HomeMy WebLinkAboutReso 1975-7816RESOLUTIOld NO. 7816
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CHULA
VISTA GRANTING AN EXTENSION OF TIME TO R. E. HAZARD
CONTRACTING COMPANY FOR THE IMPROVEMENT OF EAST "H"
STREET BETWEEN HILLTOP DRIVE AND I-805 FREEWAY -
GAS TAX PROJECT #;126
The City Council of the City of Chula Vista does hereby
resolve as follows:
4d1IEREAS, R. E. Hazard Contracting Company, by their
letter dated July 7, 1975, has requested a twenty-two day exten-
sion of time to their contract for the improvement of East "H"
Street between Hilltop Drive and I-805 Freeway because of addi-
tional work created by change orders, and
WHEREAS, on June 10, 1975, by Resolution Pdo. 7771, the
City Council granted a twenty-four day extension which made the
contract completion date July 10, 1975 and the Division of Engi-
neering has reviewed the request for an extension of time and has
determined that a seven-day extension is justified.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the
City of Chula Vista that the time for completion of said project be,
and the same is hereby extended to and until July 17, 1975.
Presented by
Gv . /~r~~
William J. obens, Director
of Public Works
Approved as to £orm by
! ~.' ~ i
ii
Georgd' D. Lindberg, City Attca'rfiey
ADOPTED AND APPROVED by the CITY COUNCIL of the CITY OF CHULA
VISTA, CALIFORNIA, this 15th day of Julv , 197, by
the following vote, to-wilt:
AYES: Councilmen Hyde, Scott, Hamilton
NAYES: Councilmen None
ABSENT: Councilmen Hobel, Egdahl
,_y . ~
1 ~ Mayor of the City of Chula Vista
ATTES i ~ l ~ ~~~
City Jerk
STATE OF CALIFORNIA )
COUNTY OF SAN DIEGO ) ss.
CITY OF CHULA VISTA )
I, , City Clerk of the City of
Chula Vista, California, DO HEREBY CERTIFY that the above is a full,
true and correct copy o£ Resolution No. and that the same has
not been amended or repealed. DATED .
City Clerk