RESOLUTION NO. 13411
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CHULA
VISTA APPROVING AGREEMENT BETWEEN THE CITY OF CHULA
VISTA AND P&D TECHNOLOGIES TO PREPARE THE GENERAL PLAN
UPDATE , APPROPRIATING FUNDS
AND AUTHORIZING THE MAYOR TO EXECUTE SAID AGREEMENT
The City Council of the City of Chula Vista does hereby
resolve as follows:
NOW, THEREFORE, BE IT RESOLVED by the City Council of
the City of Chula Vista that that certain agreement between THE
CITY OF CHULA VISTA, a municipal corporation, and P&D TECHNOLOGIES
to prepare the General Plan Update
dated the 12th day of January , 1988, a copy of which is
attached hereto and incorporated herein, the same as though fully
set forth herein be, and the same is hereby approved.
BE IT FURTHER RESOLVED that the sum of $44,486 be, and
the same is hereby appropriated from the unallocated reserve
of the General Fund for said services.
BE IT FURTHER RESOLVED that the Mayor of the City of
Chula Vista be, and he is hereby authorized and directed to
execute said agreement for and on behalf of the City of Chula
Vista.
Presented by Approved s to form by
e~rge Krem/~,~Di~e~tor of ~
Planning
0374a
ADOPTED AND APPROVED BY THE CITY COUNCIL OF THE CITY OF
JLA VISTA, CALIFORNIA, this 12th d(~J of January
19 88 , by the following vote. to-wit:
AYES: Councilmembers ivialcolm, Coy., i~looz'e, l~ade~:
NAYES: Councilmembers ~one
ABSTAIN: Councilmembers ~one
ivIcCandl~_ss
ABSENT: Counci 1 members
~ 'City of Chula Vista
,TE OF CALIFORNIA )
COUNTY OF SAN DIEGO ) ss.
CITY OF CHULA VISTA )
I, JENNIE M. FULASZ, CMC, CITY CLERK of the City of Chula Vista, California,
DO HEREBY CERTIFY that the above and foregoing is o full, true and correct copy of
RESOLUT[0N N0. 13411 ,and that the some has not been amended or repealed
DATED
City Clerk
Cl'h' OF
CHULA VISTA
CC-660
THIRD AMENDMENT TO THE AGREEMENT BETWEEN
THE CITY OF CHULA VISTA AND P&D TECHNOLOGIES
(FORMERLY PRC ENGINEERING~ INC.) FOR GENERAL PLAN UPDATE SERVICES
WHEREAS, the City of Chula Vista is in need of additional professional
planning services to assist in carrying out an expanded scope of work for
central Chula Vista, General Planning Area Buildout Data, Eastern Territory
Scenario and preparation of exhibits, data, and summaries, as well as the
ongoing coordination of the General Plan Update with City staff and other
consulting firms; and
WHEREAS, the firm of P&D Technologies (formerly PRC Engineering, Inc.)
estimates a total cost of $44,486 will adequately cover this additional work;
and
NOW, THEREFORE, BE IT RESOLVED that the City of Chula Vista and P&D
Technologies (formerly PRC Engineering, Inc.), a consulting firm, do hereby
mutually agree as follows:
Section 1. Section VII of the agreement dated July 14, 1987, entitled
COMPENSATION is amended to read as follows:
The compensation to be paid by CITY to CONSULTANT shall be on a fixed
fee basis in the amount of TWO HUNDRED EIGHTY-FIVE THOUSAND ONE
HUNDRED THIRTY-SIX DOLLARS ($285,136) in accordance with ATTACHMENT
"B", Schedule of Fees, which shall be used by the City in determining
the amount of work completed by CONSULTANT and, therefore, the
percentage of completion to be paid by CITY to CONSULTANT each month
for work program elements completed. Work program elements shall be
completed by CONSULTANT to the satisfaction of the Director of
Planning and in accordance with the Work Program and Project
Schedule, (ATTACHMENT "A" ). CITY agrees to pay the total sum
invoiced and approved by the Director of Planning each month during
the duration of this agreement; and
Section 2. ATTACHMENT "B" entitled Schedule of Fees to said agreement is
amended as attached.
IN WITNESS WHEREOF, CITY and CONSULTANT has executed this Third Amendment
to the Contract for Planning Services (agreement) this 12th day of January,
1988.
B y: · B y:
Gregory R.(/~.o~., Mayor ~ ~in(s Baak
City of Chula Vista Division Senior Vice President
Regional Manager
P&D Technologies
WPC 4679P
CHULA VISTA GENERAL PLAN
ATTACHMENT B
SCHEDULE OF FEES
(Supplementary Information)
Research and Analysis of General Plan
Policies and Programs $36,800
Project Manager 200 hrs
Deputy Project Manager 220 hrs
Graphics Coordinator 100 hrs
Word Processor 40 hrs
Conduct Baseline Studies $16,800
Project Manager 50 hrs
Deputy Project Manager 70 hrs
Assistant Planner 40 hrs
Graphics Coordinator 40 hrs ~
Graphic Artist 160 hrs
Conduct Economic/Fiscal Impact Analysis $47,100
Project Manager lO hrs
Deputy Project Manager lO hrs
Principal Economic Analyst 300 hrs
Senior Economic Analyst 270 hrs
Technical Analyst 200 hrs
Generalized City-Wide Community Design Element $15,156
Project Manager 20 hrs
Principal Planner 179 hrs
Graphic Artist 100 hrs
Central Chula Vista Land Use Plan $37,270
Project Manager 70 hrs
Deputy Project Manager 10 hrs
Principal Planner 165 hrs
Senior Planner 230 hrs
Graphic Artist 80 hrs
Word Processor 20 hrs
Eastern Territories Land Use and Open Space Plan $46,753
Project Manager llO hrs
Deputy Project Manager 80 hrs
Principal Planner 435 hrs
Graphic Artist 80 hrs
Word Processor 20 hrs
-1-
Sweetwater Precise Plan (Coordination with $2,800
General Plan)
Project Manager 20 hrs
Deputy Project Manager 20 hrs
Montgomery Plan (Coordination with General Plan) $2,800
Project Manager 20 hrs
Deputy Project Manger 20 hrs
Master EIR $18,914
Project Manager 10 hrs
Deputy Project Manager 60 hrs
Technical Analyst 310 hrs
Graphic Artist 60 hrs
Word Processor 60 hrs
General Plan Reformatting and Report Preparation $45,695
Project Manager 100 hrs
Deputy Project Manager 150 hrs
Technical Analyst 200 hrs
Graphics Coordinator 60 hrs
Graphic Artist 300 hrs
Word Processor 200 hrs
, Additional Meetings 116 hrs $9,818
Direct Costs (Including the following) $9,230
Display Graphic Mylars
Opportunities & Constraints (Eastern Territories)
General Plan Map with overlays
Regional Map
Eastern Territories and Central Chula Vista Plan maps
33 mm slides for use in presentation of all
graphics completed for reports
Blueprints and blackline prints (in-house use)
Reproduction of a maximum of 15 copies of each of the interim reports
Travel
TOTAL $285,136
On camera ready copy of the General Plan, EIR, Eastern Territories and Central
Chula Vista Plans will be provided. It is assumed that volume reproduction of
these documents will be done by the City or if done by PRC, will be billed on
a cost plus basis. One rendered and mounted plan map each for the General
Plan, Eastern Territories, and Central Chula Vista plans will be provided.
One rendered and mounted display illustrating opportunities and constraints
for the Eastern Territories study area will also be provided.
-2-
LABOR HOURS SUMMARY
Project Manager 688
Deputy Project Manager 698
Principal Planner 779
Senior Planner 230
Assistant Planner 40
Principal Economic Analyst 300
Senior Economic Analyst 270
Technical Analyst 710
Graphics Coordinator 200
Graphic Artist 780
Word Processor 340
5,035