HomeMy WebLinkAboutAgenda Statement 1975/04/15 Item 09AGENDA ITEM N0. [ g ]
CHULA VISTA CITY COUNCIL MEETING OF: April 15, 1975
ITEM TITLE: Resolution - Accepting Bids and Awarding Contract for the
Construction of a Multiple Use Court in Connoley
Park in the City of Chula Vista
INITIATED BY: Director of Public Works/City Engineer ~~
BACKGROUND:
The Director of Public Works received formal bids on Thursday, April 3,
1975 at 11:00 A.M. in the Council Chambers for the "Construction of a
Multiple Use Court in Connoley Park." Bids were submitted by four
contractors as follows:
Trepte Brothers, San Diego $3509
T. B. Penick & Sons, San Diego $3556
Patrick J. Timmins, Del Mar $5329
Sapper Construction, San Diego $5549
The low bidder is Trepte Brothers with a bid of $3509. The engineer's
estimate for the project was $2650. The low bid is 32% above the
engineer's estimate. After reviewing the bids and the project, it was
determined that the low bid was not unreasonably high. Due to the small
size of the job, unit prices are much higher than the prices currently
being bid for larger jobs.
ATTACHED: Resolution [X] Ordinance
Financial Statement
Low Bid $3,509
Contingencies 351
Total Project Cost ~$~0
Funds in Account 61-7001-PD-2-74
~~}n~~sio~~oar~~ecofinme€nd~t~ ox~~ct cost $11~; 0945
N.A.
Agreement [ ] Plat [ ]
See EXHIBITS [X] No. 1
Department Head Recommendation:
1. City Council accept bids and award contract to Trepte Brothers in the
amount of $3509.
2. Council authorize the expenditure of $3860 from account 61-7001-PD-2-7~
for the construction of the Connoley Park Multiple Use Court.
City Manager Recommendation:
Concur
~~ ~~03