HomeMy WebLinkAboutReso 1975-7794RESOLUTION NO. 7794
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
CHULA VISTA APPROVING AND ADOPTING UNIFORM
BUILDING VALUATIONS
The City Council of the City of Chula Vista does hereby
resolve as follows:
WHEREAS, the City Council has adopted Resolution No. 5656
endorsing the principle of uniform standards for building regulations
throughout San Diego County, and
WHEREAS, the existing building valuations as set forth
in City Council Resolution No. 7041 are not uniform with the val-
uations proposed by the San Diego Area Chapter of the International
Conference of Building Officials.
NOW, THEREFORE, BE IT RESOLVED by the City Council of
the City of Chula Vista that Resolution No. 7041 be, and the same
is hereby rescinded.
BE IT FURTHER RESOLVED that the City Council of the
City of Chula Vista does hereby approve and adopt the Schedule of
Average Building Valuations, marked Exhibit "A", attached hereto
and incorporated herein by reference as if set forth in full.
Presented by Approved as to form by
~,~ ~~~~°
..
e'Gra , Direc of Georges Lindberg, City Attor
ilding and Hoyr~ing
ADOPTED AND APPROVED by the CITY COUNCIL of the CITY OF
CHULA VISTA, CALIFORNIA, this i~r day of ,July , 1975, by
the following vote, to-wit:
AYES: Councilmen Hobel, Hamilton, Scott
NAYES: Councilmen None
ABSENT: Councilmen
ATTES „ ~ ~
City Clerk
STATE OF CALIFORNIA)
COUNTY OF SAN DIEGO) ss.
CITY OF CHULA VISTA)
I, , City
Chula Vista, California, DO HEREBY CERTIFY that
true and correct copy of Resolution No. ,
has not been amended or repealed. DATED
Mayor o£ the City of Chula Vista
Clerk of the City of
the above is a full,
and that the same
City Clerk
SCHEDULE OF AVERAGE BUILDING VALUATIONS
OCCUPANCY I ~ II III IV V
St eel or Concrete Masonry Walls Steel Wood Frame
Floors G Walls Wood Floors b
Interior Walls
Dwellings 24.30 22.60
Basements in Dwellings
Finished 5.80
Unfinished 4.50
Apartments 31.50 24.50 21.70
Hotels E Motels 36.00 30.00 27.00
Private Garages 9.70 7.40
Subterranean 13.60 9.70
Hospitals 56.00 53.70 45.60
Convalescent 40.30 37.20 33.20
Schools, Churches,
Auditoriums, Theaters 37.60 30.60 26.90
Stores 6 Comm'1 Bldgs. 30.40 22.20 20.00
Office Bldgs. 39.10 28.00 23.00
Restaurants 35.20 33.00 29.70
Industrial Buildings b
Warehouses 17.60 13.00 12.30 10.10
Tilt-Up 10.25
Stock Type IV 11.65
Service Stations 30.00 28.00 18.90
Canopies 9.60
Public Garages 18.30 15.30 13.10 13.10
Private Garages 9.70 7.40
SPRINKLER SYSTEM - Add $.85 per square foot of area sprinklered.
AIR CONDITIONING - Commercial - Add $2.00 per square foot of floor area.
Residential - Add $1.80 per square foot of floor area.
TRACT DWELLINGS - More than 10 units - Reduce valuation by 10~ each unit when 10 or
more permits are taken out at one time.
-1-
7794
MULTI-STORY BUILDINGS - Determine the valuation from the sum of the floor area of all
stories.
PILE FOUNDATIONS - Increase the valuation by $5.00 per lineal foot of pile for cast-in-
place concrete piles and $12.50 per lineal foot of pile for steel and pre-cast concrete
piles.
Apply other dwelling cost modifier as follows: fireplace $625.00; forced-air heat $625.00;
wood shingles or wood shakes, 60~ per square foot; the roof 70t per square foot; extra
plumbing, $250.00 per fixture for more than six bathroom fixtures.
VALUATION FOR ADDITIONS TO EXISTING RESIDENCES (TYPE
Instructions: (1) Determine floor area for valuation as a product of exterior
dimensions.
(2) Determine appropriate basic cost/sq. ft. from table below.
(3) Compute basic valuation as product of cost/sq. ft. and floor area.
(4) Add applicable costs for proposed work in excess of basic
structure valuation (see list below table).
No. of Walls 2 Exterior Walls 3 Exterior Walls
Floor Conc. Slab Wood Frame Conc. Slab Wood Frame
Roof on grade & Cont. Fnd. on grade ~ Cont. Fnd.
Shed or Combination
Deck with Ceiling 12.00 13.00 13.00 14.00
Gable or Hip to
match existing 13.00 14.00 14.00 15.00
CHARGES TO BE ADDED TO SQUARE FOOT VALUATIONS:
Kitchens - add $7.00 per sq. ft. for kitchen area only.
Bathrooms - add $1.40 per sq. ft. for bathroom area only.
Interior Partitions - $12.00 per lineal ft.
Plumbing Fixtures - add $250.00 per fixture.
ALTERATIONS TO EXISTING STRUCTURE (no additional floor area or roof cover)
Enclose porch, sunshade, garage conversion, etc. - difference in valuation per sq. ft.
between existing and new occupancy.
Interior Partitions - $12.00 per lineal foot.
Install windows or sliding glass doors - $4.00 per sq. ft. of opening.
Close exterior wall openings - $3.50 per sq. ft. of opening.
MISCELLANEOUS
(I) Plastering: (4) RETAINING WALLS
Inside .65 sq. ft. Concrete or Masonry 2.50 sq. ft.
Outside .75 sq. ft.
(5) SWIMMING POOLS
(2) Roofing: 9.30 per sq. ft. of area of
Built up 33.25 per square pool surface
Comp. Shingles 34.00 per square
Abs. Shingles 75.00 per square (6) ALUMINUM SIDING 1.10 sq. ft.
Wood Shingles 65.00 per square
Wood Shakes 67.50 per square
Alum.Shakes 110.00 per square (7) AWNINGS & CANOPIES
Clay Tile 96.00 per square Aluminum 5.00 sq. ft.
Conc. Tile 82.00 per square Canvas 2.00 sq. ft.
(3) FENCES AND WALLS: (8) PATIOS & CARPORTS
Wood .60 sq. ft. Alum. frame 2.50 sq. ft.
Wire .50 sq. ft. Wood frame 2.00 sq. ft.
Masonry 2.00 sq. ft. Masonry Walls 1.90 sq. ft.
Screen .80 sq. ft.
SIGNS AND BILLBOARDS
NON-ILLUMINATED ILLUMINATED
ROOF 1 Face 7.50 per sq. ft. 12.50 per sq. ft.
2 Face 11.00 per sq. ft. 17.50 per sq. ft.
WALL 1 Face 5.00 per sq. ft. 11.00 per sq. ft.
PROJECTING
1 Face 7.50 per sq. ft. 15.00 per sq. ft.
2 Face 10.00 per sq. ft. 17.50 per sq. ft.
POLE Same as roof, plus supporting structure
1 Face - $5.00 per sq. ft.
plus supporting structure
2 Face - $9.00 per sq. ft.