HomeMy WebLinkAboutAgenda Statement 1975/05/13 Item 09AGENDA ITEM N0. [ g ]
CHULA VISTA CITY COUNCIL MEETING OF: May 13, 1975
ITEM TITLE: Resolution - Granting an Additional Extension of Time -
Albany Avenue Improvements Between Tremont
and Main Streets /~_~//~
INITIATED BY: Director of Public Works/City Engineer ~_ ).'~i
BACKGROUND: R/ ddd
B. E. Wilson Contracting Corporation requested on April 22, 1975 a
sixteen day extension of time due to severe weather conditions. The
contract completion date is May 2, 1975.
The Engineering Division has reviewed their request and has determined
that a sixteen day extension because of inclement weather is justified.
In addition, five days were lost because of a delay in the job pending
a meeting held between City staff, the School District, Architect and
Engineer of Work to consider a change in design of the storm drain
facilities on the school property and City right of way. The
Engineering Division recommends a twenty-one day extension of time.
The twenty-one day extension of time, if granted, will extend the
contract completion date to May 23, 1975•
ATTACHED: Resolution [X] Ordinance [ ] Agreement [ ] Plat [ ]
See EXHIBITS [x] No. 1
Financial Statement:
N.A.
Commission-Board Recommendation:
N.A.
Department head Recommendation:
City Council approve a twenty-one day extension of time changing
the contract completion date to May 23, 1975•
City Manager Recommendation:
Concur
-`7~