Environmental Document; Attached Submitted on
STAFF RECOMMENDATION:
Approve Change Order #10 for the Chula Vista City Library.
BOARD/ COMMISSION RECOMMENDATION
A P P R O V D D
by the
City Council
COUNCIL ACTION ~f
Chula Vista, California
D ~y
ut e 3 _ ... ~~...........1......'.../ .....................~.
Amount
Form A-113 (Rev 5-75)
Agenda Item No. 5
Supplemental page 2
Financial Statement:
Appropriated in Account #63-7003-5569
Original contract cost
Prior change orders
This change order request
New contract amount
$1,886,470
$1,758,300
3,806
(2,050)
$1,760,056
79/~